NAVFAC IC - PWS - Sources Sought Synopsis.pdf
PDF 440 KB Posted
- Solicitation number
- N3943026NIBS
About this file
Performance Work Statement Summary
This is a Performance Work Statement (PWS) dated October 29, 2025, for the Naval Facilities Engineering Systems Command (NAVFAC) to develop criteria, standards, tools, and planning documentation supporting Industrialized Construction (IC) implementation across Navy facilities. The contract is a 24-month task order with potential government extension. The contractor must deliver comprehensive documentation and tools across ten major task areas: (1) Standards, Codes & Compliance; (2) IC Strategy, Justification & Sustainment; (3) Policy, Contracting & Acquisition Reform; (4) Architectural/Engineering Platform & Digital Integration; (5) Prototypes, Pilots & Research; (6) IC Transition Management, Training & Workforce Development; (7) IC Industrial Base Ecosystem Development; (8) Portfolio Management, Offsite & Onsite Logistics; (9) IC Program Governance; and (10) Scaling across DoD branches.
The work is structured around five major milestones spanning the 24-month period: Program Charter & Alignment (Month 3), Frameworks, Designs and Data Foundations (Month 8), Prototyping and Testing (Month 12), Pilots Implemented and Feedback Documented (Month 18), and Systems and Processes Standardized (Month 24). Deliverables include design standards, economic models, life cycle cost analyses, BIM tools, vendor databases, training materials, policy recommendations, logistics frameworks, and IC component libraries. The contractor must participate in kickoff meetings, bi-weekly progress meetings, and monthly planning charrettes with NAVFAC stakeholders. Travel to DoD installations is required with COR approval. All work requires compliance with security requirements including Tier 1 Personnel Security Investigation for CUI access, DoD 5200.01 information security protocols, and mandatory annual CUI training. The contractor shall submit personnel lists 14 days after award and report personnel changes within 48 business hours. All CUI documentation must be delivered to NAVFAC EXWC upon contract completion. Deliverables are submitted to Frank Fernandez in digital formats (PDF, Word, Excel, databases, BIM files, and dashboards as appropriate).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SSS - Capabilities Questionnaire for Interested Parties.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
FOR
THE NAVY FACILITIES ENGINEERING
SYSTEMS COMMAND (NAVFAC)
Criteria, Standards, Tools, and
Planning Documentation to Support
Industrialized Construction (IC)
October, 29, 2025
AE SERVICES PERFORMANCE WORK STATEMENT
Project Title/Location: Criteria, Standards, Tools, and Planning Documentation to Support
Industrialized Construction (IC)
Type of Product: Documentation: Criteria, Standards, Tools, and Planning
References:
(a) DoDM 8400.01, “Accessibility of Information and Communications
Technology (ICT).” 12 March 2025.
(b) MIL-STD-3007, “Unified Facilities Criteria, Facilities Criteria, and Unified
Facilities Guide Specifications.” 1 November 2019.
1. INTRODUCTION AND BACKGROUND INFORMATION
The Naval Facilities Engineering Systems Command (NAVFAC) is leading the effort to modernize shore infrastructure and facilities using innovative building techniques.
The primary objective of this project is to develop documentation that results in updates to building criteria, standards, and requirements; updates to governing policy; and the development of related tools and techniques to enable a clear path to establishing Industrialized Construction as a functional capability for the U.S. Navy.
This scope of work builds on NAVFAC's ongoing Alternative Construction Method (ACM) efforts to think, act, and operate differently, including the adoption of new and innovative solutions to reduce project construction costs and increase the speed of delivering mission-ready facilities.
2. PROJECT SCOPE
To meet the objective, the following work will be provided by a contractor:
● Standards, Code, Compliance - Align current DoD and IC best practices related to codes/standards, develop IC-based guidelines, and ensure compliance through real-time tracking and commissioning protocols that reduce cost, reduce risk, improve quality, and support long-term asset performance.
● Industrialized Construction (IC), Strategy, Justification, Sustainment - Develop and communicate the business case and strategic implementation for IC as a sound, sustainable investment for DoD at all levels of NAVFAC, DoD, and relevant operational commands.
IC/ACM may include, but is not limited to, modular components, off-site prefabricated industrial construction, tension fabric structures, and pre-engineered metal or fiber reinforced panel buildings.
● Policy, Contracting & Acquisition Reform - Review and provide practical policy (and regulation) reforms that streamline procurement, acquisition/contracting, incentivize project performance, and integrate IC early into the budgeting and RFP frameworks
● Architectural/Engineering Platform & Digital Integration - A shared platform where a standardized kit of components, BIM workflows, and digital twins converge to provide design consistency, improve as-built accuracy, and general deployment efficiency.
● IC (ACM) Prototypes, Pilot Projects & Research - Rapid prototyping, project pilots, and research to inform and refine IC designs, engineering, construction, and operations.
These efforts serve as proof points to accelerate adoption and long-term IC scaling in
NAVFAC and to other branches.
● IC (ACM) Transition Mgmt, Training & Workforce Development - Comprehensive transition plans for system-wide engagement (Navy/Marine/etc. and Private) to solicit early input, generate near-term buy-in (traction), build partnerships, and teach the skills needed for long-term IC adoption that achieves the improved cost, speed, and performance set out by DoD leadership.
● IC Industrial Base Ecosystem Development - Industrialized construction requires a strong, portfolio-wide program that starts by shifting from a “project” to a “product” approach, and pairs with a robust IC private sector industrial base whose core strength is manufacturing and assembly (as opposed to onsite construction). Emphasis is placed on establishing and incentivizing a tiered industrial base, similar to the automotive industry, where Tier 3 output feeds Tier 2, which then feeds Tier 1 IC actors, thereby achieving system-wide interoperability, redundancy, and efficiency.
● Portfolio Mgmt, Offsite & Onsite Logistics - To unlock the benefits of IC at scale, NAVFAC needs portfolio-wide visibility and streamlined logistics practices. This section provides a framework for integrated scheduling, comparative milestone tracking, and standardized delivery protocols. These tools ensure faster project execution, improved oversight, and consistent performance across offsite and onsite phases.
● IC Program Governance - Establishing clear IC implementation KPIs that align with leadership objectives and timelines. This includes both near- and long-term roles and responsibilities for the implementation and sustainment team(s), as well as establishing a multi-year funding structure and commitment.
● IC Scaling - Institutionalize IC as a core NAFVAC capability by embedding IC-based principles into a scalable program (products, processes, and teams) that NAVFAC can apply across its portfolio (geographic and building typologies), and then extend it to its peer military branch partners (AFCEC, USACE, etc.).
3. RESERVED
4. PROJECT TASKS
4.1 Task 1: Standards & Codes & Compliance
4.1.1 Establish IC solicitation criteria and vendor evaluation tools
4.1.2 Create Building Information Modelling (BIM) and IC design standards alignment tools
4.1.3 Develop standardized IC component commissioning checklists
4.1.4 Create standards and systems for construction and occupancy data tracking
4.1.5 Create a UFC code-aligned resilience adaptation assessment tool
4.2 Task 2: Industrialized Construction (IC), Strategy, Justification, Sustainment
4.2.1 Create an Economic model to compare conventional to industrialized construction.
4.2.2 Perform Life Cycle Cost Analysis (LCCA) for initial IC barrack design (then add'l typologies)
4.2.3 Develop an IC component budgetary cost guidance catalog
4.2.4 Create an IC performance dashboard and provide support to NAVFAC leadership
(Ad Hoc support, KPIs)
4.2.5 Prepare a summary IC business case for DoD leadership
4.3 Task 3: Policy, Contracting & Acquisition Reform
4.3.1 Prepare IC ‘policy updates’ recommendations and executive briefing documents
4.3.2 Review existing agreements and draft updated IC vendor contracts
4.3.3 Develop procurement and financing tools for ACM/IC projects
4.4 Task 4: AE Platform, Tool & Digital Integration
4.4.1 Deliver IC-based architecture and engineering support for priority projects (Barracks and CDCs)
4.4.2 Build design decision-making and configurator toolset
4.4.3 Compile an Open-Sourced Library of Standard Components
4.4.4 Build an IC digital deployment roadmap with cybersecurity and integration overlays
4.5 Task 5: Prototypes, Pilots & Research
4.5.1 Build an IC barrack wall and a volumetric room mockup
4.5.2 Deliver documentation and outcome reporting for IC pilots
4.5.3 Conduct IC research and technology roadmap development for NAVFAC
4.6 Task 6: IC Transition Mgmt, Training, & Workforce Development
4.6.1 Conduct collaborative planning charrettes with NAVFAC and IC vendors (as needed)
4.6.2 Develop an IC adoption change management playbook and training plan
4.6.3 Deliver IC training sessions and an educational materials package
4.6.4 Develop an IC competency framework and readiness assessment tools
4.7 Task 7: IC Industrial Base Ecosystem Development
4.7.1 Perform vendor assessments and build an IC vendor database
4.7.2 Build partnership mechanisms to strengthen IC vendor collaboration
4.8 Task 8: Portfolio Mgmt, Offsite & Onsite Logistics
4.8.1 Build a portfolio-wide dynamic scheduling and resource management framework
4.8.2 Evaluate the NAVFAC project portfolio with IC timelines and scenarios
4.8.3 Build standardized ad-hoc project evaluation templates
4.8.4 Create IC logistics procedures, inspections, and management systems
4.9 Task 9: IC Program Governance
4.9.1 Create an IC implementation authority structure and funding plan
4.9.2 Create IC oversight procedures and an annual reporting process
4.10 Task 10: Scaling (NAVFAC --> Others)
4.10.1 Build a strategic plan for IC growth across facilities and agencies
4.10.2 Publish IC documentation highlighting benefits, proof points, and best practices
5. REQUIRED MEETINGS
● Kickoff meeting: The Subcontractor will participate in a kickoff meeting approximately two weeks after Subcontract execution.
● Weekly meetings: The Subcontractor shall participate in bi-weekly meetings with the
Navy. The meeting framework will include, but not be limited to: project, barriers and risks identified, and next steps.
● Project planning charrettes (as needed, planning for monthly) w/ NAVFAC stakeholders.
6. TRAVEL
The Contractor will be required to travel. All travel requires Government approval/authorization and notification to the COR. Travel to various DoD installations and/or Contractor facilities may be necessary to accomplish the contract successfully. All Contractor travel shall be approved in advance by the COR. The Contractor shall be reimbursed for required travel in accordance with the Joint Travel Regulation (JTR) guidelines.
7. MILESTONES AND DELIVERABLES
7.1 The total duration of this task order is 24 months. If needed to fill program goals, the government may extend the period of performance end date.
7.2 The work will be divided into major milestones:
Milestone Description Key Characteristics
Month s
From
Contr act
Awar d
M
Program
Charter &
Alignment
Shared IC program vision, governance, and baseline objectives across all capability domains.
● Charter affirmed
● Roles and governance defined
● Common lexicon established
● Leadership alignment workshop completed 3
M
Frameworks, Designs and
Data
Foundations
Set
Foundational frameworks created to enable structured evaluation of IC options objectively
● Baseline Design Standards and Schematic
Concepts created for Barracks and CDCs,
● Economic Model architecture built, LCCA framework developed and populated with baseline datasets,
● Preliminary IC schedule templates created and logistics assumptions defined
● Supplier capability database established;
current national capacity mapping developed.
● Draft IC RFP templates and vendor evaluation checklist developed
M
Prototyping and Testing
Complete
Early concepts translated into tangible prototypes and digital test environments.
● Wall and room prototypes fabricated and tested for UFC compatibility and logistics
● Data schema and parameters for configurable IC components defined.
Digital prototypes modeled for manufacturing
● Selected suppliers from NAVFAC network conduct prototype builds; QA metrics validated.
M
Pilots
Implemented and Feedback
Documented
IC is applied to a limited number of pilot projects to generate real-world evidence.
● IC-based solicitations released for Pilot projects; feedback collected.
● 1-5 Pilot barracks and CDCs delivered via
IC methods; field data captured.
● Cost Models and Schedule Templates tested w/ Pilot projects; Data from
Barracks and CDC Pilot Projects integrated; sensitivity analyses refined.
M
Systems and
Processes standardized and Integrated with existing
NAVFAC
workflows
Validated tools and processes are codified into repeatable
NAVFAC
standards.
● Barracks and CDC IC design kit, cost tables, and commissioning checklists finalized.
● Full IC Component Library launched for
Barracks and CDCs with DfMA configurability and UFC Change
● Economic Model and Schedule templates standardized across NAVFAC building typologies
● Supplier qualification and QA criteria standardized.
● IC procurement templates and vendor evaluation models finalized.
7.3 Each phase consists of pre-defined deliverables to accomplish the performance objectives outlined in Section 7. Each deliverable will be provided in alignment with the project schedule. Deliverables include:
Ref Deliverable Frequen cy /
Count
Medium/Format Submit To
4.1.1 IC solicitation criteria and
vendor evaluation toolset update
4 Digital format (PDF and
Word document)
Frank Fernandez
4.1.1 IC focused updates to
existing RFPs and creation of templates
2 Digital format (PDF and
Word document)
Frank Fernandez
4.1.2 BIM alignment strategy, templates, and QA toolkit
update
8 Digital format (PDF and
Word document, excel)
Frank Fernandez
4.1.2 NAVFAC IC BIM Data
Repository update
8 Digital format (PDF and
Word document, excel, database files, .rvt, configured NAVFAC data environments)
Frank Fernandez
4.1.3 Standardized IC
component commissioning checklist set
1 Digital format (PDF and
Word document, excel)
Frank Fernandez
4.1.4 Protocols for Data
Collection During and Post
Construction Set
2 Digital format (PDF and
Word document)
Frank Fernandez
4.1.5 UFC-aligned resilience
adaptation assessment toolkit update
3 Digital format (PDF and
Word document, excel, database files)
Frank Fernandez
4.2.1 Updates to conventional vs
IC cost model and ad-hoc estimating
6 Digital format (PDF and
Word document, excel, database files, configured
NAVFAC data environments)
Frank Fernandez
4.2.2 Life Cycle Cost Analysis
(LCCA)
5 Digital format (PDF and
Word document, excel, database files)
Frank Fernandez
4.2.3 IC Components Budget
Cost Dataset Update
3 Digital format (PDF and
Word document, excel, database files)
Frank Fernandez
4.2.4 IC Performance Tracking
and Reporting Toolkit V1-
V3
3 Digital format (PDF and
Word document, excel, database files, dashboards)
Frank Fernandez
4.2.4 IC Staffing ROI Analysis
Memo
1 Digital format (PDF and
Word document, excel)
Frank Fernandez
4.2.4 Senior leader brief
packages
4 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.2.5 IC Business Case Comms
Package Updates
8 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.3.1 IC Policy Change
Recommendations
Packages
6 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.3.2 Standard Contracting
Document Updates
3 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.3.3 Procurement Toolkit
Prototype
1 Digital format (PDF and
Word document, dashboard)
Frank Fernandez
4.4.1 IC Concept Design
Documents for CDC and
Barracks
6 Digital format (PDF, .dwg or .rvt)
Frank Fernandez
4.4.1 Rendering Packages 2 Digital format (PDF, PPT
and JPEG)
Frank Fernandez
4.4.1 Barracks and CDC Design
Standard Document
Updates
4 Digital format (PDF and
Word document)
Frank Fernandez
4.4.1 IC Extensibility Status
Memo
1 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.4.2 Build Design Decision-
Making Toolkit Updates
3 Digital format (PDF and
Word document, ppt, database files, dashboard)
Frank Fernandez
4.4.3 Standard Components
Library Ecosystem - V1-
V3
3 Digital format (PDF, PPT and JPEG)
Frank Fernandez
4.4.4 Deployment Roadmap -
BIM Update
1 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.5.1 IC Barrack Mockups 2 Physical Structure &
Digital formats as needed
(PDF and Word document, ppt)
Frank Fernandez
4.5.2 IC Pilot Project Summary
Report
1 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.5.3 IC Tech. Deployment
Roadmap
1 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.6.1 Planning Charrettes 3 Dialogue & Digital
format (PDF and Word document, ppt)
Frank Fernandez
4.6.2 IC Change Management
Playbook Update
3 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.6.2 IC Training Plan Updates 2 Digital format (PDF and
Word document, ppt)
Frank Fernandez
4.6.3 Education Content
Updates
2 Digital format (PDF and
Word document, ppt, database files)
4.6.3 Training Sessions (4 hour) 3 Dialogue & Digital
format (PDF and Word document, ppt)
Frank Fernandez
4.6.4 IC Competency
Framework
1 Digital format (PDF and
Word document, ppt, database files)
Frank Fernandez
4.6.4 IC Readiness Assessment
Tool
1 Digital format (PDF and
Word document, ppt, database files)
Frank Fernandez
4.7.1 IC Vendor Database - V1-
V2
2 Digital format (PDF, excel and Word document)
Frank Fernandez
4.7.1 IC Vendor Assessments 2 Digital format (PDF, excel and Word document)
Frank Fernandez
4.7.2 IC Vendor Partnership
Framework
1 Digital format (PDF and
Word document)
Frank Fernandez
4.8.1 IC Scheduling and
Resource Management
Framework - V1-V3
3 Digital Format (PDF, .mpp or XER format)
Frank Fernandez
4.8.2 FY Portfolio Level
Schedule Evaluations
4 Digital Format (PDF, .mpp or XER format)
Frank Fernandez
4.8.3 Barracks and CDC Project
Schedule Templates
2 Digital Format (PDF, .mpp or XER format)
Frank Fernandez
4.8.3 Schedule Templates
Validations through Pilot
Projects
4 Digital Format (PDF, .mpp or XER format)
Frank Fernandez
4.8.4 Updates to Procedures for
IC logistics and
Inspections
4 Digital format (PDF, excel and Word document)
Frank Fernandez
4.9.1 IC implementation
authority structure and funding plan
1 Digital format (JPEG, PDF and Word document)
Frank Fernandez
4.9.2 IC oversight charter and
procedures set
1 Digital format (PDF and
Word document)
Frank Fernandez
4.9.2 IC Annual Report
Template and Schedule Set
1 Digital format (PDF and
Word document)
Frank Fernandez
4.10.
Strategic Plan to Scale across DoD branches updates
1 Digital format (PDF and
Word document)
Frank Fernandez
4.10.
IC Publications highlighting benefits and proof points
3 Digital format (PDF and
Word document)
8. SERVICE SUMMARY
8.1 The contract service requirements are summarized into performance objectives that relate to the expectations for the deliverables. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to project success.
Performance Objective
(PO)
Standard Performance
Threshold
Method of
Surveillance
PO#1
Develop and deliver criteria, standards, and tools for
Industrialized Construction
(IC) that align with DoD and
NAVFAC requirements
(PWS Task 1–4).
Standards documentation aligns with DoD criteria format (MIL-STD-
3007) and supports
NAVFAC mission objectives for IC implementation.
≤ 3 validated customer complaints on deliverable quality;
adjudicated within
3 days.
100 % inspection of final deliverables for technical and policy compliance.
PO#2
Create and validate the IC business case and economic model for DoD adoption
(PWS Task 2).
Model accurately compares conventional vs industrialized construction with traceable assumptions and inputs.
≤ 2 substantiated errors in data model calculations or assumptions.
Analytical review of model and source data by government technical team.
PO#3
Produce policy and contracting framework updates that enable IC procurement and acquisition reform (PWS Task 3).
Policy recommendations address procurement efficiency and align with DoD and FAR requirements.
≤ 2 revisions requested by COR after initial submission.
100 % inspection of policy deliverables for accuracy and clarity.
PO#4
Deliver BIM and Digital
Integration Tools that enable standardized IC design and deployment (PWS Task 4).
Tools and templates interoperate with DoD
BIM and Digital Twin standards, recommending adjustments; (UFC 1-
300-09N).
≤ 3 validated technical issues identified in testing resolved within 10 days.
Verification testing and user acceptance review reports.
PO#5
Design and document IC prototype and pilot projects with validated outcomes
(PWS Task 5).
Prototype documentation demonstrates repeatability and cost/schedule benefits.
No more than two
(2) corrective actions required following
Government review.
Inspection of pilot deliverables and data validation reports.
PO#6
Develop and deliver training and transition materials for
IC adoption across
NAVFAC (PWS Task 6).
Materials cover all target audiences and include change management playbook, competency framework, and training modules.
≤ 2 revisions requested by COR after initial submission.
COR review of training content and survey results.
PO#7
Establish IC industrial base ecosystem and vendor database (PWS Task 7).
Database complete with
≥ 80% of identified vendors categorized by tier level and capability.
≤ 2 data accuracy issues per vendor entry.
COR spot check and data validation audit.
PO#8
Develop portfolio-wide logistics and scheduling framework for IC (PWS
Task 8).
Framework enables tracking of offsite and onsite activities with >
80% data availability.
≤ 2 validated reporting errors per quarter upon scaling to enterprise usage.
Review of milestone tracking outputs and schedule dashboards.
PO#9
Establish IC program governance and reporting framework (PWS Task 9).
Governance structure defines roles, responsibilities, and KPI reporting cycle within
DoD oversight structure.
No more than one missed deliverables per year without previous consent.
100 % inspection of governance deliverables and
KPI reports.
PO#10
Develop IC scaling plan for
DoD enterprise adoption
(PWS Task 10).
Plan includes phased implementation path, risk mitigation strategy, and cross-agency coordination roadmap.
≤ 3 revisions requested after government review.
COR review and acceptance of scaling plan.
9. PLACE OF PERFORMANCE
The Contractor shall perform work under this contract at the Contractor’s normal place of work or travel location as authorized by the COR and required to complete task performance. The
Contractor will take appropriate steps to ensure the security of their network is up-to-date and is sufficiently protected against viruses and malware. Most documents can be sent via e-mail or via the use of a file sharing/exchange system. Larger files will be sent electronically via Department of Defense Secure Access File Exchange (DoD SAFE).
10. GOVERNMENT POINTS OF CONTACT
The Government’s Points of Contact will be determined at the time of award.
Security Requirements
Security Eligibility Requirement
This effort will involve the Contractor to access and potentially populate information/material at the Controlled Unclassified Information (CUI) level. All Contractor and Subcontractor employees gaining access to CUI must have a current (within the past 10 years) favorable Tier 1 or equivalent investigation or higher investigation prior to starting work on the contract. All service and support on this contract are required to be U.S. citizens and must be able to obtain and maintain favorable suitability of the aforementioned Personnel Security Investigation (PSI). Personnel not engaging with CUI are exempt from the aforementioned Personnel Security Investigation (PSI) requirement.
As this is an unclassified contract, NAVFAC EXWC Security will be responsible for ensuring contractors meet the PSI requirements. Some restricted areas may require higher PSI, contractor will comply with local site requirements as needed.
Contractor and Subcontractor personnel cannot begin work on the contract until written concurrence from the government security management office is obtained, stating that the employee has met the criteria to support this contract. In support of this requirement, the contractor shall submit a list reflecting all personnel working on the contract 14 days after the contract has been awarded. This list shall be updated as needed due to personnel changes.
The government retains the right to request removal of Contractor/Subcontractor personnel, who regardless of prior clearance or adjudication status whose actions, while assigned to this contract, are determined by the COR or government security management office to conflict with the interest of the government. If such a removal occurs, the Contractor shall assign qualified personnel, who is able to meet the criteria of this contract, to any vacancy.
The Contractor/Subcontractor shall report any personnel who are no longer working under this contract effort within 48 business hours to the Contracting Officers Representative (COR).
Logical and Physical Access
Contractors and Subcontractors may require logical or physical access to DoD installations and or
Navy Information Technology (IT) systems. Common Access Cards (CAC) will only be issued in accordance with DoDI-5200.46. Contractors shall submit required paperwork to the COR and all CAC issuances will be conducted by the government security management office. Contractor employees who do not require access to Navy IT systems or physical access to a single DoD installation will use the local defense Biometric Identification System (DBIDS). DBIDS processing is the responsibility of the Contractor.
If a Contractor/Subcontractor is already in possession of a CAC in support of another contract, they may retain the CAC until such a time as they no longer require it for that contracting effort. The Contractor/Subcontractor must still submit the required Contractor Eligibility Request vice a DD-1172-2 to the government security management office via the COR.
Once a contractor no longer requires CAC or DBIDS access in support of this contract, the
Contractor/Subcontractor shall mail the applicable card to NAVFAC EXWC via Command
Security Manager, 1000 23rd Ave, Port Hueneme, CA 93043 and email the COR the USPS tracking number, or return it to a local RAPIDS office.
Safeguarding Controlled Unclassified Information
The Contractor shall protect all CUI information per DoD 5200.01 volumes 1-3, DoD 5200.48, 32
CFR Part 117, and Navy Information Security Program manuals. Contractor/Subcontractor personnel shall not disclose and must safeguard procurement sensitive information, computer systems and data, privacy act data, and government personnel work products, which are obtained or generated in the performance under this contract. This includes but is not limited to electronic transmission of material.
Personnel shall adhere to the Privacy Act, Title 5 of the U.S. Code (USC), section 552a and applicable agency rules and regulations.
Contract and Subcontractor shall be held liable for all PII and CUI data breaches where it is culpable (e.g., unauthorized disclosure, contract proprietary information, social security numbers, etc.).
All contractors shall take the DoD Mandatory Controlled Unclassified Information (CUI) Training every year and submit training certificate to the CORs. Link provided is:
https://securityawareness.usalearning.gov/cui/index.html
Upon completion of this contract, all CUI documentation (reports, working papers, photographs, drawings, government furnished equipment or information, etc.) shall be turned over to: NAVFAC
EXWC, SH23, 1000 23rd Avenue, Building 1100, Port Hueneme, CA 93043-4370.
Photography
If photography or video imagery is required in the performance of this contract, contractor must obtain the appropriate command and/or installation photography pass. A formal review of all photography or video imagery must be completed by the host security office before the use of photography or video imagery can be utilized by the Contractor or Subcontractor. Contractor shall ensure all photography and video associated with this task are safeguarded per DoD I 5200.01 vol
1-3. Dissemination is limited to NAVFAC EXWC and publishing of imagery is prohibited to any other source without the consent of the COR. At the completion of this contract/task order/project all copies of said material are turned over to the COR or properly destroyed.
File details come from the government source that posted it. Updated .