N39430-19-R-2110 Amendment 02

QUESTIONS AND ANSWERS_RFI #2

1. Will you provide guidance on what an offeror may provide to demonstrate past performance on projects where they served as a sub consultant?

Answer: The offeror may submit a PPQ completed by the Prime if the sub consultant performed a significant share of the work on the project presented.