OMAC_3_Amendment_7_DEC_17.docx

DOCX document 35 KB Posted

Attached to
Oceans Multiple Award Contract Federal contract opportunity
Solicitation number
N3943018R2004
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

OMAC_3_Amendment_7_DEC_17.docx

View the file

Other files for this federal contract opportunity

Other files attached to Oceans Multiple Award Contract, newest first.
File Type Posted
OMAC_3_Amendment__8_DEC_17.docx DOCX document
OMAC3_Amendment_1-1_DEC__17-REV_4.docx DOCX document
OMAC3_Amendment_1-1_DEC__17-REV_4.docx DOCX document
OMAC_RFP_9_NOV_17-NECO.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N39430-18-R-2004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

A. Proposal Due Date is changed to 12:00pm on December 18, 2017.

B. Answers to Requests for Information are as follows:

1. Question:

a. Paragraph F, pg. 3, Section L.2 (1) is revised as follows: a through e shall be submitted separately from Volumes I and II. Only one original of these documents is required.

b. Question 56, pg. 11. Referring to the instructions on page 63, Section L.2 (1): Should each three-ring binder contain all required documentation (a-e)? Answer: Yes, Volume I and II should contain all required documentation (a-e).

Could you tell us which is the correct submittal requirement?

Answer: Only one copy of documents a through e shall be submitted.

2. Question: Why was amendment 1 posted twice? Is there a difference?

Answer: Proposal Due date and time were corrected on the NECO website to read, “11 December 2017 12:00PM PST.”

3. Question: RFP, Amendment 01, Question 34, pg. 9. Does the Project Manager (not the Senior Program Manager) need to be a PE? Asking to confirm yet the Solicitation only states Program Manager needs to be PE.

Answer: Confirmed, solicitation is correct. Professional Engineering registration for Project Manager is required.

The following have been deleted:

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 11-Dec-2017 12:00 PM to 18-Dec-2017 12:00 PM.