This is a Request for Quote (RFQ) for rental and maintenance of material handling equipment (MHE) issued by Portsmouth Naval Shipyard, Contracting, Code 410.2, located in Kittery, ME 03904. The solicitation number is N3904026Q3157 with a due date of August 3, 2026 at 10:00 AM ET.
The requirement calls for the rental and maintenance of two forklifts for a primary performance period of September 28, 2026 through November 1, 2026 (5 weeks) with an option to extend both units for an additional 2 weeks. Equipment will be deployed to Naval Base New London (NLON) in Groton, Connecticut. CLIN 0001 specifies rental and maintenance of one 6K# counterbalance, pneumatic, internal combustion forklift for 5 weeks; CLIN 0002 specifies rental and maintenance of one 17K# counterbalance, pneumatic, internal combustion forklift for 5 weeks. CLINs 0003 and 0004 cover freight and associated shipping costs for each unit. Additional CLINs address Contract Data Requirement List (CDRL) submissions and contractor personnel rosters for the base period and option period. The contractor must provide delivered prices on an F.O.B. destination basis, with all associated shipping costs included. Payment methods available are WAWF (Wide Area Workflow) and GCPC (Government Commercial Purchase Card, up to $100,000). Quotes will be evaluated on an "All or None" basis with CPARS evaluation procedures applied. Evaluation criteria include: Factor 1—Technical Acceptability (compliance checklists demonstrating specifications are met, schedule adherence); Factor 2—Experience/Past Performance (two relevant projects completed within the last five years involving forklift rental and maintenance); and Factor 3—Price (best value after adherence to other factors). The Statement of Work requires equipment to operate around-the-clock with unlimited usage hours, repair response within 4 hours and completion within 24 hours or replacement within 48 hours, preventative maintenance coordination, liquid spill containment, and provision of alternate forks at no charge if requested. All units must comply with applicable OSHA standards (29 CFR 1910.178, NAVSHIPYD PTSMH INST 10490.1M, ANSI/ITSDF B56 series), be no older than 5 years, include enclosed cabs with heat/defrost/air circulation, have independent side-shift, hydraulic fork positioners, backup alarms, working lights, and manufacturer capacity data plates. Personnel accessing Portsmouth Naval Shipyard must be U.S. citizens with proper identification; security clearance and background screening requirements apply. The solicitation includes standard FAR and DFARS clauses, NAVSEA-specific terms addressing mercury exclusion, yellow material restrictions, on-site safety requirements, and conflict-of-interest disclosures.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation N3904026Q3157
THIS IS NOT AN ORDER
PLEASE PROVIDE DELIVERED PRICES, AVAILABILITY, AND PRICE SOURCE WITH QUOTE
REFERENCE # N3904026Q3157 DUE DATE: 08/03/2026 10:00 AM ET
From: Portsmouth Naval Shipyard Your company info:
William (Bill) V. LeDuc III NAME:
Contracting, Code 410.2 POC:
Kittery, ME 03904 (P) PHONE: 207-994-4935 Email:
Email: william.v.leduciii.civ@us.navy.mil Cage Code:
BUSINESS SIZE (circle one): SMALL LARGE PAYMENT TERMS ______%______DAYS
MOBILIZATION TIME: _________ARO PRICES DERIVED FROM (CHECK ONE)
F.O.B. DESTINATION, Y____N____ ___COMMERCIAL PRICE LIST DATED
IF NO, SHIPPING COST__________. ___INTERNAL PRICE LIST DATED
___OTHER ( PLEASE EXPLAIN )
Please indicate your preferred payment method by checking one of the options below. Payment options available are WAWF and GCPC: Government Commercial Purchase Card (up to $100,000). Please ensure that you register for WAWF (www.wawftraining.com) GCPC_____ WAWF (Wide Area Workflow) _____
*Please note that purchase card orders are not paid up front. Once material is received, a Government cardholder may be contacted for purchase card information.
_X__ If checked, to be awarded on an “All or None” basis, and CPARS evaluation procedures apply.
YOUR SIGNATURE___________________________________DATE________________________
ITEM DESCRIPTION QTY Unit Price Total
Rental and maintenance of (1) 6K# in accordance with the Statement of Work (SOW) and Attachment 3.
Weeks
0002 Rental and maintenance of (1) 17K# Forklift in accordance with the Statement of Work (SOW) and Attachment 4.
0003 Freight: All associated shipping costs related to CLIN 0001. 2 Job
0004 Freight: All associated shipping costs related to CLIN 0002. 2 Job
Contract Data Requirement List- Exhibit A consists of the CDRL which shall be provided in accordance with the Statement of
Work.
1 Set
NSP
NSP
A001 Contractor’s Personnel Roster in accordance with Exhibit A 1 Each
Option
Option to Extend CLIN 0001 2
Option
Option to Extend CLIN 0002 2
1003 Contract Data Requirement List- Exhibit B consists of the CDRL which shall be provided in accordance with the Statement of
Work.
1 Set NSP NSP
B001 Contractor’s Personnel Roster in accordance with Exhibit B 1 Each
Period of Performance: 09/28/2026 – 11/01/2026 (5 weeks) o Option 1: 11/02/2026 – 11/15/2026 (2 weeks)
Place of performance is: Naval Base New London (NLON)- Groton, CT For evaluation purposes, please provide any applicable procedures and technical information. If no information is provided, your quotation may be determined to be unresponsive.
Please provide published commercial labor rates and breakdown of total prices, if applicable, for Price Justification purposes.
See below for Statement of Work and Applicable Clauses.
ATTACHMENTS
Attachment 1- OPSEC Encl 2_redacted Attachment 2- Compliance Checklist for Unit 1- 6K# Attachment 3- Compliance Checklist for Unit 2- 17K# Exhibit A_redacted Exhibit B_redacted
STATEMENT OF WORK
1. SCOPE
1.1. Material Handling Equipment (MHE) to support required movement of equipment and materials.
2. APPLICABLE DOCUMENTS
2.1. Issues of Publications - The following documents of the issue date in effect on the date of this request for proposal form a part of this specification to the extent applicable, or as specified herein. Within the specification, they shall be referred to by their basic designation only.
2.1.1. Government
2.1.1.1. 29 CFR 1910.178
2.1.1.2. NAVSHIPYD PTSMH INST 10490.1M
2.1.2. Nongovernment
2.1.2.1. ANSI/ITSDF B56 (series)
2.2. Order of precedence - In the event of conflict between the text of this specification and that of the references cited above, the text of this specification shall take precedence. Nothing in this specification, however, shall supersede applicable laws or regulations unless a specific exemption has been obtained.
3. REQUIREMENTS
3.1. Machine capacities listed in Table-1 are approximate, actual required capacity range is noted in the Unit Specifications Table(s). Tables 2 and 3 will be returned with the bid submittal indicating yes or no in the checklist for compliance with each noted specification. In the event that no bidder is able to fully meet the specifications without requiring the exceptions listed, the unit that best meets the operational needs of the Government will be selected.
Table-1
Unit Number Machine type
Unit 1 6K# Counterbalance, Pneumatic, IC Forklift
Unit 2 17K# Counterbalance, Pneumatic, IC Forklift
3.2 Unit Specification: Unit 1
Comply
Description Yes No
•Capacity/type: 5.5K#-8K# capacity @ 24” rated Load Center (L.C.), counterbalanced forklift.
•Max outside turning radius: 96”
•Pallet Forks: MAX Width: 5”, MAX thickness: 2”, Length: 48”
•Power type: Internal Combustion, Diesel
•Shall be no older than 5 years
•Pneumatic, solid pneumatic, or foam filled tires
•Will have enclosed cab with heat, defrost, and air circulating fan (temporary or aftermarket cab enclosure is acceptable)
•EXCEPTION: Rain Canopy will be considered if no bidder is able to meet this specification without need for exception(s).
•The carriage will be equipped with independent side-shift that is not a function of the fork positioners.
•Will be equipped with hydraulic fork positioners
•EXCEPTION: Manual forks will be considered if no bidder is able to meet this specification without need for exception(s).
•Light package to include front and rear working lights.
•Will be equipped with audible backup alarm
•Will have manufacturer’s capacity data plate containing safe working load and maximum reach height at a minimum.
•Operator controls shall be properly and clearly marked
•An operator’s manual will be in the machine
1. Table-2
3.2. Unit Specification: Unit 2
Comply
Description Yes No
•Capacity/type: Between 17K#-20K# capacity @ 24” rated Load Center (L.C.), counterbalanced forklift
Units with official rated capacity and load center that differ from the noted requirements will be deemed acceptable if the capacity is equivalent when adjusted for the load center noted in the requirement.
•Max outside turning radius: 160”
•Forks: Standard tip and taper
MAX Width: 6”, MAX Thickness: 3”
MIN Length: 72”, Preferred Length: 96”
•Capable of a minimum outside fork spread of 72”
•Power type: Internal Combustion, Diesel
•Shall be no older than 5 years
•Pneumatic, solid pneumatic, or foam filled tires
•Will have enclosed cab with heat, defrost, and air circulating fan (temporary or aftermarket cab enclosure is acceptable)
•EXCEPTION: Rain Canopy will be considered if no bidder is able to meet this specification without need for exception(s).
•The carriage will be equipped with independent side-shift that is not a function of the fork positioners.
•Will be equipped with hydraulic fork positioners
•Light package to include front and rear working lights.
•Will be equipped with audible backup alarm
•Will have manufacturer’s capacity data plate containing safe working load and maximum reach height at a minimum.
•Operator controls shall be properly and clearly marked
•An operator’s manual will be in the machine
2. Table-3
4. RESPONSIBILITITES
4.1. Government
4.1.1. Equipment Technical Evaluation: Code 986 Engineering
4.1.2. Receipt Inspection: Contracting Officer Representative (COR), Technical Point of Contact (TPOC), Zone Manager (ZM), and/or C338 Team Lead (TL). If none of these are Portsmouth Naval Shipyard (PNSY) licensed MHE operators, a licensed operator assigned by PNSY will also be present in accordance with section 5.3 of this SOW.
4.1.3. Schedule equipment delivery and returns: COR, and TPOC, ZM and C338 TL
4.1.4. Schedule equipment service, and repair: COR, TPOC, ZM and C338 TL
4.2. Contractor
4.2.1. The equipment will be operating around-the-clock under a rigorous deployment performance schedule. Rentals will include unlimited usage hours within the contracted period of performance.
4.2.2. Within four (4) hours of initial notification of the need for repair, the Contractor shall have a qualified and equipped technician on the job-site fully prepared to repair the rental equipment.
The defective unit(s) shall be repaired within twenty-four (24) hours (one day) of initial notification or, if the original defective unit(s) cannot be made operational, replaced within forty-eight (48) hours (two days) of initial notification. If the equipment failure is not the fault of the Government, the Contractor shall bear all costs associated with its repair and/or replacement.
4.2.3. If requested by the Government during the term of the lease, the Contractor shall provide and install alternate forks as specified by the Government at no charge. Alternate forks will also be provided with an appropriate updated Capacity Data Plate if required.
4.2.4. The contractors and non- PNS Government Agencies (NPGAs) shall be responsible to read and understand the Work Site Operational Safety Environment requirements of OSHECM Chapter 250 and can see an electronic copy of OSHECM Chapter 250 (latest revision) by using the following web site:
https://www.navsea.navy.mil/Home/Shipyards/Norfolk/NNSY-Forms/
4.2.5. The Contractor shall provide and require their personnel to wear personal protection equipment (PPE) (e.g., hearing protection, eye protection, gloves, steel-toed shoes or boots, aprons, masks, face shields, reflective vests, safety harnesses for fall protection in accordance with OSHA CFR 1926 (construction) and CFR 1915 (shipyard) standards.
4.2.6. The Contractor is required to follow all appropriate lockout/tag out requirements as specified by OSHECM Chapter 250 and CFR 1915.89. Contractor shall conform to all applicable safety and occupational health standards published in the Federal Register or any other Occupational Safety and Health Administration (OSHA) Public Laws and ensure employees observe safety, traffic control, and fire prevention requirements in effect at the site.
4.3. Maintenance
4.3.1. Surveillance Checks
4.3.1.1. The Government will conduct daily fluid level checks; however, the contractor shall be responsible for adding fluids to the equipment to ensure the loss of fluid is not due to a more serious mechanical issue.
4.3.1.2. Except for daily fluid checks, the contractor shall be responsible for all materials and labor for preventative maintenance and repairs not arising out of abuse or negligence by the Government.
4.3.2. Preventative Maintenance
4.3.2.1. The Contractor shall coordinate the scheduling of preventative maintenance in advance with the COR, TPOC, ZM and C338 TL.
4.3.2.2. Any routine preventative maintenance will be completed by the Contractor during normal first-shift hours unless alternative arrangements are made ahead of time.
4.3.2.3. During routine maintenance, or emergency breakdown repairs, the Contractor shall provide liquid spill protection to the ground surface. All spills shall be contained and cleaned up prior to leaving the site. If a spill is caused by a broken or leaking liquid line or some other system on the Contractor’s equipment, the Installation Fire Department will be alerted to contain the spill until the Contractor can make the necessary repairs. Applicable emergency contact numbers will be obtained by the Contractor from the local pass office prior to commencement of any work. It shall be the responsibility of the Contractor to reimburse the Government for containing the spill.
4.3.2.4. If at the determination of the Government, leaks are unacceptably frequent, the unit will be swapped out for a different unit meeting the same specification.
4.3.2.5. The Contractor is responsible for disposal of any fluids or hazardous material generated as a result of maintenance, spills, or leaks.
4.3.3. Repairs
4.3.3.1. The Contractor shall provide a qualified service technician to repair all equipment deficiencies and malfunctions and return the system to an operable condition. The response time for the repair or replacement of deficient equipment shall meet the requirements defined in section 4.2.2.
4.3.3.2. The Contractor shall validate all completed repairs by either signing the appropriate PNSY provided MHE Inspection Sheet, or by providing a completed repair order at the time of the completed repair. Completed repair orders not provided at the time of the completed repair will be forwarded to the COR, TPOC, ZM & C338 TL at the earliest convenience.
4.3.3.3.
4.3.3.4. If breakdowns become frequent, the equipment will be removed from the shipyard and replaced with a more reliable unit in accordance with the unit specifications outlined herein upon request by the Government.
4.4. Training
4.4.1. N/A
4.5. Required Documents
4.5.1. Points of contact with telephone numbers for requesting emergency repair regardless of the time or type of day. (CDRL A001)
5. DELIVERY / RETURN.
5.1. Delivery
5.1.1. The Contractor shall be responsible for shipping, loading, and unloading of the equipment.
Delivery truck(s) will be capable of loading/unloading the unit(s) at ground level without a loading dock or additional material handling equipment.
5.1.2. The Contractor shall deliver machinery that is fully-charged/fueled, fully-assembled, ready-to-use, and in a first-class-operating condition and functions as intended. Machines shall be functionally tested prior to delivery.
5.1.3. All units will be in compliance with any and all applicable laws governing internal combustion equipment and its operation in the State and/or jurisdiction where the rental will be used. All units for use in California will have a CARB EIN clearly visible on each machine.
5.1.4. The machinery with its support equipment shall be delivered to the site on or prior to the request date. The Contractor shall confirm the date and time of delivery prior to each delivery with the COR, TPOC, ZM & C338 TL, if appointed.
5.1.5. The Contractor shall provide the COR, TPOC, ZM & C338 TL with an itemized list of all equipment delivered at the time of delivery.
5.2. Security
5.2.1. To be allowed onto a government Shipyard, personnel must be US citizens and in possession of appropriate personal identification. Proof of US citizenship may be necessary and can be required for access to the drydock. Allowable documentation of US citizenship is an official government issued Certificate of Birth or Naturalization (w/ raised seal & not a photocopy) or a valid US passport. Vehicular access requires a non-expired personal REAL ID compliant Driver’s License and appropriate vehicle identification or registration. The transport vehicle must have the company’s name / logo prominently displayed. To gain access to the drydock environs, authorization must be given by the Security Department, personnel must be escorted and possess / wear their own personal safety gear.
5.3. Receipt Inspection Criteria
5.3.1. An inspection of each forklift shall be performed by a shipyard licensed operator using a PNSY provided MHE Inspection Sheet on delivery. Any machines not meeting the requirements of this statement of work or having defects or damage that negatively affect the operation of the machine will be refused.
5.3.2. If there are de minimis defects or damage found that are determined to be superficial in nature and that do not affect the operation of the machine, they will be noted on the inspection form.
The Contractor’s representative will sign the PNSY inspection form or attest in writing that the damage was pre-existing and does not affect the operation of the machine. This will be completed before the unit is accepted by the Government.
5.4. Final Acceptance - Upon satisfactory completion of inspection and test of the equipment, the authorized Government Representative (COR, TPOC, ZM, or C338 TL) will sign and forward the acceptance document(s) to PNSY, Code 420 COR for completion. The rental period does not begin until the government has accepted the forklift(s). Unloading of equipment from Contractor’s transport does not signify acceptance.
5.5. Return - The Government will provide a temporary storage location convenient for Contractor pick-up. The Government will notify the Contractor as well as the Contracting Office as to when the rental Item has been released and is available for pick-up.
6. GENERAL
6.1. N/A
See below for Clauses and Provisions Applicable to this procurement.
CLAUSES:
Responsibility and Inspection: unless otherwise specified in the order, the supplier is responsible for the performance of all inspection requirements and quality control. The following FAR provisions and clauses are applicable to this procurement:
52.204-7 System for Award Management 52.204-13 System for Award Management Maintenance 52.204-19 Incorporation by Reference of Representations and Certifications 52.209-2 Prohibition on Contracting with Inverted Domestic Corporations—Representation 52.209-10 Prohibition on Contracting With Invented Domestic Corporations 52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any
Federal Law 52.211-14 Notice of Priority Rating for National Defense, Emergency Preparedness, and Energy Program Use 52.211-15 Defense Priority and Allocation Requirements 52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services 52.217-5 Evaluation of Options 52.217-9 Option to Extend the Term of the Contract 52.219-1 Small Business Program Representations 52.219-6 Notice of Total Small Business Set-Aside 52.219-28 Post-Award Small Business Program Rerepresentation 52.222-3 Convict Labor 52.222-19 Child Labor—Cooperation with Authorities and Remedies 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment 52.222-36 Equal Opportunity for Workers with Disabilities 52.222-50 Combating Trafficking in Persons 52.222-90 Addressing DEI Discrimination by Federal Contractors 52.223-5 Pollution Prevention & Right-To-Know Information 52.223-23 Sustainable Products and Services (DEVIATION)(Feb 2026) 52.226-7 Drug-Free Workplace 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving 52.232-18 Availability of Funds 52.232-33 Payment by Electronic Funds Transfer—System for Award Management 52.232-39 Unenforceability of Unauthorized Obligations 52.232-40 Providing Accelerated Payments to Small Business Subcontractors 52.233-1 Disputes 52.233-3 Protest after Award 52.233-4 Applicable Law for Breach of Contract Claim 52.237-1 Site Visit 52.237-2 Protection Of Government Buildings, Equipment, And Vegetation 52.240-90 Security Prohibitions and Exclusions Representations and Certifications 52.204-91 Contractor Identification 52.242-15 Stop-Work Order 52.242-17 Government Delay of Work 52.244-6 Subcontracts for Commercial Products and Commercial Services 52.246-2 Inspection of Supplies—Fixed-Price 52.247-34 F.o.b. Destination 52.252-1 Solicitation Provisions Incorporated by Reference 52.252-2 Clauses Incorporated by Reference 52.252-5 Authorized Deviations in Provisions 52.252-6 Authorized Deviations in Clauses
252.201-7000 Contracting Officer’s Representative 252.203-7000 Requirements Relating to Compensation of Former DoD Officials 252.203-7002 Requirement to Inform Employees of Whistleblower Rights 252.203-7005 Representation Relating to Compensation of Former DoD Officials 252.204-7003 Control of Government Personnel Work Product 252.204-7009 Limitations on the Use or Disclosure of Third-Party Contractor Reported Cyber Incident Information 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting (DEVIATION 2024-O0013, Revision 1) 252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
252.204-7016 Covered Defense Telecommunications Equipment or Services-Representation 252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services- Representation 252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services 252.204-7022 Expediting Contract Closeout 252.204-7024 Notice on the Use of the Supplier Performance Risk System 252.204-7998 Alternate A, Annual representations and Certifications. (DEVIATION 2024-O0013 REVISION 1) 252.211-7003 Item Unique Identification and Valuation 252.211-7008 Use of Government-Assigned Serial Numbers 252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors 252.216-7010 Postaward Debriefings for Task Orders and Delivery Orders 252.219-7003 Small Business Subcontracting Plan (DoD Contracts) 252.223-7008 Prohibition of Hexavalent Chromium 252.225-7000 Buy American-Balance of Payments Program Certificate 252.225-7001 Buy American and Balance of Payments Program 252.225-7012 Preference for Certain Domestic Commodities 252.225-7035 Buy American-Free Trade Agreements-Balance of Payments Program Certificate 252.225-7036 ALT I Buy American-Free Trade Agreements-Balance of Payments Program- Alternate I 252.225-7048 Export-Controlled Items 252.225-7055 Representation Regarding Business Operations with the Maduro Regime 252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime 252.225-7059 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region-Representation 252.225-7060 Prohibition on Certain Procurements from the Xinjing Uyghur Autonomous Region 252.227-7990 Technical Data-Commercial Products and Commercial Services (DEVIATION 2026-O0036) 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports 252.232-7006 Wide Area WorkFlow Payment Instructions 252.232-7010 Levies on Contract Payments 252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel 252.237-7019 Training for Contractor Personnel Interacting with Detainees 252.243-7001 Pricing Of Contract Modifications 252.244-7999 Subcontracts for Commercial Products or Commercial Services. (DEVIATION 2026-O0015) 252.247-7023 Transportation of Supplies by Sea—Basic
52.212-1 Instructions to Offerors—Commercial Products and Commercial Services.
As prescribed in 12.205(a)(1), insert a clause substantially as follows:
INSTRUCTIONS TO OFFERORS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEVIATION DATE)
(a) Submission of offers. Submit signed and dated offers to the office specified in this solicitation at or before the exact time specified in this solicitation. As a minimum, offers shall include—
(1) The solicitation number;
(2) The name, address, telephone number of the Offeror;
(3) The Offeror’s Unique Entity Identifier (UEI) and, if applicable, Electronic Funds Transfer (EFT) indicator;
(4) Information necessary to evaluate the factors contained in the provision at 52.212-2 or as described in the solicitation;
(5) Responses to provisions that require Offeror completion of information, representations, and certifications (other than those collected via the System for Award Management (SAM)); and
(6) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and any solicitation amendments.
(b) Period for acceptance of offers. The Offeror agrees to hold the prices in its offer firm for 60 calendar days from the date specified for receipt of offers, unless another time period is specified in an addendum to the solicitation.
(c) Late submissions, modifications, revisions, and withdrawals of offers.
(1) Offerors are responsible for submitting offers and any modifications or revisions to the Government office designated in the solicitation by the time specified in the solicitation.
(2) Any offer, modification, or revision received after the time specified for receipt of offers is “late” and will not be considered unless it is received before award is made and the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition. However, a late modification of an otherwise successful offer that makes its terms more favorable to the Government will be considered at any time it is received and may be accepted.
(3) If an emergency or unanticipated event interrupts normal Government processes so that offers cannot be received at the
Government office designated for receipt of offers by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation or other notice of an extension of the closing date, the time specified for receipt of offers will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(4) Offerors may withdraw their offers by written notice to the Government received at any time before award.
(d) Contract award (not applicable to Invitation for Bids). The Government intends to evaluate offers and award a contract without discussions with Offerors. Therefore, the Offeror’s initial offer should contain the Offeror’s best terms. However, the
Government reserves the right to conduct discussions, if necessary. The Government may reject any or all offers if such action is in the public interest, accept other than the lowest offer, and waive informalities and minor irregularities in offers received.
(e) Debriefings. If a postaward debriefing is given to requesting Offerors, the Government will disclose the following information, if applicable:
(1) The agency’s evaluation of the significant weak or deficient factors in the debriefed Offeror’s offer.
(2) The overall evaluated cost or price and technical rating of the successful Offeror and the debriefed Offeror and past performance information on the debriefed Offeror.
(3) The overall ranking of all Offerors when any ranking was developed by the agency during source selection.
(4) A summary of the rationale for award.
(5) For acquisitions of commercial products, the make and model of the product to be delivered by the successful Offeror.
(6) Reasonable responses to relevant questions posed by the debriefed Offeror as to whether the agency followed source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities.
(End of provision)
SUPPLEMENTAL INSTRUCTIONS
ADDENDUM TO 52.212-1 Instructions to Offerors--Commercial Items
I. GENERAL
In addition to FAR 52.212-1, “Instructions to Offerors – Commercial Items” and any other instructions contained elsewhere in this solicitation, the following information is provided:
Objections to any of the terms and conditions of the RFQ will constitute a deficiency which will make the offer unacceptable.
IMPORTANT NOTES:
(1) Vendors shall respond to all requirements of the solicitation document. Vendors are cautioned not to alter the solicitation.
(2) Initial quotes and any modifications thereto are to be submitted to the Contracting Office on or before the closing dated time cited elsewhere in this Request for Quote.
(3) Responses should be submitted via email only
(4) Please review all specifications carefully.
II. CONTENT OF QUOTE
1. RFQ pricing and information pages completed by the vendor.
2. A Point of Contact, name, email address, phone, CAGE code.
3. Representations and Certifications completed by the vendor in accordance with instructions contained elsewhere in this solicitation. If the vendor has completed all of the representations and certifications required by this solicitation in SAM.gov in accordance with FAR 52.204-7, then the vendor need not submit the hardcopy Representations and Certifications.
4. Technical Submission as noted below.
a. Submission of technical information demonstrating compliance with the specifications, including, but not limited to:
Technical Acceptability (Compliance Checklists Attachments 3 and 4) Adherence to Schedule
5. Experience/Past Performance
6. Pricing Submission. Vendors shall provide firm, fixed prices for each CLIN
Factor 1- Technical Acceptability Submissions: Vendors shall demonstrate their Technical Acceptability by meeting specifications and document capabilities
Factor 2- Experience Submission: Vendors shall submit documentation of two (2) projects/contracts that demonstrate recent and relevant experience with the two (2) major tasks identified in the Statement of Work (SOW). Contracts or projects are considered recent if they have been completed within the last five (5) years. Contracts or projects are considered relevant if they involve the rental and maintenance of forklifts. For each contract or project, Vendors shall provide the following:
(i) Customer’s name, organization and contact information;
(ii) Contract or project number and title;
(iii) Dates of performance (identify the start and end dates by month and year);
(iv) A description of the work performed and how it is relevant to the SOW.
Factor 3- Price: The Price Factor will not be rated. The Vendor’s response will be evaluated for compliance with the Addendum to 52.212-1, completeness and price reasonableness in accordance with FAR 12.204(a).
If the technical submittal is determined “Unacceptable”, it renders the entire quote technically unacceptable. Technical submissions that do not meet the minimum requirements will be rated as “Unacceptable” and will no longer be considered for further competition or award.
(End of Provision)
52.212-2, Evaluation - Commercial Items is applicable to this procurement.
(a)The Government will award a contract resulting from this solicitation to the responsible Offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The following factors will be used to evaluate offers:
Factor 1-Technical Acceptability
a. Compliance Checklists (Attachment 3 and Attachment 4)
b. Must meet specifications and document capabilities
c. Adherence to Schedule (Award may be made based on delivery and ability to meet the requested schedule)
Factor 2- Experience/Past Performance Factor 3-Price (Best Value, after adherence to other factors)
Vendors will be required to submit a quote that will be evaluated in accordance with the specifications provided in the solicitation, FAR 52.212-1 Instruction to Offerors. Failure to include pricing for all line items shall be cause for rejection of the quote for all line items.
Factor 1- Technical: Please provide documentation demonstrating your capabilities in fulfilling the SOW. Technical will be evaluated in accordance with L-212-W001.
a. Compliance Checklists- Must complete compliance checklists for quoted items, see attachments 3 & 4.
b. Must meet Statement of Work specifications and document capabilities
c. Adherence to Schedule- Please confirm availability for requested period of performance. If your company is unavailable for the requested period, please provide earliest available start. Please provide your best and fastest schedule. Award may be made based on delivery and ability to meet the requested schedule.
Technical Evaluation Ratings
Rating Description
Acceptable Submission clearly meets the minimum requirements of the solicitation
Unacceptable Submission does not clearly meets the minimum requirements of the solicitation
Technical Evaluation Ratings Rating Description Acceptable Submission clearly meets the minimum requirements of the solicitation Unacceptable Submission does not clearly meet the minimum requirements of the solicitation.
If the technical submittal is determined “Unacceptable”, it renders the entire quote technically unacceptable. Technical submissions that do not meet the minimum requirements will be rated as “Unacceptable” and will no longer be considered for further competition or award.
Factor 2- Experience Submission: Vendors shall submit documentation of two (2) projects/contracts that demonstrate recent and relevant experience with the two (2) major tasks identified in the Statement of Work (SOW). Contracts or projects are considered recent if they have been completed within the last five (5) years. Contracts or projects are considered relevant if they involve the rental and maintenance of forklifts. For each contract or project, Vendors shall provide the following:
(i) Customer’s name, organization and contact information;
(ii) Contract or project number and title;
(iii) Dates of performance (identify the start and end dates by month and year);
(iv) A description of the work performed and how it is relevant to the SOW.
Adjectival Rating
Description
Acceptable Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, OR the offeror’s performance record is unknown.
Unacceptable Based on the offeror’s performance record, the Government does not have a reasonable expectation that the offeror will be able to successfully perform the required effort.
Factor 3- Price: The Price will be evaluated as Best Value in accordance with L-212-W002, after adherence to other factors, however, the Contracting Officer reserves the right to award based on ability to meet the required schedule.
(b) Options (if applicable). The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. The evaluation of options does not obligate the Government to exercise the option(s).
(c) Notice of award. A written notice of award or acceptance of an offer furnished to the successful Offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
NAVSEA Texts:
C-202-H001 ADDITIONAL DEFINITIONS--BASIC (NAVSEA) (OCT 2018)
(a) Department - means the Department of the Navy.
(b) Commander, Naval Sea Systems Command - means the Commander of the Naval Sea Systems Command of the Department of the Navy or his duly appointed successor.
(c) References to The Federal Acquisition Regulation (FAR) - All references to the FAR in this contract shall be deemed to also reference the appropriate sections of the Defense FAR Supplement (DFARS), unless clearly indicated otherwise.
(d) National Stock Numbers - Whenever the term Federal Item Identification Number and its acronym FIIN or the term Federal Stock Number and its acronym FSN appear in the contract, order or their cited specifications and standards, the terms and acronyms shall be interpreted as National Item Identification Number (NIIN) and National Stock Number (NSN) respectively which shall be defined as follows:
(1) National Item Identification Number (NIIN). The number assigned to each approved Item Identification under the Federal Cataloging Program. It consists of nine numeric characters, the first two of which are the National Codification Bureau (NCB) Code. The remaining positions consist of a seven digit non-significant number.
(2) National Stock Number (NSN). The National Stock Number (NSN) for an item of supply consists of the applicable four-position Federal Supply Class (FSC) plus the applicable nine-position NIIN assigned to the item of supply.
(End of Text)
C-204-H001 USE OF NAVY SUPPORT CONTRACTORS FOR OFFICIAL CONTRACT FILES (NAVSEA) (OCT 2018)
(a) NAVSEA may use a file room management support contractor, hereinafter referred to as "the support contractor", to manage its file room, in which all official contract files, including the official file supporting this procurement, are retained. These official files may contain information that is considered a trade secret, proprietary, business sensitive or otherwise protected pursuant to law or regulation, hereinafter referred to as “protected information”. File room management services consist of any of the following: secretarial or clerical support; data entry; document reproduction, scanning, imaging, or destruction; operation, management, or maintenance of paper-based or electronic mail rooms, file rooms, or libraries; and supervision in connection with functions listed herein.
(b) The cognizant Contracting Officer will ensure that any NAVSEA contract under which these file room management services are acquired will contain a requirement that:
(1) The support contractor not disclose any information;
(2) Individual employees are to be instructed by the support contractor regarding the sensitivity of the official contract files;
(3) The support contractor performing these services be barred from providing any other supplies and/or services, or competing to do so, to NAVSEA for the period of performance of its contract and for an additional three years thereafter unless otherwise provided by law or regulation; and,
(4) In addition to any other rights the contractor may have, it is a third party beneficiary who has the right of direct action against the support contractor, or any person to whom the support contractor has released or disclosed protected information, for the unauthorized duplication, release, or disclosure of such protected information.
(c) Execution of this contract by the contractor is considered consent to NAVSEA's permitting access to any information, irrespective of restrictive markings or the nature of the information submitted, by its file room management support contractor for the limited purpose of executing its file room support contract responsibilities.
(d) NAVSEA may, without further notice, enter into contracts with other contractors for these services. Contractors should enter into separate non-disclosure agreements with the file room contractor. Contact the Procuring Contracting Officer for contractor specifics. However, any such agreement will not be considered a prerequisite before information submitted is stored in the file room or otherwise encumber the government.
C-211-H001 ACCESS TO THE VESSEL(S) (NAVSEA) ( OCT 2018 )
Officers, employees and associates of other prime Contractors with the Government and their subcontractors, shall, as authorized by the Supervisor, have, at all reasonable times, admission to the plant, access to the vessel(s) where and as required, and be permitted, within the plant and on the vessel(s) required, to perform and fulfill their respective obligations to the Government. The Contractor shall make reasonable arrangements with the Government or Contractors of the Government, as shall have been identified and authorized by the Supervisor to be given admission to the plant and access to the vessel(s) for office space, work areas, storage or shop areas, or other facilities and services, necessary for the performance of the respective responsibilities involved, and reasonable to their performance.
C-211-H018 APPROVAL BY THE GOVERNMENT (NAVSEA) (JAN 2019)
Approval by the Government as required under this contract and applicable specifications shall not relieve the Contractor of its obligation to comply with the specifications and with all other requirements of the contract, nor shall it impose upon the Government any liability it would not have had in the absence of such approval.
C-222-H001 ACCESS TO THE VESSELS BY NON-U.S. CITIZENS (NAVSEA) (APR 2019)
(a) No person not known to be a U.S. citizen shall be eligible for access to naval vessels, work sites and adjacent areas when said vessels are under construction, conversion, overhaul, or repair, except upon a finding by COMNAVSEA or his designated representative that such access should be permitted in the best interest of the United States. The Contractor shall establish procedures to comply with this requirement and NAVSEAINST 5510.2D.
(b) If the Contractor desires to employ non-U.S. citizens in the performance of work under this contract or agreement that requires access as specified in paragraph (a) of this requirement, approval must be obtained prior to access for each contract or agreement where such access is required. To request such approval for non-U.S. citizens of friendly countries, the Contractor shall submit to the cognizant Contract Administration Office (CAO), an Access Control Plan (ACP) which shall contain as a minimum, the following information:
(1) Badge or Pass oriented identification, access, and movement control system for non-U.S. citizen employees with the badge or pass to be worn or displayed on outer garments at all times while on the Contractor's facilities and when performing work aboard ship.
(i) Badges must be of such design and appearance that permits easy recognition to facilitate quick and positive identification.
(ii) Access authorization and limitations for the bearer must be clearly established and in accordance with applicable security regulations and instructions.
(iii) A control system, which provides rigid accountability procedures for handling lost, damaged, forgotten or no longer required badges, must be established.
(iv) A badge or pass check must be performed at all points of entry to the Contractor's facilities or by a site supervisor for work performed on vessels outside the Contractor's plant.
(2) Contractor's plan for ascertaining citizenship and for screening employees for security risk.
(3) Data reflecting the number, nationality, and positions held by non-U.S. citizen employees, including procedures to update data as non-U.S. citizen employee data changes, and pass to cognizant CAO
(4) Contractor's plan for ensuring subcontractor compliance with the provisions of the Contractor's ACP.
(5) These conditions and controls are intended to serve as guidelines representing the minimum requirements of an acceptable ACP. They are not meant to restrict the Contractor in any way from imposing additional controls necessary to tailor these requirements to a specific facility.
(c) To request approval for non-U.S. citizens of hostile and/or communist-controlled countries (listed in Department of Defense Industrial Security Manual, DOD 5220.22-M or available from cognizant CAO), Contractor shall include in the ACP the following employee data: name, place of birth, citizenship (if different from place of birth), date of entry to U.S., extenuating circumstances (if any) concerning immigration to U.S., number of years employed by Contractor, position, and stated intent concerning U.S. citizenship. COMNAVSEA or his designated representative will make individual determinations for desirability of access for the above group. Approval of ACP's for access of non-U.S. citizens of friendly countries will not be delayed for approval of non-U.S. citizens of hostile communist-controlled countries. Until approval is received, Contractor must deny access to vessels for employees who are non-U.S. citizens of hostile and/or communist-controlled countries.
(d) The Contractor shall fully comply with approved ACPs. Noncompliance by the Contractor or subcontractor serves to cancel any authorization previously granted, in which case the Contractor shall be precluded from the continued use of non- U.S. citizens on this contract or agreement until such time as the compliance with an approved ACP is demonstrated and upon a determination by the CAO that the Government's interests are protected. Further, the Government reserves the right to cancel previously granted authority when such cancellation is determined to be in the Government's best interest. Use of non-U.S. citizens, without an approved ACP or when a previous authorization has been canceled, will be considered a violation of security regulations. Upon confirmation by the CAO of such violation, this contract, agreement or any job order issued under this agreement may be terminated for default in accordance with the clause entitled "Default (Fixed-Price Supply And Service)" (FAR 52.249-8), "Default (Fixed-Price Research And Development)" (FAR 52.249-9) or "Termination (Cost Reimbursement)" (FAR 52.249-6), as applicable.
(e) Prime Contractors have full responsibility for the proper administration of the approved ACP for all work performed under this contract or agreement, regardless of the location of the vessel, and must ensure compliance by all subcontractors, technical representatives and other persons granted access to U.S. Navy vessels, adjacent areas, and work sites.
(f) In the event the Contractor does not intend to employ non-U.S. citizens in the performance of the work under this contract, but has non-U.S. citizen employees, such employees must be precluded from access to the vessel and its work site and those shops where work on the vessel's equipment is being performed. The ACP must spell out how non-U.S. citizens are excluded from access to contract work areas.
(g) The same restriction as in paragraph (f) above applies to other non-U.S. citizens who have access to the Contractor's facilities (e.g., for accomplishing facility improvements, from foreign crewed vessels within its facility, etc.) except that, with respect to access to the vessel and worksite, the restrictions shall not apply to uniformed U.S. Navy personnel who are non- U.S. citizens and who are either assigned to the ship or require access to the ship to perform their duties.
C-223-H003 EXCLUSION OF MERCURY (NAVSEA) (MAR 2019)
(a) Definitions. As used in this text:
Article means a manufactured item other than a fluid or particle: (i) which is formed to a specific shape or design during manufacture; (ii) which has end use function(s) dependent in whole or in part upon its shape or design during end use;
and (iii) which under normal conditions of use does not release more than very small quantities, e.g., minute or trace amounts of a hazardous chemical, and does not pose a physical hazard or health risk to employees.
Boundary of containment means a continuous tight seal (barrier) to prevent the release of functional mercury during normal operation and maintenance. Examples include the exterior of a fluorescent lamp, glass capsule of a mercury switch, and container for mercury reagents. A double boundary of containment consists of two independent seals.
Functional mercury means mercury or mercury compound(s) contained in equipment that is required for the equipment to operate properly, such as that found in mercury switches, fluorescent lamps, flat-panel monitors, thermostats, thermostat probes, small coin type batteries, barometers, and dental amalgams.
Hardware means any article, container, piece of material, individual part, subassembly, assembly, component, or system to which mercury control requirements apply.
Mercury-free means hardware that does not contain functional mercury and is not contaminated by mercury or mercury compounds.
Portable means items that are frequently transported during normal operation. Desk lamps, shop lights, and hand-held instruments are considered portable, while bulbs in stationary light fixtures are not. In general, items that require transport only during maintenance, installation, and removal of the items are not considered portable.
(b) The Contractor, and all subcontractors and vendors, shall ensure that mercury or mercury containing compounds are not intentionally added to, or come in direct contact with, hardware or supplies furnished under this contract.
(1) The Contractor shall ensure that mercury and mercury compounds are not taken onboard naval vessels by Contractor, subcontractor, or vendor personnel except for functional mercury used in batteries, dental amalgams, fluorescent lamps, flat-panel monitors, required instruments, sensors or controls, weapon systems, and chemical analysis reagents specified by the Naval Sea Systems Command (NAVSEA).
(2) Portable fluorescent lamps and portable instruments containing elemental mercury must be shock-proof in accordance with MIL-DTL-901E entitled Requirements for Shock Tests, H.I. (High Impact) Shipboard Machinery, Equipment, and Systems and have mercury enclosed by a double boundary of containment. Some devices with liquid crystal display (LCD) screens utilize a fluorescent bulb backlight to illuminate the LCD screen. No additional restrictions or controls apply to devices with LCD screens; however, the Contractor shall remove the LCD screen and seal it in plastic following any evidence that the backlight failed.
(3) For Submarines, any use of mercury containing items must be approved as required by the Nuclear Powered Submarine Atmosphere Control Manual (S9510-AB-ATM-010/U) Volume 1.
(4) The Contractor shall ensure that mercury and mercury compounds do not contact hardware surfaces in systems covered by NAVSEA Manual NAVSEA 0989-064-3000 entitled Cleanliness Requirements for Nuclear Propulsion Plant Maintenance and Construction, submarine air systems, level I systems per NAVSEA Publication 0948-LP-045- 7010, NAVSEA Material Control Standard, or the submarine safety program (SUBSAFE) surfaces during maintenance or repair. Such hardware is designated as mercury-free. The Contractor shall ensure that all other hardware that could be structurally degraded by contamination with elemental mercury or reactive mercury compounds is separated from it by sufficient distance, or boundaries of containment that effectively prevents contact in all but the most extreme circumstances.
(5) The Contractor shall check any hardware surfaces in the above systems which are known or suspected to have come in contact with mercury or mercury compounds for evidence of structural degradation and external mercury contamination. The existence of external mercury contamination can be determined following MIL-STD-2041D entitled Control of Detrimental Materials.
(6) The presence of mercury in a product may be determined by checking product labeling on material safety data sheets or safety data sheets. Chemical analysis is not required.
(7) The Contractor shall dispose of any mercury and mercury compounds in accordance with OPNAV Manual (OPNAV M-5090.1) entitled Environmental Readiness Program Manual of 10 January 2014.
(8) If the use of mercury or mercury compounds cannot be avoided, a risk assessment and waiver request, if required, must be performed and submitted per the NAVSEA Hazardous Material Avoidance Process (T9070-AL-DPC-020/077- 2).
This is the start of the file's text. The full file is on GovTribe.