This document is a Contract Data Requirements List (CDRL) for the 100 Ton Chiller System procurement with contract number N3904026Q3090. The CDRL specifies seven data deliverables required throughout contract performance, all subject to DD Form 1423 requirements and referencing DoDM 5010.12 for detailed instructions.

The seven required data items include: (001) Certification Data Report for lifting and handling with padeye certification per DI-MISC-82386, due at component delivery with subsequent submissions required when new components are delivered or replaced; (002) Hydrostatic Test Report for pressure testing per DI-QCIC-82089, due at component delivery with testing by an independent certified vendor within one calendar year of scheduled arrival; (003) Calibration Certificate/Report for flow meter calibration per DI-QCIC-80798C, due at component delivery with subsequent submissions at each calibration cycle by a licensed metrology laboratory within five years of delivery; (004) Contractor's Personnel Roster identifying emergency repair points of contact per DI-MGMT-81834A, due upon personnel assignment with updates within one day of personnel changes; (005) Equipment Technical Manual (Sanitized) providing technical/operating instructions and equipment data sheets per DI-TMSS-81675A, due upon component delivery with updates as manuals are revised; (006) Maintenance Support Plan detailing preventive maintenance schedules per DI-ILSS-81225, due upon delivery with updates for new components or manufacturer changes; and (007) Maintenance Service Report providing technical field inspection reports per DI-MGMT-80995A, due seven days after delivery with weekly submissions required one day after each maintenance/inspection instance. All distribution requires waterproof case affixture to equipment and electronic submission through Wide Area Workflow (WAWF). The requiring office is Code 230 with Project TSZM identified as an additional distribution recipient for items 004, 006, and 007.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED (Updated 20260326)

CONTRACT DATA REQUIREMENTS LIST

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A, B, C □ TOP □ TM ~ OTHER MISC

D. SYSTEM/ITEM

100 TON ClilLLER SYSTEM

IE. CONTRACT/PR NO. F. CONTRACTOR

NIA

1. DATA ITEM NO.

2. TITLE OF DATA ITEM

CERTIFICATION DATA REPORT

3. SUBTITLE

Lifting & Handling w/Padeye Certification

4. AUTHORITY (Data Acquisition Document No.)

DI-MISC-82386 1

5. CONTRACT REFERENCE

SOW Para. 5.5.l.

6. REQUIRING OFFICE

Code230

9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION 7. 00 250 REQ

DD REQUIRED lTIME 1--------~~-------I

8. APP CODE

NIA

16. REMARKS

A 11. AS OF DATE

See Block 16

5DAC

13. DATE OF SUBSEQUENT

SUBMISSION

See Block 16

Block 11 As of Date shall be most up to date certification for each component.

b. COPIES

a. ADDRESSEE Final Draft 1-------1

Reg Repro

Code420

Code230

Block 13. Date of Subsequent Submissions shall be if any new component are delivered or replaced, and if 1----------11---+---+---1 any updated certifications.

Block 14. Distribution shall be affixed to the machine in a waterproof case and electronic submissions will be submitted through Wide Area Workflow (WAWF).

G. PREPARED BY H. SIGNATURE I. APPROVED BY

15.TOTAL ------i·► 0 0

J. SIGNATURE

Andrea Williams ■ Amanda Kenney DANlEIA. - DA.N. WILLIAMS.ANDREA.I1:=::Jt:~~::_ _______ jiKENNEY~ ~ .AMAN .. ...,_., ----------------DD FORM 1423 FEB 2024 UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

~7. PRICE GROUP

na. ESTIMATED

TOTAL PRICE

(Updated 20260326)

INSTRUCTIONS FOR COMPLETING DD FORM 1423

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: IDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator)

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CORL

Item H. Date CORL was prepared and signature of preparer of CORL

Item I. Name of CORL approval authority

Item J. Date CORL was approved and signature of CORL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering To add or delete additional data items, point and dick the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-0f date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additionaVdarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

DD FORM 1423, FEB 2024

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group L Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be induded under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government

b. Group IL Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control , or quality of the data item.

Estimated Price - Costs to be induded under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government

c. Group Ill. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be induded under Group Ill are the administrative and other expenses related to reproducing and delivering such data item to the Government

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not indude any amount for rights in data. The Government's rights to use the data shall be governed by the pertinent provisions of the contract

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A, B, C □TOP D™ ~OTHER QCIC

D. SYSTEM/ITEM IE. CONTRACT/PR NO. F. CONTRACTOR

100 TON ClilLLER SYSTEM NIA

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

002 HYDROSTATIC TEST REPORT Hydrostatic Pressure Test Report

4. AUTHORITY (Data Acquisition Document No.)

5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-QCIC-82089 SOW Para. 4.3. & 5.5.2. Code230

7. 0 0 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

DD

REQUIRED

lTIME b. COPIES See Block 16

8. APP CODE A 11. AS OF DATE 13. DATE OF SUBSEQUENT a. ADDRESSEE Final SUBMISSION Draft

NIA NIA See Block 16 Reg Repro

16. REMARKS Code420 l

Block 12. Date of First Submission will be at delivery of component. Code230 l

Block 13. Date of Subsequent Submissions shall be if any new component are delivered or replaced.

Hydrostatic test by an independent ( of the Contractor) and certified Vendor shall be within one calendar year of scheduled Arrival Date of the equipment

Block 14. Block 14. Distribution shall be affixed to the machine in a waterproof case and electronic submissions shall be submitted through Wide Area Workflow (WA WF).

15.TOTAL .

0 0 0

G. PREPARED BY H. SIGNATURE I. APPROVED BY J. SIGNATURE

Andrea Williams Will.IAMS.ANDREA.. ~~AnNmJ..A lj) Amanda Kenney

KENNEY .AMAN .. ...,_.,

DD FORM 1423, FEB 2024

DANlEIA--

UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

DA.N

~7. PRICE GROUP

na. ESTIMATED

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: IDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator)

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CORL

Item H. Date CORL was prepared and signature of preparer of CORL

Item I. Name of CORL approval authority

Item J. Date CORL was approved and signature of CORL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering To add or delete additional data items, point and dick the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-0f date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additionaVdarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

DD FORM 1423, FEB 2024

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group L Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be induded under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government

b. Group IL Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control , or quality of the data item.

Estimated Price - Costs to be induded under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government

c. Group Ill. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be induded under Group Ill are the administrative and other expenses related to reproducing and delivering such data item to the Government

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not indude any amount for rights in data. The Government's rights to use the

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A,B, C □TOP D™ ~OTHER QCIC

D. SYSTEM/ITEM IE. CONTRACT/PR NO. F. CONTRACTOR

100 TON ClilLLER SYSTEM NIA

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

003 CALIBRATION CER'IIBCATF/REPORT Flow Meter Calibration Certificate

4. AUTHORITY (Data Acquisition Document No.)

5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-QCIC-80798C SOW Para. 4.6. & 5.5.3. Code230

7. 00250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

DD

REQUIRED

lTIME b. COPIES See Block 16

8.APP CODE A 11. AS OF DATE 13. DATE OF SUBSEQUENT a. ADDRESSEE Final SUBMISSION Draft

NIA NIA See block 16 Reg Repro

16. REMARKS Code420 l

Block 12. Date of First Submission will be at delivery of component. Code230 l

Block 13. Subsequent Submissions of calibration certification/reporting will be required at each calibration cycle. The calibration performed by a licensed Metrology Laboratory within five (5) years of its scheduled delivery shall be provided five (5) days after test completion but within five (5) year of system delivery with flow meter assembly.

Block 14. Distribution shall accompany flow meter assembly and electronic submissions shall be submitted through Wide Area Workflow (WA WF).

15.TOTAL .

0 0 0

G. PREPARED BY H. SIGNATURE I. APPROVED BY J. SIGNATURE

Andrea Williams WILLIAMS.ANDREA.--- DANlEIA---

Amanda Kenney KENNEY.AMAN---

DA.N.

DD FORM 1423, FEB 2024 UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

~7. PRICE GROUP

na. ESTIMATED

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: IDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator)

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CORL

Item H. Date CORL was prepared and signature of preparer of CORL

Item I. Name of CORL approval authority

Item J. Date CORL was approved and signature of CORL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering To add or delete additional data items, point and dick the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-0f date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additionaVdarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

DD FORM 1423, FEB 2024

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group L Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be induded under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government

b. Group IL Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control , or quality of the data item.

Estimated Price - Costs to be induded under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government

c. Group Ill. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be induded under Group Ill are the administrative and other expenses related to reproducing and delivering such data item to the Government

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not indude any amount for rights in data. The Government's rights to use the

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A, B, C □TOP D™ ~OTHER MGMT

D. SYSTEM/ITEM IE. CONTRACT/PR NO. F. CONTRACTOR

100 TON ClilLLER SYSTEM NIA

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

004 CONTRACTOR'S PERSONNEL ROSTER Emergency Repair Point of Contact

4. AUTHORITY (Data Acquisition Document No.) 6. REQUIRING OFFICE

DI-MGMT-81834A 1

5. CONTRACT REFERENCE

SOW Para. 5.5.2. Code 230, Project TSZM

7. 0 0 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION

DD

REQUIRED

lTIME 5DAC

8. APP CODE A 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

NIA See Block 16 See Block 16

16. REMARKS

Block 4. For DI-MGMT81834A, omit 2.1. j-n andp-s. See SOW Paragraph 5.5.2.

Block 11. As of Date will be for date that personnel are assigned and provided for contract points of contact.

Block 13. Date of Subsequent Submission if a change to POCs for this contract are made to be provided (1) Day upon POC changes.

Block 14. Distribution shall be affixed to the machine in a a waterproof case and any electronic submissions shall be submitted through Wide Area W orldlow (WA WF).

G. PREPARED BY

Andrea Williams

DD FORM 1423, FEB 2024

H. SIGNATURE I. APPROVED BY

WILLIAMS.ANDREA.---

DANIEJ.A_,,

Amanda Kenney

UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

14. DISTRIBUTION

b. COPIES

a. ADDRESSEE Draft

Final

Reg Repro

Code420 l

Code230 l

Project TSZM l

15.TOTAL .

0 0 0

J. SIGNATURE

KENNEY.AMAN---

DA.N

~7. PRICE GROUP

na. ESTIMATED

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: IDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator)

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CORL

Item H. Date CORL was prepared and signature of preparer of CORL

Item I. Name of CORL approval authority

Item J. Date CORL was approved and signature of CORL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering To add or delete additional data items, point and dick the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-0f date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additionaVdarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

DD FORM 1423, FEB 2024

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group L Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be induded under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government

b. Group IL Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control , or quality of the data item.

Estimated Price - Costs to be induded under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government

c. Group Ill. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be induded under Group Ill are the administrative and other expenses related to reproducing and delivering such data item to the Government

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not indude any amount for rights in data. The Government's rights to use the

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A, B, C □TOP D™ ~OTHER TMSS

D. SYSTEM/ITEM IE. CONTRACT/PR NO. F. CONTRACTOR

100 TON ClilLLER SYSTEM NIA

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

005 EQUIP:MENT TECHNICAL MANUAL (SANITIZED) Technical/Operating Instructions & EDS

4. AUTHORITY (Data Acquisition Document No.)

5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-1MSS-81675A SOW Para. 5.5.5, 5.5.6. & 5.5.8. Code230

7. 0 0 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

DD

REQUIRED

lTIME b. COPIES 5DAC

8. APP CODE A 11. AS OF DATE 13. DATE OF SUBSEQUENT a. ADDRESSEE Final SUBMISSION Draft

NIA See Block 16 See Block 16 Reg Repro

16. REMARKS Code420 l

Block 11. As of Date shall be the most recent manual, instruction and Equipment Data Sheet (EDS). Code230 l

Block 13. Date of Subsequent Submission shall be if any updates are made to manuals, instructions and

EDS.

Block 14. All electronic submissions shall be submitted through Wide Area Worldlow (WA WF).

15.TOTAL .

0 0 0

G. PREPARED BY H. SIGNATURE I. APPROVED BY J. SIGNATURE

Andrea Williams WILLIAMS.ANDREA.---

DANIEJ.A_,,

Amanda Kenney KENNEY.AMAN---

DA.N

DD FORM 1423, FEB 2024 UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

~7. PRICE GROUP

na. ESTIMATED

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: IDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator)

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CORL

Item H. Date CORL was prepared and signature of preparer of CORL

Item I. Name of CORL approval authority

Item J. Date CORL was approved and signature of CORL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering To add or delete additional data items, point and dick the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-0f date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additionaVdarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

DD FORM 1423, FEB 2024

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group L Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be induded under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government

b. Group IL Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control , or quality of the data item.

Estimated Price - Costs to be induded under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government

c. Group Ill. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be induded under Group Ill are the administrative and other expenses related to reproducing and delivering such data item to the Government

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not indude any amount for rights in data. The Government's rights to use the

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A, B, C □TOP D™ ~OTHER ILSS

D. SYSTEM/ITEM IE. CONTRACT/PR NO. F. CONTRACTOR

100 TON ClilLLER SYSTEM NIA

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

006 MAIN1ENANCE SUPPORT PLAN Preventive Maintenance Plan with Schedules

4. AUTHORITY (Data Acquisition Document No.)

5. CONTRACT REFERENCE 6. REQUIRING OFFICE

DI-ILSS-81225 SOW Para. 5.3.2. & 5.5.7. Code 230, Project TSZM

7. 0 0 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION

DD

REQUIRED

lTIME b. COPIES 5DAC

8. APP CODE A 11. AS OF DATE 13. DATE OF SUBSEQUENT a. ADDRESSEE Final

NIA NIA

SUBMISSION

See Block 16

16. REMARKS

Block 13. Subsequent Submission shall be required if any new components are delivered or replaced, and if any updates to the preventive maintenance plan by the Original Equipment Manufacturer.

Block 14. All Electronic submissions shall be submitted through Wide Area W orldlow (WA WF).

G. PREPARED BY

Andrea Williams

DD FORM 1423, FEB 2024

H. SIGNATURE I. APPROVED BY

WILLIAMS.ANDREA.---

DANIEJ.A_,,

Amanda Kenney

UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

Draft Reg Repro

Code420 l

Code230 l

Project TSZM l

15.TOTAL .

0 0 0

J. SIGNATURE

KENNEY.AMAN---

DA.N

~7. PRICE GROUP

na. ESTIMATED

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: IDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator)

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CORL

Item H. Date CORL was prepared and signature of preparer of CORL

Item I. Name of CORL approval authority

Item J. Date CORL was approved and signature of CORL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering To add or delete additional data items, point and dick the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-0f date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additionaVdarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

DD FORM 1423, FEB 2024

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group L Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be induded under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government

b. Group IL Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control , or quality of the data item.

Estimated Price - Costs to be induded under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government

c. Group Ill. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be induded under Group Ill are the administrative and other expenses related to reproducing and delivering such data item to the Government

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not indude any amount for rights in data. The Government's rights to use the

A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY:

A, B, C □TOP D™ ~OTHER MGMT

D. SYSTEM/ITEM IE. CONTRACT/PR NO. F. CONTRACTOR

100 TON ClilLLER SYSTEM NIA

1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE

007 MAIN1ENANCE SERVICE REPORT Technical Field Inspection Report

4. AUTHORITY (Data Acquisition Document No.) 6. REQUIRING OFFICE

DI-MGMT-80995A 1

5. CONTRACT REFERENCE

SOW Para. 5.3.3 Code 230, Project TSZM

7. 0 0 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION

DD

REQUIRED

WEEKLY See Block 16

8. APP CODE A 11. AS OF DATE 13. DATE OF SUBSEQUENT

SUBMISSION

NIA NIA See Block 16

16. REMARKS

Block 12. Date of First Submission will be seven (7) Days after delivery of components.

Block 13. Subsequent Submission will be required(!) Day after each instance the maintenance/inspection is performed.

Block 14. Send all electronic submissions through Wide Area Workflow (WA WF).

G. PREPARED BY

Andrea Williams

DD FORM 1423, FEB 2024

H. SIGNATURE I. APPROVED BY

WILLIAMS.ANDREA.---

DANIEJ.A_,,

Amanda Kenney

UNCLASSIFIED

PREVIOUS EDITION MAY BE USED.

14. DISTRIBUTION

b. COPIES

a. ADDRESSEE Draft

Final

Reg Repro

Code420 I

Code230 I

Project TSZM I

15.TOTAL .

0 0 0

J. SIGNATURE

KENNEY.AMAN---

DA.N

~7. PRICE GROUP

na. ESTIMATED

(See DoDM 5010.12 for detailed instructions.)

FOR GOVERNMENT PERSONNEL

Item A. Self-explanatory.

Item B. Self-explanatory.

Item C. Mark (X) appropriate category: IDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.

Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator)

Item E. Self-explanatory (to be filled in after contract award).

Item F. Self-explanatory (to be filled in after contract award).

Item G. Name of preparer of CORL

Item H. Date CORL was prepared and signature of preparer of CORL

Item I. Name of CORL approval authority

Item J. Date CORL was approved and signature of CORL approval authority.

Item 1. See DFARS Subpart 204.71 for proper numbering To add or delete additional data items, point and dick the plus or minus sign to the right of Block J.

Item 2. Enter title as it appears on data acquisition document cited in Item 4.

Item 3. Enter subtitle of data item for further definition of data item (optional entry).

Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.

Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).

Item 6. Enter technical office responsible for ensuring adequacy of the data item.

Item 7. Specify requirement for inspection/acceptance of the data item by the Government

Item 8. Specify requirement for approval of a draft before preparation of the final data item.

Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref DoDI 5230.24).

Item 10. Specify number of times data items are to be delivered.

Item 11. Specify as-0f date of data item, when applicable.

Item 12. Specify when first submittal is required.

Item 13. Specify when subsequent submittals are required, when applicable.

Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.

Item 15. Enter total number of draft/final copies to be delivered.

Item 16. Use for additionaVdarifying information for Items 1 through 15.

Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.

Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.

Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.

DD FORM 1423, FEB 2024

FOR THE CONTRACTOR

Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.

a. Group L Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.

Estimated Price - Costs to be induded under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government

b. Group IL Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control , or quality of the data item.

Estimated Price - Costs to be induded under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government

c. Group Ill. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.

Estimated Price - Costs to be induded under Group Ill are the administrative and other expenses related to reproducing and delivering such data item to the Government

d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.

Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost

Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.

These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not indude any amount for rights in data. The Government's rights to use the

CDRL_001_DD1423_Certification_Data _Report _Padeye_100T_CHILLER_SYSTEM_Redacted
CDRL_002_DD1423_Hydrostatic_Test_Report_100T_CHILLER_SYSTEM_Redacted
CDRL_003_DD1423_Calibration_Certificate_Report_100T_CHILLER_SYSTEM_Redacted
CDRL_004_DD1423_Contractor's_Personnel_Roster_100T_CHILLER_SYSTEM_Redacted
CDRL_005_DD1423_Equipment Technical_Manual_100T_CHILLER_SYSTEM_Redacted
CDRL_006_DD1423_Maintenance_Support_Plan_100T_CHILLER_SYSTEM_Redacted
CDRL_007_DD1423_Maintenance_Service_Report_100T_CHILLER_SYSTEM_Redacted
NIA:
1 DATA ITEM NO 001 2 TITLE OF DATA ITEM CERTIFICATION DA TA REPORT:
Code 420:
Code 230:
Row1:
Row1_2:
Row1_3:
Row1_4:
Row2:
Row2_2:
Row2_3:
Row2_4:
Row3:
Row3_2:
Row3_3:
Row3_4:
Row4:
Row4_2:
Row4_3:
Row4_4:
Row5:
Row5_2:
Row5_3:
Row5_4:
Row6:
Row6_2:
Row6_3:
Row6_4:
Row7:
Row7_2:
Row7_3:
Row7_4:
Row8:
Row8_2:
Row8_3:
Row8_4:
Row9:
Row9_2:
Row9_3:
Row9_4:
Row10:
Row10_2:
Row10_3:
Row10_4:
Row11:
Row11_2:
Row11_3:
Row11_4:
Row12:
Row12_2:
Row12_3:
Row12_4:
Row13:
Row13_2:
Row13_3:
Row13_4:
Row14:
Row14_2:
Row14_3:
Row14_4:
Row15:
Row15_2:
Row15_3:
Row15_4:
Row16:
Row16_2:
Row16_3:
Row16_4:
Row17:
Row17_2:
Row17_3:
Row17_4:
Row18:
Row18_2:
Row18_3:
Row18_4:
Row19:
Row19_2:
Row19_3:
Row19_4:
Row20:
Row20_2:
Row20_3:
Row20_4:
Row21:
Row21_2:
Row21_3:
Row21_4:
Row22:
Row22_2:
Row22_3:
Row22_4:
Row23:
Row23_2:
Row23_3:
Row23_4:
Row24:
Row24_2:
Row24_3:
Row24_4:
Row25:
Row25_2:
Row25_3:
Row25_4:
Row26:
Row26_2:
Row26_3:
Row26_4:
Row27:
Row27_2:
Row27_3:
Row27_4:
Row28:
Row28_2:
Row28_3:
Row28_4:
Row29:
Row29_2:
Row29_3:
Row29_4:
Row30:
Row30_2:
Row30_3:
Row30_4:
Row31:
Row31_2:
Row31_3:
Row31_4:
Row32:
Row32_2:
Row32_3:
Row32_4:
Row33:
Row33_2:
Row33_3:
Row33_4:
Row34:
Row34_2:
Row34_3:
Row34_4:
Row35:
Row35_2:
Row35_3:
Row35_4:
Row36:
Row36_2:
Row36_3:
Row36_4:
Row37:
Row37_2:
Row37_3:
Row37_4:
Row38:
Row38_2:
Row38_3:
Row38_4:
undefined:
Text5: A001
Text6: N3904026Q3090

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .