N3904025Q3025 Attachment 1 - Statement of Work.pdf

PDF 237 KB Posted

Attached to
Solicitation for 100 Ton Chiller - Portsmouth Naval Shipyard
Solicitation number
N3904025Q3025
Issued by

About this file

This document is a Statement of Work (SOW) for leasing a temporary Chiller System for the Portsmouth Naval Shipyard (PNSY). The system must include a 100-ton air-cooled chiller unit, a pump capable of 240 gpm at 130 ft, 400 ft of 4" non-collapsible hoses, 8 90-degree elbows, and heat tape. Key technical requirements include non-ferrous water-contacting components, operation in 0-100°F ambient temperatures, process water temperature range of 38-60°F, and ability to operate at 25% load. The chiller must have a minimum of two refrigerator circuits, an HMI user interface, and be capable of continuous operation under varying ambient conditions.

The contractor is responsible for preventative maintenance, weekly equipment inspections, providing technical support, and delivering documentation including hydrostatic test reports, flow meter calibration certificates, and operation manuals. Delivery specifications require the equipment to be fully assembled, tested, and in first-class operating condition. Security requirements mandate that vendor personnel be US citizens with appropriate identification. The SOW includes a compliance checklist (Table E1) that vendors must complete to demonstrate their equipment meets all specified requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Spec #:

100TNCHWNM2052925

CHILLER SYSTEM

STATEMENT OF WORK

1. SCOPE

1.1. Portsmouth Naval Shipyard (PNSY) is seeking to lease a temporary Chiller System that meets the specifications and requirements of this document.

2. REFERENCES

2.1. Issues of Publications - The following documents in effect on the date of this requested proposal is a part of this specification to the extent applicable, or as specified herein. Within the specification, they shall be referred to by their basic designation only.

2.1.1. Government

2.1.1.1. PI 354: Ships Systems; Freeze Prevention

2.1.1.2. US Federal standard A-A-59326: Standard for cam action couplings.

2.1.2. Non-Government

2.1.2.1. ARI Standard 410

2.2. Order of precedence - In the event of conflict between the text of this specification and that of the references cited above, the text of this specification shall take precedence. Nothing in this specification, however, shall supersede applicable laws or regulations unless a specific exemption has been obtained.

3. REQUIREMENTS

3.1. Component List

3.1.1. Required components.

PIECE NO. QTY. NAME OF PART TABLE

CW-01 1 Chiller Unit 1 (1A) CW-02 1 Pump 2 (2A) H-01 400 FT Hose 3 PC-01 8 90 Degree Elbows 4

TABLE 1: Chiller Mechanical Data Material Constraint All components that come in contact with the process water shall be Non-Ferrous Tonnage (Max) 100 Cooling (Condenser) Air Cooled PSI (Working Pressure) Not to exceed hose rating **** Turndown Capable of operation at 25% Load at 4:1 Turndown

Operating Temp (Ambient) 00F - 1000F

Process water temperature 380F-600F

Process Water Supply/Return Gages Range of 200F-1000F with 10F resolution

Connection Type Non-Ferrous/Galvanized A-A-59326 Plug (Supply) Socket (Return) Connection Size 4" Nominal Flow switch Integrated into process water piping. Note: Cannot be PSI Gages

Flow Meter (Calibrated) Electronic (Not Axial Turbine) 50-400 gpm with a minimum accuracy of 1% of reading and 1 gpm minimum resolution. Calibrated within 5 years.

Hot Gass By-Pass Shall Have for low flow conditions Footprint (Max) 180in x 90in Weight (Max) 15000lb

Lifting/Handline Must have forklift pockets and padeyes integrated into the machine designed/tested for machines nameplate weight rating

HMI for user interface Shall have to log parameters and adjust setpoint i.e. process water temperature.

Compressor and Refrigerator circuits Minimum of 2

TABLE 1A: Chiller Electrical Data

Power 480VAC, 3PH, 60HZ, 200FLA (max)

Power Source Must be energized by a dedicated circuit, discrete from the pump power source regardless of if integrated or separated from the chiller unit

Power Supply Connection Camlock 16 Series, Type J style connection with min 3ft whips or box mounted.

Electrical Components Nema 3 (4) to allow for unsheltered outdoor use

TABLE 2: Pump Mechanical Data

Material All components that come into contact with the process water shall be Non-Ferrous Size (min) 240gpm @ 130ft @ 1750 RPM Connection Type Non-Ferrous/Galvanized A-A-59326 Plug (Supply) Socket (Return) Connection Size 4" Nominal Pressure Gages Range: 0-200 PSI. Shall be installed on the suction and discharge side of pump.

Rated to 25% over operating range

Layout Can either be integral to chiller or stand-alone unit Lifting/Handling If stand alone, shall have forklift pockets and rigging pad rated to lift the piece of equipment Footprint (standalone only)

MAX

48" x 48" (includes the rigging gear)

Weight Pump weight shall be either etched into a location on the unit or certification provided to COAR (POC Provided in Note Section:)

TABLE 2A: Pump Electrical Data

Power 480VAC, 3 PH, 60HZ Power Source Must be energized by a dedicated circuit, discrete from the chiller power source regardless of if integrated or spirited from the chiller unit

Isolation Switch Nema 4 rated knife switch. Sized in accordance with Pump nameplate data.

Pump Supply Connection Type

Sized and rated in accordance with pump nameplate data.

TABLE 3: Hoses

Type Non-Collapsible suction hose with exterior cover shall be a thick rubber (Buna-N)

Size 4" Connection Type Non-Ferrous / Galvanized A-A-59326 Plug (Supply) Socket (Return) Orientation Plug on one end and socket on the other end of hose Required individual length (max) 25ft lengths to equal total of 400ft Required Total Length (min) 16 lengths of 25ft hose for a total of 400ft Working Pressure Rating Rated to Pump max output Pressure.

TABLE 4: Elbows

Type 90-Degree Material Non-Ferrous / Non-Galvanized End Connections Non-Ferrous / Non-Galvanized A-A-59326 Plug (Supply) Socket (Return) Total Eight (8)

TABLE 5: Heat Tape

Chiller, Pump and Hoses

The vendor shall determine which exposed piping components require electrical heat trace and insulation. The Vendor shall provide the electrical heat trace in the proper lengths with the Nema watertight l5-15P fittings and shall also provide the insulation. The Vendor shall wrap the Electrical Heat Trace in the location – orientation – methodology as determined by the vendor; obtain the appropriate insulation thickness; and install the insulation over the Electrical Heat Trace. All heat trace and freeze prevention methods shall meet the requirements of reference 2.1.1.1. Similar to all of the other Electrical Heat Trace for freezing prevention, the electrical power source shall be from the Secure Power Facility provided by the Shipyard. Electrical heat trace shall be 110 VAC. All gage lines need to be heat traced as well.

4. NOTES:

4.1. Chiller Capacity & Utilities:

4.1.1. Cooling: The minimum nominal chilled water capacity shall be as indicated with the actual capacity, based on an ambient temperature of 95ºF dry bulb with an Entering Water Temperature (EWT) of 52ºF and a Leaving Water Temperature (LWT) of 42ºF, to be not less than 5% of the desired nominal capacity. The unit capacity shall not be greater than one-third above (+⅓) the minimum specified capacity and shall be able to run continuously at one-quarter of that unit's stated capacity.

4.1.2. Automatic Operation, Regulation, & Controls: The Chiller shall be equipped with an automatic variable capacity control requiring only initial temperature adjustment from 38 to 60°F by the operator. The Chiller shall be fully controllable under a wide range of loads even though the daily and seasonal ambient temperatures vary greatly.

4.1.3. Design & Component Integration: The Chiller can either be an integrated Chilled Water Unit capable of both refrigerating and pressurizing water or can be two separate types of components consisting of a Chiller that refrigerates water and a Pump Module that pressurizes water. The unit / modules shall be designed for continuous operation at minimal loading (i.e. one-quarter of full capacity for refrigeration & one-third of full capacity for pumping) despite extreme ambient conditions (e.g. –10 to +100°F and 0 to 100% RH).

4.2. Coolant Free:

Besides manifolds and hose assemblies that are normally flushed and tested, all machinery conveying chilled water such as: the Chiller, Pump and machines with a chilled water coil; shall arrive with no coolant of any type in its piping (i.e. No Water & No Anti-Freeze).

4.3. Chilled Water Hose Assembly / Manifold Construction / Cooling Coil Hydrostatic Testing:

All Chilled water connectors / fittings must be quick disconnect style fittings meeting the requirements defined in reference 2.1.1.2. Chilled Water Hose assemblies shall be non-collapsible and the camlock fittings shall be attached to the hose material via the more secure, newer type, crimp style hose fitting via a single specified diameter, elongated sleeve length and not from the less secure, older type, band clamp style hose fitting via multiple universal diameters, shorter ferrules. Gaskets for couplings shall be pre-installed inside the female coupling(s) of hose assemblies and manifolds. The gasket shall be inspected for presence, tight fit, and lack of deterioration. Gaskets shall not protrude into the waterway. A gasket with a smaller diameter than that of the recess can cause a leaky connection when pressure is applied.

Hose/manifold/valve assemblies and all cooling coils shall be hydrostatically tested with new hose gaskets for Strength and Tightness and/or Valve Seat Leakage by an independent (of the Contractor) and certified Vendor to a minimum of 150 psig for five minutes and visually inspected and/or internal valve leakage measured while pressurized. Hydrostatic test date shall be within one calendar year of scheduled Arrival Date of the equipment. Hoses/manifolds/valve assemblies shall have a banded identification (ID) tag or label attached to the assembly displaying the hydrostatic test results. The Hydrostatic Test Certificates issued by the certified testing facility shall provide a copy of the certificates to the Contracting Officer Representative (COR).

4.4. Phase Rotation:

To prevent or identify an out-of-phase electrical power situation, three-phase machines shall include either:(a) a reverse phase relay and/or meter that identifies an out-of-phase condition and prevents operation in which such a condition could cause damage or (b) an arrow prominently displayed at an appropriate location on the machine's housing to indicate the proper direction of shaft rotation with the ability to observe a portion of the shaft after a momentary application of power (a.k.a. jog or bump). A reverse phase relay is not required nor desired for VFD motors, however, the VFD shall have a jog button so as to verify correct rotation.

4.5. Supplemental Equipment:

For the protection and cleanliness of the machinery components, all chilled water connection points shall be shipped with plug/cap fittings.

4.6. Hydronic Flow Meter:

Attached to the Chiller and its associated pump shall be a continuous reading liquid flow meter, preferably, in-line with flow. The type of meter must be Electronic Metering. The physical positioning of the instrument shall be downstream of the Chiller immediately after its discharge. The flow meter assembly shall be rated for 150 psig; dimensioned for the nominal diameter pipework. The instrument shall be calibrated by a licensed Metrology Laboratory within five years of its scheduled delivery with certified calibration test results accompanying the flow meter assembly and reported via E-mail to the Contract Officer Representative

(COR).

4.7. Freeze protection:

4.7.1. Season:

For cold weather geographic regions including Portsmouth NH and New London CT, the all-season chiller and its accompanying pump are machines that have the potential for its chilled water coils or other piping components to freeze sometime during the Freezing Prevention season (Oct 1st – Apr 30th) causing considerable damage to the unit.

4.7.2. Low Ambient Temperature & Low Cooling Load:

As an all-season (year-round) continuously operating chiller, the unit must be able to function at very low ambient temperatures and at low cooling loads of one-quarter or less of its full-load or a combination of both substantially below freezing weather and low load conditions. This low ambient and low load chiller shall be capable of producing 55ºF chilled water with no antifreeze during the freezing prevention season.

4.7.3. Seasonal Resets of The Leaving Chilled Water Temperature:

Prior to commencement of the freezing prevention season, the Vendor shall reset the discharge leaving chilled water temperature from 42ºF to 55ºF. Soon after (within a month of) termination of the freezing prevention season, the Vendor shall reset the discharge leaving chilled water temperature from 55ºF to 42ºF thus, maximizing the potential load capacity of the chiller. The Vendor shall schedule and coordinate with the Project.

4.8. Noise Requirement:

When operating at full speed, noise levels must not be over 105 dB[A] and preferably, 85 dB[A] or less at six feet from the unit or frame unless a quieter noise level is specified. A hearing protection safety placard shall be posted on each machine generating more than 85 dB[A] at the unit's edge or frame.

4.9. Machinery / Equipment Tagging and Markings:

Fluid piping inlet(s) / outlet(s) must be clearly marked. Machinery and itemized equipment require tagging to show Project Number / Technical Specification Identification (ID) Number.

4.10. Vendor Identification of Itemized and Ancillary Equipment:

The Contractor shall uniquely tag and permanently mark all of its ancillary and itemized equipment / hardware (e.g. manifolds, hose assemblies, pipe fittings, duct adapters, ducting, etc.) so as to differentiate from that owned by either the Shipyard or other Vendors.

5. RESPONSIBILITES

5.1. Government

5.1.1. Equipment Technical Evaluation: C230 Engineering

5.1.2. Receipt Inspection: COR & Technical Point of Contact (TPOC)

5.1.3. Coordination of equipment delivery & returns: COR & TPOC

5.1.4. Schedule equipment service, repair, and training: COR & TPOC

5.2. Contractor

5.2.1. Use Table E1 of Enclosure 1 to verify conformity with the technical requirements.

5.2.2. The equipment will be operating around-the-clock under a rigorous deployment performance schedule.

Within twenty-four (24) hours of initial notification of the need for repair, the Contractor shall have a knowledgeable and equipped technician on the jobsite fully prepared to repair the rental equipment. The defective unit(s) shall be repaired within forty-eight (48) hours of initial notification or, if the original defective unit(s) cannot be made operational, replaced within seventy-two (72) hours of initial notification. If the equipment failure is not the fault of the Government, the Contractor shall bear all costs associated with its repair and/or replacement.

5.2.3. The vendor shall provide technical support to PNSY project personnel as required.

5.3. Maintenance

5.3.1. Except for daily surveillance checks, the Contractor is responsible for all equipment preventative maintenance and repairs for the duration of the lease. Coordinate maintenance with Shipyard Temporary Services Zone Manager.

5.3.2. The vendor shall provide Preventative Maintenance (PM) schedules which are equipment specific. The PM shall meet all requirements determined by the Original Equipment Manufacture (OEM). The vendor shall provide the PM documentation and schedules to the COR/TPOC for review and approval prior to being considered for a successful Bid. The routine PM plan for each piece of equipment shall include a comprehensive list of the components to be serviced as well as identifying the service frequency. (e.g. all consumables to be replaced, bearing grease points, belt replacement / tensioning, filter changes, refrigerant charge, oil changes, other lubrication, coolant refills, liquid top-offs, etc.) All PMs conducted shall include a technical service report identifying component, maintenance conducted, date, and next scheduled PM date.

Copies of all reports shall be delivered to the project COR and the Temporary Service Zone Manager

(TSZM).

5.3.3. In addition to providing routine preventative maintenance, the vendor shall provide a service technician on a weekly basis for the duration of the lease to perform weekly equipment inspections. Weekly equipment inspections shall consist of checking all functional operating parameters of each individual piece of equipment. This shall include but is not limited to: verifying correct equipment performance and operation, checking for diagnostic or trouble codes, verification of chilled water coils performance, verify pump operation, motor speed, and differential pressure, Chiller performance operation, etc. Weekly equipment inspections shall include a technical field report identifying the status of each piece of equipment and shall include all data / measurement points verified. All reports are delivered to the COR upon completion of the PM services.

5.3.4. The vendor shall provide a knowledgeable service technician to cover the repair of all equipment deficiencies and malfunctions. The response time for the repair or replacement of deficient equipment shall meet the requirements defined in section 5.2.2.

5.4. Training

5.4.1. The Contractor is responsible for and shall provide training sessions to Shipyard Personnel on the operation and setup of all equipment. Training shall be available throughout the duration of the lease to accommodate equipment swap out and seasonal equipment operation.

5.5. Deliverables – In addition to all required equipment, technical documentation shall also be provided electronically to the project COR. Minimally, the documentation shall consist of:

5.5.1. Lifting & Handling the equipment with its padeye(s) Certification.

5.5.2. Hydrostatic Pressure Test Reports.

5.5.3. Flow Meter Calibration Certificate.

5.5.4. Points of contact with telephone numbers for requesting emergency repair regardless of time or type of day.

5.5.5. Technical Instructions (TIs) such as an Operations & Maintenance Manual, Controls Manual, and/or Mechanical/Electrical Manual with Schematics.

5.5.6. Operating Instructions, if not in the TI.

5.5.7. Preventative Maintenance Schedules. (See section 5.3.2)

5.5.8. Equipment Data Sheet (EDS).

6. DELIVERY / ACCEPTANCE / RETURN

6.1. Delivery- The machinery shall be in a fully charged, fully assembled, ready-to-use, and in a first-class-operating condition. Machines shall be functionally tested prior to its delivery and all leased products, including machine / equipment / ancillary component accompanying machine, must fully function as intended. The machinery with its support equipment shall be delivered to the site on or prior to the request date. It is incumbent and the responsibility of the Contractor to either confirm or coordinate the date and time of delivery prior to each shipment via the Point-of-Contact (POC) as designated on the Contract and/or the Contracting Officer's Representative (COR). The Government can provide forklift services for removing machinery from Vendor’s transport during work hours. Documentation with Shipyard copies shall accompany each delivery.

6.2. Acceptance-Upon satisfactory completion of inspection and test of the equipment, the authorized Government Representative (Portsmouth Naval Shipyard, Code 420 COR) will sign and forward the acceptance document(s) to Code 410 Contracting Division for completion. Unloading of equipment from Vendor’s transport does not signify acceptance.

6.3. Start Up- If requested by the Project, the Vendor shall: (i) start and run the equipment to verify its operability;

(ii) confirm that a set of operating instructions was previously delivered; and/or (iii) instruct designated Shipyard personnel on how to properly run the equipment to include its operation, control, daily checks, & service contacts. For multiple sets of comparable equipment with essentially similar operation, the orientation given to a specific Project on a particular type and/or capacity of machine can be accomplished just once regardless of delivery.

6.4. Security- To be allowed onto a government Shipyard, personnel must be US citizens and in possession of appropriate personal identification. Proof of US citizenship may be necessary and can be required for access to the drydock. Allowable documentation of US citizenship is an official government issued Certificate of Birth or Naturalization (w/ raised seal & not a photocopy) or a US passport. Vehicular access requires a non-expired personal Driver’s License and appropriate vehicle identification or registration. The transport vehicle must have the company’s name / logo prominently displayed. To gain access to the drydock environs, personnel must be escorted and possess / wear their own personal safety gear.

6.5. Receipt Inspection Criteria- Equipment must meet all criteria defined in this Document.

6.6. Return- The Government will provide a temporary storage location convenient for Contractor pick-up. The Government will notify the Contractor as well as the Contracting Office as to when the rental Item has been released and is available for pick-up. The last day of the rental period shall be the next normal workday after the Contractor has been so notified. The Contractor shall be responsible for shipping. The Government can provide forklift services during work hours for placing the equipment onto the vendor’s transport.

7. GENERAL

7.1. Response to Request

As part of the response to this request, descriptive literature shall be furnished in sufficient detail to show that the proposed design will meet these specifications. Vendor submittals shall include brochures of the model being submitted, assembly sketches with critical dimensions, sketches (with dimensions) of all tooling being provided, statements of compliance with specification, and performance statements with special instructions.

Supporting information shall be organized and packaged by unit. If supporting information includes multiple models the vendor shall clearly state model number of proposed unit and redact all information not applicable to proposed unit.

Enclosure 1 Table E1

SOW Compliance Checklist

SOW REQUIREMENT COMPLIANCE WITH SOW.

(See Instructions Below)

EXCEPTIONS TO SOW.

(See Instructions Below)

Equipment TABLE 1 Chiller [Mechanical Data] TABLE 1A Chiller [Electrical Data] TABLE 2 Pump [Mechanical Data] TABLE 2A Pump [Electrical Data]

TABLE 3 Hoses

TABLE 4 Elbows TABLE 5 Heat Tape Section 4.1 Chiller Capacity & Utilities Section 4.2 Coolant Free Section 4.3 Hydrostatic Testing Section 4.6 Hydronic Flowmeter Calibration Section 4.7 Freeze Protection Section 4.8 Noise Requirements Section 4.9 Tagging Requirements

SOW REQUIREMENT COMPLIANCE WITH SOW.

(See Instructions Below)

EXCEPTIONS TO SOW.

(See Instructions Below)

Services

Section 5 (in its entirety) Deliverables

Section 6 (in its entirety) Delivery Acceptance and Return

Section 7 General

INSTRUCTIONS

1. COMPLIANCE WITH SOW.

(i) Use YES or NO to identify if equipment and services comply with all SOW requirements.

(ii) Ensure answers are consistent with any brochures, specification sheets or other descriptive literature provided in your quote.

2. EXCEPTIONS TO SOW.

(i) Identify any exceptions to the SOW. Note, answers are required for any NO in prior column.

(ii) Explain reason for exception.

NOTE:

This Table is not all inclusive, all requirements of the SOW must be satisfied.

Provide comment for any “No” answer in the Table above.

1. SCOPE
2. REFERENCES
2.1.2. Non-Government
3. REQUIREMENTS
3.1.1. Required components.
TABLE 1: Chiller Mechanical Data
All components that come in contact with the process water shall be Non-Ferrous
Material Constraint
100
Tonnage (Max)
Air Cooled
Cooling (Condenser)
Not to exceed hose rating ****
PSI (Working Pressure)
Capable of operation at 25% Load at 4:1 Turndown
Turndown
00F - 1000F
Operating Temp (Ambient)
380F-600F
Process water temperature
Process Water Supply/Return Gages
Range of 200F-1000F with 10F resolution
Non-Ferrous/Galvanized A-A-59326 Plug (Supply) Socket (Return)
Connection Type
4" Nominal
Connection Size
Integrated into process water piping. Note: Cannot be PSI Gages
Flow switch
Electronic (Not Axial Turbine) 50-400 gpm with a minimum accuracy of 1% of reading and 1 gpm minimum resolution. Calibrated within 5 years.
Flow Meter (Calibrated)
Shall Have for low flow conditions
Hot Gass By-Pass
180in x 90in
Footprint (Max)
15000lb
Weight (Max)
Must have forklift pockets and padeyes integrated into the machine designed/tested for machines nameplate weight rating
Lifting/Handline
Shall have to log parameters and adjust setpoint i.e. process water temperature.
HMI for user interface
Compressor and Refrigerator circuits
Minimum of 2
TABLE 1A: Chiller Electrical Data
480VAC, 3PH, 60HZ, 200FLA (max)
Power
Must be energized by a dedicated circuit, discrete from the pump power source regardless of if integrated or separated from the chiller unit
Power Source
Camlock 16 Series, Type J style connection with min 3ft whips or box mounted.
Power Supply Connection
Nema 3 (4) to allow for unsheltered outdoor use
Electrical Components
TABLE 2: Pump Mechanical Data
All components that come into contact with the process water shall be Non-Ferrous
Material
240gpm @ 130ft @ 1750 RPM
Size (min)
Non-Ferrous/Galvanized A-A-59326 Plug (Supply) Socket (Return)
Connection Type
4" Nominal
Connection Size
Range: 0-200 PSI. Shall be installed on the suction and discharge side of pump. Rated to 25% over operating range
Pressure Gages
Can either be integral to chiller or stand-alone unit
Layout
If stand alone, shall have forklift pockets and rigging pad rated to lift the piece of equipment
Lifting/Handling
48" x 48" (includes the rigging gear)
Footprint (standalone only) MAX
Pump weight shall be either etched into a location on the unit or certification provided to COAR (POC Provided in Note Section:)
Weight
TABLE 2A: Pump Electrical Data
480VAC, 3 PH, 60HZ
Power
Must be energized by a dedicated circuit, discrete from the chiller power source regardless of if integrated or spirited from the chiller unit
Power Source
Nema 4 rated knife switch. Sized in accordance with Pump nameplate data.
Isolation Switch
Sized and rated in accordance with pump nameplate data.
Pump Supply Connection Type
TABLE 3: Hoses
Non-Collapsible suction hose with exterior cover shall be a thick rubber (Buna-N)
Type
4"
Size
Non-Ferrous / Galvanized A-A-59326 Plug (Supply) Socket (Return)
Connection Type
Plug on one end and socket on the other end of hose
Orientation
25ft lengths to equal total of 400ft
Required individual length (max)
16 lengths of 25ft hose for a total of 400ft
Required Total Length (min)
Rated to Pump max output Pressure.
Working Pressure Rating
TABLE 4: Elbows
90-Degree
Type
Non-Ferrous / Non-Galvanized
Material
Non-Ferrous / Non-Galvanized A-A-59326 Plug (Supply) Socket (Return)
End Connections
Eight (8)
Total
4. NOTES:
4.1.1. Cooling: The minimum nominal chilled water capacity shall be as indicated with the actual capacity, based on an ambient temperature of 95ºF dry bulb with an Entering Water Temperature (EWT) of 52ºF and a Leaving Water Temperature (LWT) of 42ºF,...
4.1.2. Automatic Operation, Regulation, & Controls: The Chiller shall be equipped with an automatic variable capacity control requiring only initial temperature adjustment from 38 to 60 F by the operator. The Chiller shall be fully controllable under ...
4.1.3. Design & Component Integration: The Chiller can either be an integrated Chilled Water Unit capable of both refrigerating and pressurizing water or can be two separate types of components consisting of a Chiller that refrigerates water and a Pum...
4.7.1. Season: For cold weather geographic regions including Portsmouth NH and New London CT, the all-season chiller and its accompanying pump are machines that have the potential for its chilled water coils or other piping components to freeze somet...
4.7.2. Low Ambient Temperature & Low Cooling Load: As an all-season (year-round) continuously operating chiller, the unit must be able to function at very low ambient temperatures and at low cooling loads of one-quarter or less of its full-load or a ...
4.7.3. Seasonal Resets of The Leaving Chilled Water Temperature: Prior to commencement of the freezing prevention season, the Vendor shall reset the discharge leaving chilled water temperature from 42ºF to 55ºF. Soon after (within a month of) termina...
5. RESPONSIBILITES
5.1. Government
5.3. Maintenance
5.4. Training
5.5. Deliverables – In addition to all required equipment, technical documentation shall also be provided electronically to the project COR. Minimally, the documentation shall consist of:
6. DELIVERY / ACCEPTANCE / RETURN
6.1. Delivery- The machinery shall be in a fully charged, fully assembled, ready-to-use, and in a first-class- operating condition. Machines shall be functionally tested prior to its delivery and all leased products, including machine / equipment / an...
6.2. Acceptance-Upon satisfactory completion of inspection and test of the equipment, the authorized Government Representative (Portsmouth Naval Shipyard, Code 420 COR) will sign and forward the acceptance document(s) to Code 410 Contracting Division ...
6.3. Start Up- If requested by the Project, the Vendor shall: (i) start and run the equipment to verify its operability; (ii) confirm that a set of operating instructions was previously delivered; and/or (iii) instruct designated Shipyard personnel on...
6.4. Security- To be allowed onto a government Shipyard, personnel must be US citizens and in possession of appropriate personal identification. Proof of US citizenship may be necessary and can be required for access to the drydock. Allowable document...
6.5. Receipt Inspection Criteria- Equipment must meet all criteria defined in this Document.
6.6. Return- The Government will provide a temporary storage location convenient for Contractor pick-up. The Government will notify the Contractor as well as the Contracting Office as to when the rental Item has been released and is available for pick...
7. GENERAL
7.1. Response to Request As part of the response to this request, descriptive literature shall be furnished in sufficient detail to show that the proposed design will meet these specifications. Vendor submittals shall include brochures of the model be...