This document appears to be the Status Report Requirements attachment for a federal contract opportunity related to providing non-commercial production trade labor support services for Marine Weight Handler personnel, supervisors, and program management at the Portsmouth Naval Shipyard.
The key details are:
- The contract requires 10 experienced, skilled, and qualified Marine Weight Handler personnel, 2 supervisors, and program management to assist with non-nuclear production labor support modernization and repair work on nuclear-powered submarines.
- The period of performance is from September 30, 2024 to August 29, 2025.
- The required level of effort includes 9,000 straight time hours and 900 overtime hours for each shift of 5 Weight Handler personnel, as well as 1,800 straight time hours and 180 overtime hours for each shift supervisor.
- The work will be performed on-site at the Portsmouth Naval Shipyard in Kittery, Maine.
- The contract is being solicited by the Department of the Navy's Naval Sea Systems Command.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1
Attachment 1 – Status Report Requirements
Status Reporting Requirements
Items to include in status report:
1. Contract number.
2. Contract number.
3. Data date for data being used.
4. Funded amount.
a. Funds expended to date.
b. Funds remaining.
c. Percentage of funds expended to date.
d. Percentage of funds remaining.
5. Period of performance.
a. PoP Start Date.
b. PoP End Date.
c. Days PoP elapsed.
d. Days PoP remaining.
e. Percentage PoP elapsed.
f. Percentage PoP remaining.
6. Mechanic Time Tracking.
a. Straight time hours expended in reporting period (week).
b. Straight time hours expended to date.
c. Straight time hours remaining.
d. Overtime hours expended in reporting period (week).
e. Overtime hours expended to date.
f. Overtime hours remaining.
Attachment 1
Attachment 1 – Status Report Requirements
7. Management Time Tracking.
a. Hours expended in reporting period (week).
b. Hours expended to date.
c. Hours remaining.
8. Projections.
a. Projected funded fully expended date.
b. Projected mechanic straight time hours expended date.
c. Projected mechanic overtime hours expended date.
9. Graphical Representations (Updated Weekly)
a. Graph #1: Actual Straight Time Hours, Budgeted Straight Time Hours, Forecasted Straight Time
Hours.
b. Graph #2: Actual OT Hours, Budgeted OT Hours, Forecasted OT Hours.
c. Graph #3: Actual Funds Expended, Budgeted Funds Expended, Forecasted Funds Expended.
Graphical Data Representation Example: