IDIQ_3_YR_CONEX_SCHEDULE_12-2-16.xlsx
XLSX spreadsheet 18 KB Posted
- Solicitation number
- N39040-17-T-0164
About this file
Estimated schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Past_Performance_Report_Form.doc | DOC document | |
| N39040-17-T-0164_0001.pdf | ||
| Questions-Answers.docx | DOCX document | |
| Att._1_CAP.doc | DOC document | |
| N39040-17-T-0164.pdf | ||
| Att._2_Past_Performance.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
revised
THREE YEAR CONEX BOX USAGE FORECAST
PNSY
03.04.16
| Total units per project 3. One 40 ft std, one 40 ft combo, one 20 ft std. (*NLON requires 4 units, *two 20 ft std) | |||||||||||||
| Base Period FY 17 | Option Year 1 FY 18 | Option Year 2 FY 19 | Total | Max # of units required | |||||||||
| Estimated Delivery Order dates | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | ||
| LOCATION | PNSY | PNSY | PNSY | PNSY | PNSY | NLON - CT | PT LOMA - CA | PNSY | PT LOMA - CA | PNSY | PNSY | ||
| Base: 11/17/2016 | 3 | 3 | |||||||||||
| 12/17/16 | 3 | 3 | |||||||||||
| 1/17/17 | 3 | 3 | 6 | ||||||||||
| 2/17/17 | 3 | 3 | 6 | ||||||||||
| 3/17/17 | 3 | 3 | 6 | ||||||||||
| 4/17/17 | 3 | 3 | 6 | ||||||||||
| 5/17/17 | 3 | 3 | 6 | ||||||||||
| 6/17/17 | 3 | 3 | 6 | ||||||||||
| 7/17/17 | 3 | 3 | 6 | ||||||||||
| 8/17/17 | 3 | 3 | 3 | 9 | |||||||||
| 9/17/17 | 3 | 3 | 3 | 9 | |||||||||
| 10/17/17 | 3 | 3 | 3 | 9 | |||||||||
| 11/17/17 | 3 | 3 | 3 | 9 | |||||||||
| 12/17/17 | 3 | 3 | 3 | 9 | 9 | ||||||||
| Opt 1: 1/17/2018 | 3 | 3 | 3 | 9 | |||||||||
| 2/17/18 | 3 | 3 | 3 | 3 | 12 | ||||||||
| 3/17/18 | 3 | 3 | 3 | 3 | 12 | ||||||||
| 4/17/18 | 3 | 3 | 3 | 3 | 12 | ||||||||
| 5/17/18 | 3 | 3 | 3 | 3 | 12 | ||||||||
| 6/17/18 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 7/17/18 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 8/17/18 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 9/17/18 | 3 | 3 | 3 | 3 | 3 | 4 | 3 | 22 | |||||
| 10/17/18 | 3 | 3 | 3 | 3 | 3 | 4 | 3 | 22 | 22 | ||||
| 11/17/18 | 3 | 3 | 3 | 3 | 3 | 4 | 19 | ||||||
| 12/17/18 | 3 | 3 | 3 | 3 | 3 | 4 | 19 | ||||||
| Opt 2: 1/17/2019 | 3 | 3 | 3 | 3 | 3 | 4 | 19 | ||||||
| 2/17/19 | 3 | 3 | 3 | 3 | 4 | 16 | |||||||
| 3/17/19 | 3 | 3 | 3 | 4 | 3 | 16 | |||||||
| 4/17/19 | 3 | 3 | 3 | 4 | 3 | 16 | |||||||
| 5/17/19 | 3 | 3 | 3 | 4 | 3 | 3 | 19 | ||||||
| 6/17/19 | 3 | 3 | 3 | 4 | 3 | 3 | 19 | 19 | |||||
| 7/17/19 | 3 | 3 | 3 | 3 | 12 | ||||||||
| 8/17/19 | 3 | 3 | 3 | 3 | 3 | 3 | 18 | ||||||
| 9/17/19 | 3 | 3 | 3 | 3 | 3 | 3 | 18 | ||||||
| 10/17/19 | 3 | 3 | 3 | 3 | 3 | 3 | 18 | ||||||
| 11/17/19 | 3 | 3 | 3 | 3 | 3 | 3 | 18 | ||||||
| 12/17/19 | 3 | 3 | 3 | 3 | 3 | 3 | 18 | ||||||
| 1/17/20 | 3 | 3 | 3 | 3 | 3 | 3 | 18 | ||||||
| 2/17/20 | 3 | 3 | 3 | 3 | 3 | 3 | 18 | 18 | |||||
| 3/17/20 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 4/17/20 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 5/17/20 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 6/17/20 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 7/17/20 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 8/17/20 | 3 | 3 | 3 | 3 | 3 | 15 | |||||||
| 9/17/20 | 3 | 3 | 3 | 3 | 12 | ||||||||
| 10/17/20 | 3 | 3 | 6 | ||||||||||
| 11/1/21 | 3 | 3 | |||||||||||
| 12/1/21 | 3 | ||||||||||||
| 1/1/21 | 3 | ||||||||||||
| 2/1/21 | 3 | ||||||||||||
| 3/1/21 | 3 | ||||||||||||
| 4/1/21 | 3 | ||||||||||||
| 5/1/21 | 3 | ||||||||||||
| 6/1/21 | |||||||||||||
| 7/1/21 | |||||||||||||
| 8/1/21 | |||||||||||||
| Estimated Project duration in months + Risk | 27 | 26 | 23 | 24 | 28 | 10 | 9 | 21 | 10 | 14 | 22 | ||
| 76 | 71 | 67 |