AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

N3319122R4002 D-B Renovate Maritime Operations Center, Antisiranana, Madagascar

See Page 2 for description of amendment

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 01-Feb-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N3319122R4002

X 9B. DATED (SEE ITEM 11)

24-Nov-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

01-Feb-2022

CODE

NAVFAC EUROPE AFRICA CENTRAL

VIALE PORTO CAPODICHINO

NAPOLI 80144

N33191 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N3319122R4002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0002

The purpose of the subject amendment is to:

1.) Revised Factor 1, Corporate Experience (i) Solicitation Submittal Requirements point 3 on page 7 of 44.

From:

“3. Performed in the country of Madagascar within the last 10 years of the date this RFP was issued;”

To:

“3. Performed in the country of Madagascar, South Africa, Kenya, Uganda, or Tanzania within the last 10 years of the date this RFP was issued;”

2.) Revised Factor 1, Corporate Experience (ii) Basis of Evaluation Point 3 on page 8 of 44:

From:

“3. Performed in the country of Madagascar within the last 10 years of the date this RFP was issued;”

To:

“3. Performed in the country of Madagascar, South Africa, Kenya, Uganda, or Tanzania within the last 10 years of the date this RFP was issued;”

3). Revised Attachment 1 – PTS, 8. ENGINEERING TECHNICAL SPECIFICATION:

SECTION D50: ELECTRICAL [08/06]

- 1.4.1. Qualified Testing Organiation, 1.4.1.1, 1.4.1.2, 1.4.1.3

- 1.4.7 Factory Trained Engineer

SECTION G40: SITE ELECTRICAL UTILITIES [06/07]

- 1.4.10 Electrical System Startup and Testing, 1.4.10.4.2, 1.4.10.3

4.) Extend the Proposal Due Date to 04 March 2022 no later than 2:00 pm Central European

Time (CET).

N3319122R4002

SECTION 00 10 00 - SOLICITATION

The standard size code $39,500,000 has been added.

(End of Summary of Changes)

Maritime Operations Center (MOC) WON: 1628050 Antisiranana Naval Base, Madagascar

1. SECTION D50: ELECTRICAL [08/06]

2. D50 GENERAL

3. 1.1 Narrative

4. This section includes the construction of interior electrical systems. This section covers installations inside the facility and out to the 5-feet (1.5 m) line. See Section G40, Site Electrical, for continuation of systems beyond the 5-feet (1.5 m) line.

5. 1.2 Design Guidance

6. Provide design and installation in accordance with Section 6 General Work Requirements. The Designer of Record is responsible for approving the submittals listed below.

7. 1.3 Construction Submittals

8. Provide product and operation and maintenance data for all equipment and fixtures to

COR.

9. 1.4 Qualifications, Certifications, and Test Plans

10. Qualifications, certifications, and Test Plans indicated herein shall be submitted 45 calendar days prior to the expected date of execution. Notify the Contracting Officer 14 calendar days prior to all testing. Submit test results within 7 calendar days of completion of testing.

11. 1.4.1 Qualified Testing Organization

1.4.1.1 Contractor shall engage the services of a qualified testing organization to provide inspection, testing, calibration, and adjustment of the electrical distribution system and equipment listed in paragraph entitled "Acceptance Tests and Inspections" herein.

1.4.1.2 Organization shall be independent of the supplier, manufacturer, and installer of the equipment. The organization shall be a first tier subcontractor.

1.4.1.3 Submit name and qualifications of organization. Organization shall have been regularly engaged in the testing of electrical materials, devices, installations, and systems for a minimum of 5 years.

12. 1.4.1.4 The organization shall have a calibration program, and test instruments used shall be calibrated in accordance with local government criteria.

13. 1.4.1.5 Submit name and qualifications of the lead engineering technician performing the required testing services.

14. 1.4.1.6 Include a list of three comparable jobs performed by the lead engineering technician with specific names and telephone numbers for reference.

15. 1.4.1.7 Testing, inspection, calibration, and adjustments shall be performed by the lead engineering technician, certified by local government with a minimum of 5 years' experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.

16. 1.4.2 Qualified Worker

17. 1.4.2.1 Provide in accordance with local government criteria.

18. 1.4.2.2 Qualified workers shall be allowed to be assisted by helpers on a 1 to 1 ratio, provided such helpers are registered in recognized apprenticeship programs.

19. 1.4.2.3 Submit a certification confirming to local government criteria for qualified workers.

20. 1.4.4 Material Standards

21. 1.4.4.1 Ensure service support and provide manufacturer’s nameplate in accordance with PTS Section 6 General Work Requirements.

22. 1.4.4.2 Provide arc flash warning labels.

23. 1.4.4.3 Provide laminated plastic nameplates for each switchboard, switchgear, panel board, equipment enclosure, motor controller, relay, and switch. Each nameplate must identify the function and, when applicable, the position. Provide melamine plastic nameplates, 0.125 inch (3 mm) thick, white with black center core. Surface shall be matte finish. Corners shall be square. Accurately align lettering and engrave into the core. Minimum size of nameplates shall be 1 inch by 2.5 inches (25mm by 65 mm).

Lettering shall be a minimum of 0.25 inch (6.35 mm) high normal block style.

24. 1.4.5 Factory Testing

25. The COR reserves the right to witness all factory testing. The manufacturer shall have a calibration program that assures that all applicable test instruments are maintained within rated accuracy.

26. 1.4.6 Electrical System Startup And Testing

27. 1.4.6.1 Submit test plans for approval. The test plans shall be tailored to the systems provided.

28. 1.4.6.2 The test plan shall list make and model and provide functional description of the test instruments and accessories and shall describe the setup of the tests to be conducted.

29. 1.4.6.3 Test instruments shall be capable of measuring and recording or displaying test data at a higher resolution and greater accuracy than specified for the equipment’s performance.

1.4.7 Factory Trained Engineer

Provide a factory trained engineer to supervise start-up and testing as required in referenced specifications.

SECTION G40: SITE ELECTRICAL UTILITIES [06/07]

G40 GENERAL

1.4.10.4.2 Submit a separate electrical field test plan in accordance with manufacturer’s recommendations and that conforms to [local government criteria][NETA ATS] for each piece of Electrical Distribution Equipment and/or System requiring Performance Verification Testing.

1.4.10.4.3 The following items identify specific test requirements. Additional test requirements are contained in the applicable [local government criteria].

Cable – Test cable in accordance with the manufacturer's recommendations and local government criteria. Adhere to precautions and limits as specified in the applicable local government criteria for the specific cable.

Grounding - Test ground systems in accordance with the manufacturer's recommendations and [local government criteria][NETA ATS].

Site Lighting - Contractor’s Quality Control (CQC) representative shall perform a field survey of site lighting systems in accordance with local government criteria for acceptance. Show that the lighting system operates in accordance with the user’s requirements and is in accordance with designed levels. Provide certification that the measured lighting levels conform to the design requirements. Telecommunications wiring - Test all cables in accordance with industry standards.

22R4002 - Amendment 0002
PTS - Revised
1. SECTION D50: ELECTRICAL [08/06]
2. D50 General
3. 1.1 Narrative
5. 1.2 Design Guidance
7. 1.3 Construction Submittals
9. 1.4 Qualifications, Certifications, and Test Plans
11. 1.4.1 Qualified Testing Organization
16. 1.4.2 Qualified Worker
20. 1.4.4 Material Standards
24. 1.4.5 Factory Testing
26. 1.4.6 Electrical System Startup And Testing
SECTION G40: SITE ELECTRICAL UTILITIES [06/07]
G40 General