19R0405_Amend_0001.pdf
PDF 152 KB Posted
- Solicitation number
- N3319119R0405
About this file
19R0405_Amend_0001.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19R0405_-_RFP.pdf | ||
| 19R0405_-_Attach_2_-_PPI.docx | DOCX document | |
| 19R0405_-_Attach_3_-_Perf_Bond_Sample.docx | DOCX document | |
| 19R0405_-_Attach_1_-_PTS.pdf | ||
| N3319119R0405_19R0405_Military_Vehicle_Maint_Facility__-_Pre_sol.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N3319119R0405 D-B Construct Military vehicle Maintenance Facility, Chisinau, Moldova
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 24-Apr-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N3319119R0405
X 9B. DATED (SEE ITEM 11)
05-Apr-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
24-Apr-2019
CODE
NAVFAC EUROPE AFRICA SOUTHWEST ASIA
VIALE PORTO CAPODICHINO
NAPOLI 80144
N33191 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N3319119R0405
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
The purpose of this Amendment is to respond to Pre-Proposal Inquiries.
Pre-Proposal Inquiry 001
We suppose to design will be steel structure basis and the thermal façade will be polyurethane sandwich system as painted galvanized sheet metal+ polyurethane foam+painted galvanized sheet metal as design calculated required thickness (estimated 8 cm.) So the subject SOW section definition basis on concrete masonary system+insulation layer.
Does polyurethane sandwich system acceptable for steel structural designed building for exterior wall? (Mentioned at N3319119R040519R0405_-_Attach_1_-_PTS section 3.3.2 Thermal Façade)
Pre-Proposal Inquiry 001 Response
No. Polyurethane sandwich panels system is not acceptable for the building façade or exterior walls.
Pre-Proposal Inquiry 002
What is the details of lighting control mentioned at N3319119R040519R0405_-_Attach_1_-_PTS section 3.6.
DETAILED ELECTRICAL SCOPE OF WORK?
Pre-Proposal Inquiry 002 Response
“Lighting control” refers to the mechanisms to connect or disconnect the lights, which shall be with the use of switches, as designed by the contractor’s engineer.
Pre-Proposal Inquiry 003
Do you request any lighting for 100 meters new fence mentioned at N3319119R040519R0405_-_Attach_1_-_PTS section 3.1. DETAILED SITE/CIVIL SCOPE OF WORK?
Pre-Proposal Inquiry 003 Response
No. Only exterior lighting required is described in paragraph 3.6.3
Pre-Proposal Inquiry 004
N3319119R040519R0405_-_Attach_1_-_PTS / 3.6.8. Pad Mounted Back-Up generator section says that ‘The new facility will be used by the Ministry of Defense and it is mandatory that they are provided with electrical back-up generator’.
We understood that Ministry of Defense and it is mandatory will provide back-up generator also. Please verify.
Pre-Proposal Inquiry 004 Response
N3319119R0405
Yes. A generator is required as part of this project and it is described in paragraph 3.6.8
Pre-Proposal Inquiry 005
What do you mean Fire and Rescue Station loads which shall connect to generator? (N3319119R040519R0405_- _Attach_1_-_PTS section 3.6.8. Pad Mounted Back-Up generator). Please explain.
Pre-Proposal Inquiry 005 Response
Fire and Rescue Station is a typo, it should have said “Vehicle Maintenance Facility”. Change sentence: in page 76 “Under automatic operation, the generator shall start automatically when a power outage of more than 5 seconds is detected, and shall connect the Fire and Rescue Station loads within 30 seconds” to “Under automatic operation, the generator shall start automatically when a power outage of more than 5 seconds is detected, and shall connect the Vehicle Maintenance Facility loads within 30 seconds”
Pre-Proposal Inquiry 006
What is the approximately distance of the service provider to the building? (N3319119R040519R0405_- _Attach_1_-_PTS section 3.6.7. Telephone and Internet Service Connection)
Pre-Proposal Inquiry 006 Response
Maximum of 240 linear meters in straight line from the closest edge of the new building.
(End of Summary of Changes)