This document is a Questions and Answers (Q&A) file for a federal contract opportunity to dismantle a metal tower. The solicitation (N32253-25-Q-1008) is issued by the Department of the Navy for a salvage/scrap job involving an enclosed metal tower with an interior staircase, measuring 17'L x 17'W x 40'H. The contract is 100% set aside for small businesses, with a tentative Period of Performance from August 1, 2025 to February 6, 2026, using NAICS code 238910 for Site Preparation Contractors.
Key details include requiring an Environmental Manager with 5 years experience who must be on-site during all work operations, and provisions for working near dry dock floor gratings. The government will provide crane support for lifting, allow staging of dismantled materials in the dry dock basin, and offer as-built drawings and interior/exterior tower images upon request. Quotes are due by July 11, 2025, at 8:00 a.m. HST, and must be submitted via email with completion of specific FAR forms. The contract will be awarded as a Firm Fixed Price, with the tower's lighting and power to be removed prior to the start of the performance period.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reference (para/page #, etc.)
1 General question Will any pictures of DXX tower #.1 be provided?
Photos can be provided by government upon request. Info will be provided via DoD safe and should be requested by sending email to fiona.c.lynch.civ@us.navy.mil. In the request, please provide Name, Title, Solicitation Number, and Email.
2 General question Will there be a site visit to look at the structure ? Site Visit is scheduled for 05.15.2025 see “Encl(1) Site_Visit_Information” for more detail and RSVP information. EDIT: 05.15.2025 site visit canceled.
5 General question Is there a designated staging area available for our trucks and equipment?
There is currently no designated staging area available. Space may be available. This will have to be coordinated with the C900F manager.
9 General question Is there a cost estimate , budget or ballpark figure for the project listed? There will be no government estimate provided to potential offerors.
Site Visit is scheduled for 05.15.2025 see “Encl(1) Site_Visit_Information” for more detail and RSVP information.
Lighting and power will be removed by start of PoP.
This requirement will be subject to Wage Determination:
Service Contract Act WD # 2015-5689 (Please see attachment).
Q ue s.
# Question Government Response
4 General question Can you provide current pictures of the structure to be removed, along with the surrounding area?
Current pictures of the structure can be provided. The surrounding area will not be provided. However, you can view the surrounding area by attending the site visit scheduled for 05.15.2025. Additional information regarding the site visit is provided in the response to question #2.
6 General question
Photos can be provided by government upon request. Info will be provided via DoD safe and should be requested by sending email to fiona.c.lynch.civ@us.navy.mil. In the request, please provide Name, Title, Solicitation Number, and Email.
Could you please send me over any supporting documents as well as any photos of the structure and GPS Coordinates of the tower?General question3
Will this project be subject to Davis-Bacon wage rates?
7 General question Is the tower currently connected to electrical power?
8 General question Could we see the actual location of the tower on the base?
10 General question Is there an actual start date for the project? The estimated Period of Performance start date in July 01,2025 (See Pg. 11 Solicitation)
11 General question What kind of of tower this is? Enclosed metal tower with interior staircase
12 General question Is this a salvage/scrap job or take it apart to be reassembled elsewhere? Salvage/scrap job
Reference (para/page #, etc.)Q ue s.
# Question Government Response
14 General question Is an Environmental Manager with 5years experience required for this project? If so, how often are they required to be on site?
Yes, an Environmental Manager (EM) with 5 years experience is required for this project. The EM must be on-site during work operations at all times.
17 General question
Paragraph 3.12 states "Work shall not be performed on or within 20 feet of any basin floor gratings." The DXX Tower is currently less than 10 feet from a dry dock floor grating. Will the tower be moved prior to the availability or will the Contractor be responsible for containing the adjacent grating?
Work may be performed within the 20 foot clearance provided that the contractor prohibits any vehicles and/or materials from being located on sump gratings. Provisions by contractor shall be made to safely contain the adjacent grating to preclude items being placed on top of the gratings and prevent materials/debris from entering the grating.
18 General question
Will standard containment, cleanliness and quality assurance requirements be the the same for working in the dry dock #3 basin as when conducting availabilities in other CIA drydocks. YES
19 General question
Will the Government provide crane support for lifting rolling stock into the drydock basin.
YES, Code 740 has supported similar jobs with contractors in the past. Code 2310 will collaborate with Code 700 to deteremine what is needed to safely support these lifts.
20 General question Will the Contractor be able to stage dismantled materials in the drydock basin to minimize daily crane lifts.
YES, per discussion with Code 300WM space to stage dismantled materials inside of the drydock basin will be made available provided that an approximate footprint size is provided for planning purposes.
15 General question Can you include any as-built drawings you have of the tower to be torn down? We have as-built drawings that can be provided upon request.
16 General question Can you provide any pictures of the exterior of the tower? We cannot provide pictures of the exterior, but we can provide on request pictures of the interior and drawings of the exterior.