This document contains a questions and answers (Q&A) table for a federal contract opportunity to dismantle a metal framed tower at Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility (PHNSY & IMF). The Q&A addresses critical project details including a site visit scheduled for 05.15.2025, request procedures for obtaining project photos, and confirmation of project specifics such as wage determination (Service Contract Act WD # 2015-5689), no designated staging area, and no government cost estimate. The estimated Period of Performance start date is July 01, 2025, with lighting and power to be removed at the start of the project period. Interested contractors must request project photos via email to aaron.k.miller22.civ@us.navy.mil, providing their name, title, solicitation number, and email address, with photos to be shared through DoD safe.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reference
(para/page #, etc.)
1 General question Will any pictures of DXX tower #.1 be provided?
2 General question Will there be a site visit to look at the structure ?
5 General question Is there a designated staging area available for our trucks and equipment?
9 General question Is there a cost estimate , budget or ballpark figure for the project listed?
Q u es
# Question
4 General question Can you provide current pictures of the structure to be removed, along with the surrounding area?
6 General question
Could you please send me over any supporting documents as well as any photos of the structure and GPS Coordinates of the tower?
General question3
10 General question Is there an actual start date for the project?
Will this project be subject to Davis-Bacon wage rates?
7 General question Is the tower currently connected to electrical power?
8 General question Could we see the actual location of the tower on the base?
Photos can be provided by government upon request. Info will be provided via DoD safe and should be requested by sending email to aaron.k.miller22.civ@us.navy.mil. In the request, please provide Name, Title, Solicitation Number, and Email.
Site Visit is scheduled for 05.15.2025 see “Encl(1) Site_Visit_Information” for more detail and RSVP information.
There is currently no designated staging area available. Space may be available.
This will have to be coordinated with the C900F manager.
There will be no government estimate provided to potential offerors.
Lighting and power will be removed by start of PoP.
This requirement will be subject to Wage Determination:
Service Contract Act WD # 2015-5689 (Please see attachment).
Government Response
Current pictures of the structure can be provided. The surrounding area will not be provided. However, you can view the surrounding area by attending the site visit scheduled for 05.15.2025. Additional information regarding the site visit is provided in the response to question #2.
Photos can be provided by government upon request. Info will be provided via DoD safe and should be requested by sending email to aaron.k.miller22.civ@us.navy.mil. In the request, please provide Name, Title, Solicitation Number, and Email.
The estimated Period of Performance start date in July 01,2025 (See Pg. 11 Solicitation)
Site Visit is scheduled for 05.15.2025 see “Encl(1) Site_Visit_Information” for more detail and RSVP information.