This document is a Questions and Answers (Q&A) file for a federal contract opportunity to dismantle DXX Tower No. 1. The file contains 16 questions and corresponding government responses covering project details such as site visits, photography requests, tower characteristics, and project requirements. Key details include the tower being an enclosed metal structure to be salvaged/scrapped, with an estimated Period of Performance starting July 1, 2025. An Environmental Manager with 5 years experience is required to be on-site during all work operations. Photos, as-built drawings, and interior tower images can be provided upon request via email to fiona.c.lynch.civ@us.navy.mil, with information to be shared through DoD safe. The site visit originally scheduled for 05.15.2025 was canceled, and no government cost estimate will be provided to potential offerors. The project will be subject to Service Contract Act Wage Determination #2015-5689, and lighting and power will be removed by the start of the Period of Performance.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Reference (para/page #, etc.)
1 General question Will any pictures of DXX tower #.1 be provided?
Photos can be provided by government upon request. Info will be provided via DoD safe and should be requested by sending email to fiona.c.lynch.civ@us.navy.mil. In the request, please provide Name, Title, Solicitation Number, and Email.
2 General question Will there be a site visit to look at the structure ? Site Visit is scheduled for 05.15.2025 see “Encl(1) Site_Visit_Information” for more detail and RSVP information. EDIT: 05.15.2025 site visit canceled.
5 General question Is there a designated staging area available for our trucks and equipment?
There is currently no designated staging area available. Space may be available. This will have to be coordinated with the C900F manager.
9 General question Is there a cost estimate , budget or ballpark figure for the project listed? There will be no government estimate provided to potential offerors.
Site Visit is scheduled for 05.15.2025 see “Encl(1) Site_Visit_Information” for more detail and RSVP information.
Lighting and power will be removed by start of PoP.
This requirement will be subject to Wage Determination:
Service Contract Act WD # 2015-5689 (Please see attachment).
Q ue s.
# Question Government Response
4 General question Can you provide current pictures of the structure to be removed, along with the surrounding area?
Current pictures of the structure can be provided. The surrounding area will not be provided. However, you can view the surrounding area by attending the site visit scheduled for 05.15.2025. Additional information regarding the site visit is provided in the response to question #2.
6 General question
Photos can be provided by government upon request. Info will be provided via DoD safe and should be requested by sending email to fiona.c.lynch.civ@us.navy.mil. In the request, please provide Name, Title, Solicitation Number, and Email.
Could you please send me over any supporting documents as well as any photos of the structure and GPS Coordinates of the tower?General question3
Will this project be subject to Davis-Bacon wage rates?
7 General question Is the tower currently connected to electrical power?
8 General question Could we see the actual location of the tower on the base?
10 General question Is there an actual start date for the project? The estimated Period of Performance start date in July 01,2025 (See Pg. 11 Solicitation)
11 General question What kind of of tower this is? Enclosed metal tower with interior staircase
12 General question Is this a salvage/scrap job or take it apart to be reassembled elsewhere? Salvage/scrap job
Reference (para/page #, etc.)Q ue s.
# Question Government Response
14 General question Is an Environmental Manager with 5years experience required for this project? If so, how often are they required to be on site?
Yes, an Environmental Manager (EM) with 5 years experience is required for this project. The EM must be on-site during work operations at all times.
15 General question Can you include any as-built drawings you have of the tower to be torn down? We have as-built drawings that can be provided upon request.
16 General question Can you provide any pictures of the exterior of the tower? We cannot provide pictures of the exterior, but we can provide on request pictures of the interior and drawings of the exterior.