This document is a Statement of Requirements (SOR) for propulsion machinery maintenance on the USNS TRENTON (T-EPF 5), specifically targeting the scheduled maintenance of two Main Propulsion Diesel Engines (MPDE) at the 4,000 hour interval. The requirement calls for Original Equipment Manufacturer (OEM) authorized representatives to perform comprehensive maintenance tasks on MTU Series 8000 Diesel Engines (Model 20V8000M71L), with each engine rated at 9100kW/455kW per cylinder, located in Engine Rooms 1 and 2.
Key requirements include conducting detailed maintenance across multiple qualification levels (QL1-QL4), performing engine overhaul with OEM parts, coordinating with ship's force for system tagouts, and completing extensive pre-startup and startup readiness assessments. The maintenance must include comprehensive inspections, parts replacement, system checks, and performance testing, with mandatory documentation and reporting to MSCREP. The work requires an ABS surveyor inspection at the midpoint of the engine overhaul, and all maintenance must be performed using only OEM-authorized technicians and parts. The maintenance is scheduled for 2025-04-04 and is categorized as a "A" priority item.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS TRENTON (T-EPF 5)
PROPULSION MACHINERY SOR 25-xxx
ITEM NO. 0293 CATEGORY "A" 2025-04-04
TEPF-CSI-MPDE MAINTENANCE (4K HRS) (SCSI) LEFEBVRE
0293 - 1
1.0 ABSTRACT
This item describes the requirement to provide technical services and industrial support to accomplish 4,000 hours scheduled maintenance of the Main Propulsion Diesel Engines.
2.0 REFERENCES/ENCLOSURES
2.1 References
2.1.1 S9233-EM-MMC-010; Main Propulsion Diesel Engines
2.1.2 Tech Manual MS50094/04E Maintenance Schedule
2.2 Enclosures
2.2.1 T-EPF 5 MTU Diesel Engine Data
2.2.2 Diesel Engine Maintenance Start-up and Dormant Start-up Readiness
Assessment (One Checklist per Diesel Engine)
3.0 ITEM LOCATION/DESCRIPTION
3.1 Location/Quantity
3.1.1 Location
a. Engine Room 1 (5-52-1)
b. Engine Room 2 (5-52-2)
3.1.2 Quantity
a. Two (2) Main Propulsion Diesel Engines
3.2 Item Description/Manufacturer's Data
3.2.1 MTU Series 8000 Diesel Engine, 9100kW/455kW per cylinder, Model
20V8000M71L.
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES
4.1 Government Furnished Equipment (GFE): None.
4.2 Government Furnished Material (GFM)
4.2.1 Lube oil.
4.2.2 Engine coolant additive.
4.3 Government Furnished Services (GFS): None.
5.0 NOTES
5.1 The individual maintenance intervals are assigned to the qualification levels QL1 to QL4.
QL1: Operational monitoring and maintenance work which does not require disassembly of the product.
QL2: Exchange of components and parts (corrective only, not part of the maintenance schedule).
QL3: Maintenance work which requires partial disassembly of the product.
QL4: Maintenance work which requires complete disassembly of the product.
0293 - 2
6.0 QUALITY ASSURANCE REQUIREMENTS
6.1 At least one member of the ship’s force will be assigned to assist with quality assurance efforts whenever diesel work is being accomplished.
6.2 Make it known to all personnel working on the engine that electrical and electronic controls and devices are present and may require necessary precautions and isolations that must be protected from damage during the overhaul period.
6.3 Enclosure 2.2.1 for engine specific model and serial number data. This information is required for identification of correct parts for completion of work identified in Section 7.0.
7.0 STATEMENT OF WORK REQUIRED
7.1 Coordinate with ship’s force to tagout all required systems and equipment. Drain and dispose of any liquid, to vessel tanks.
7.2 Only lead Original Equipment Manufacturer (OEM) authorized or qualified representatives will be permitted to temporarily remove, inspect, refurbish, and reinstall main diesel components.
7.2.1 The OEM representative is to remain on-site from the beginning of work until completion of work with satisfactory dock trials. If there is a need to change the lead OEM representative during this scheduled maintenance action, ship’s force is to schedule a turnover meeting with the departing and arriving lead OEM representatives to ensure a proper turnover is accomplished.
7.3 At the halfway point of the engine overhaul, the contractor representative will contact ABS to conduct an inspection for credit towards the unit's Continuous Machinery Survey.
The unit will not be closed until approval is granted by the ABS surveyor. Provide the attending
ABS Surveyor, MSC Port Engineer and Chief Engineer with a minimum of 24-hour notice as to when the unit will be open and ready for inspection by the ABS Surveyor.
7.4 The OEM will provide all tools and material required, including, but not limited to special tools, rags, degreaser, lubricant and loctite for accomplishment of all elements of this work item. Ship’s force will NOT provide any tools.
7.5 Only OEM parts are to be used in the accomplishment of work under this work item.
7.6 Ship’s force is to schedule and provide a representative to attend a daily meeting onboard the vessel with OEM representatives to review data collected and the work planned for the next twenty-four (24) hour period.
7.7 Accomplish the requirements associated with 4,000 operating hours as found in
Reference 2.1.3, as listed below in Table 293–1, using References 2.1.1 and 2.1.2 as guidance.
Maintenance Tasks are available in Reference 2.1.1.
0293 - 3
Table 293-1 Qualification
Level
Interval
(Hours)
Item Maintenance Task Task
QL1 500 Automatic engine oil filter Check and clean oil indicator filter. W1047
QL1 500 Starter Grease starter ring gear. W1075
QL1 500 Screw Connections
Check secure seating of screw connections: Safety valves on cylinder heads.
W1072
QL1 500 Air Intake Grease air flap shaft in intake housing. W1439
QL1 500 Centrifugal oil filter
Check the thickness of oil residue layer. Clean. Fit new sleeves, at the latest, each time the engine oil is changed.
W1009
QL1 1000 High-pressure pump
Check secure seating of screw connections: Connection of high-pressure pump on gearcase.
W1074
QL1 1000 Fuel filters
Check differential pressure and fit new easy-change filter if necessary
(fit new filter at latest when time limit
[years] is reached).
W1057
QL1 1000 Air filters Check filters and fleece for contamination and damage.
W1032
QL1 2000
Engine mounts (Rubber
Design)
Check buffer clearance of resilient mounts. Check proper seating of securing screws.
W1424
QL1 2000 Engine mounts (Super D) Visually inspect for cracks. Check the tightness of securing screws.
W1685
QL1 2000 Engine mounts Check static deflection. W1686
QL1 2000 Air filters Fit new filters and fleece. W1040
QL1 2000 Starting ring gear
Check secure seating of screw connections: Starter ring gear on intermediate ring and intermediate ring, starter/coupling.
W1073
QL1 2000 Valve gear Check valve clearance, adjust if necessary.
W1002
QL1 2000
Misalignment-accommodating coupling Check condition visually X5355
QL1 2000 Air filters Clean air filter(s) X7650
QL1 4000 Intercooler Check operating data, remove and clean the intercooler, if required.
W4079
7.8 All parts that are required to be IMO certified for IAPP shall be procured directly from the OEM to meet IMO requirements.
NOTE: SHIP'S FORCE WILL FILL THE ENGINE’S WITH GFM LUBE OIL AND TREAT
ENGINE HIGH TEMPERATURE FRESH WATER WITH GFM ADDITIVE IDENTIFIED IN
4.2. Ship’s Force will provide deionized water.
0293 - 4
7.9 Inspection/Test
7.9.1 Notify the Chief Engineer when the overhauled engine is ready to be tested during dock trials for an approximate period of one hour. Notify the ABS Surveyor in order to attend the final testing so credit can be given for the Continuous Machinery Survey on the unit.
Record cylinder operating temperatures, fluid operating temperatures and pressures during load test. Submit an “as found” condition report.
a. Prior to engine start-up the checklist in Enclosure 2.2.2 is to be completed. This evolution is to be accounted for in the scheduling of work under this item and related items.
7.9.2 Complete a performance test on each overhauled engine for a minimum of four hours. Record all operating temperatures and pressures and submit them to MSCREP.
7.10 Reports
7.10.1 When inspection, service and testing reveal any deficiency, a condition report is to be submitted to the MSCREP with recommended repairs and parts required. Submit three (3) typewritten copies and one (1) electronic copy in Portable Document Format (PDF).
7.10.2 Submit a report that includes “as released” condition of each Main
Propulsion Diesel Engine. Submit three (3) typewritten copies and one (1) electronic copy in
Portable Document Format (PDF).
a. The report is to include as a minimum, engine hours, engine serial number, all parts removed and installed, and combustion parts associated with ABS NOX rules with serial numbers.
7.10.3 All reports and checklists are to be completed and signed by the person who carried out the inspection and maintenance work and countersigned by the Company’s representative.
7.11 Paint/Lagging
7.11.1 Prepare, prime, paint and restore all new, soiled, and disturbed surfaces to match surrounding surfaces.
7.11.2 Renew lagging where damaged or disturbed.
7.12 Manufacturer's Representative
7.12.1 Provide the services of an OEM authorized field service representative to accomplish all work and testing on the diesels identified in Paragraph 3.0 ensuring compliance with the manufacturer’s standards and performance specifications.
7.12.2 This work item requires maintenance and repair actions to be performed on a MSC ship critical safety item. Only original equipment manufacturer (OEM) authorized technical field service providers or MSC qualified non-OEM technical field service providers and
OEM authorized or MSC qualified non-OEM parts shall be used to accomplish the requirements of this work item for this ship critical safety item including oversight and guidance on all aspects of equipment as-found condition inspection, removal, disassembly, reassembly, repairs, modifications, reinstallation, and testing as applicable. The technical service provider is to attend dock trials.
0293 - 5
7.12.3 Contractors interested in gaining MSC qualification as a non-OEM parts and/or service provider should visit this website for qualification and submittal requirements:
https://www.msc.usff.navy.mil/Business-Opportunities/Contracts/Qualification-for-Items-
Critical-to-Shipboard-Safety-on-MSC-Vessels/.
7.12.4 Possible Source
Larry Oberti
Service Manager – East Coast
TXNGE – Services, Land & Marine Defense
Rolls-Royce Solutions America, Inc.
Mobile: + 1 (757) 469-9241
Lawrence.Oberti@PS.Rolls-Royce.com
Provide the MSCREP with a signed letter of qualification from the Original Equipment
Manufacturer and certificate of training for the field service representative for the equipment listed in Paragraph 3.0 prior to the start of any work.
7.12.5 All reports and checklists are to be completed and signed by the person who carried out the inspection and maintenance work and countersigned by the Company’s representative.
7.12.6 Assist ship’s force in completion of Enclosure 2.2.2 checklist.
7.12.7 Prepare and submit an Engine Start-Up Certification to MSCREP within one (1) day of work completion. This document certifies that work is complete and the engine may be started.
7.13 Preparation of Drawings: None additional.
8.0 GENERAL REQUIREMENTS:
8.1 None additional.
0293 - 6
Enclosure 2.2.1 - T-EPF 5 MTU DIESEL ENGINE DATA
MPDE 1
Model 20V8000M71L
Serial Number: 569100247
MPDE 2
Serial Number: 569100246
MPDE 3
Serial Number: 569100249
MPDE 4
Serial Number: 569100248
0293 - 7
Enclosure 2.2.2 - DIESEL ENGINE MAINTENANCE START-UP AND DORMANT
START-UP READINESS ASSESSMENT (ONE CHECKLIST PER DIESEL ENGINE)
USNS/USS ________________________ Hull No: _______
Diesel Engine Examined for Start-up: ____________________________________
Port / Shipyard: __________________________ Date: ________
72 Hours (notional) Prior to Dock Trial (Machinery Space Turnover) Verification received from Contractor / Tech Rep that all work is complete, and Engine is ready and safe to start.
Verify machinery space fire and smoke detection systems are fully operational.
Verify all Lockout / Tag out locks / tags are cleared IAW SMS 2.1-004-ALL “Lockout /
Tag out.”
Verify that diesel exhaust systems are intact, and no fire hazards exist in the uptake spaces.
Verify all tanks are closed.
Verify all machinery space doors are operating correctly including any installed door closers.
Verify fixed, semi-portable and portable firefighting systems are fully certified and operational.
Verify Damage Control Locker and equipment are available.
Verify that all machinery space reach rods and remote pull stations are fully functional where fitted.
Verify all hoses, staging, covers, rigging, etc., temporarily installed in support of ship maintenance and repair, are removed from the machinery spaces.
Verify machinery space bilges are clean with no accumulations of liquids or debris.
Verify that machinery space supply and exhaust ventilation and fire dampers are functioning properly.
Verify that all installed engine hoses have been checked for wear and compliance with the COMSC 5-year replacement mandate.
0293 - 8
48 Hours (notional) Prior to Startup Check engine oil level in sump.
Check governor oil level.
Check cooling water level.
Check central freshwater treatment and level.
Check oil levels in reduction gear, lineshaft bearings and auxiliary sumps.
Verify fuel oil lines on engine are secure.
Transfer fuel oil from storage tanks to settler.
Check fuel oil service tanks for water or contamination. Conduct fuel oil analysis.
Check lube oil service tanks and sumps for water or contamination. Conduct lube oil analysis.
Verify all engine filters cleaned or renewed.
24 Hours (notional) Prior to Startup Remove stack covers.
Walk around the engine and check for leaks on and under the engine.
Verify 115V / 24VDC control voltage available.
Perform lamp test locally and at EOS console.
Run the lube oil and fuel oil purifiers on sumps and service tanks.
Run auxiliary systems; check pressures and temperatures.
Verify auto start of standby pumps.
Verify machinery space bilges are clean with no accumulations of liquids or debris.
0293 - 9
Pre-Start Check oil level in sump.
Check head tank levels.
Disengage barring gear.
Review USCG Periodic Safety Test Plan (PSTP) and verify that all engine related safety and alarm features are functioning properly.
Verify that saltwater cooling / freshwater cooling systems and heat exchangers are on-line and fully operational.
Verify that lube oil service pumps / lube oil service system is fully functional.
Verify that lube oil purifiers are operating properly.
Verify that fuel oil service pumps / fuel oil service system is fully functional.
Verify that fuel oil purifiers are operating properly.
Verify that compressed air / start air systems are fully functional.
Verify shafts and props are clear to spin.
Stop all fuel transfers.
Test sliding watertight doors.
Verify EDG is available and ready; test run off line.
Open all Engine cocks and roll the engine.
Check local emergency stop.
Check remote emergency stop.
Chief Engineer to notify Master and Port Engineer that start-up readiness assessment has been completed for all prime movers, and associated support systems and that machinery is ready / not ready for start-up.
Master to provide concurrence for start-up or not and conveys same to Type Desk and PM for information.
Chief Engineer Port Engineer