This document contains questions and answers regarding solicitation N3220521R4209 from the Department of the Navy Military Sealift Command for the USNS NEWPORT (T-EPF 12) Mid-Term Availability (MTA). The solicitation requires coating and repair work on 19 heat exchangers, including fabrication and installation of cleaning fittings. It also requires coating approximately 380 square feet of bilge pockets and edge grinding of an estimated 13,640 linear feet of hull. One question seeks clarification on the number of heat exchangers, and the answer confirms there are 19 total. Another question addresses referencing the correct specification paragraphs for hull coating work. No pricing, response dates, or other contract details are provided in this questions and answers document.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N3220521R4209
QUESTIONS AND ANSWERS #5
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
QUESTION #1: 7.1.7.1- Is there an allowance for the amount of Belzona application is to be required?
7.2.1- How many linear feet of edge grinding is to be required?
SPECIFICATION ITEM NO.: 108
PARAGRAPH / SECTION NO: 7.1.7.1& 7.2.1
TITLE: Machinery Space Coating
ANSWER: 7.1.7.1 - 10 square feet per bilge pocket (380 sqft total)
7.2.1 - Estimate approximately 13640 linear feet. Note: This is an approximate estimate based on General Ship Drawings.
QUESTION #2: Paragraph 3.1.2 v. 3.2: Paragraph 3.1.2 calls for 15 heat exchangers while paragraph 3.2 adds up to 19. Please clarify how many units total are being worked.
SPECIFICATION ITEM NO.: 201
PARAGRAPH / SECTION NO: Multiple
TITLE: Heat exchangers
ANSWER: 3.1.2 is incorrect. 3.2 is correct. There are 19 total. No “cleaning in place” fittings were installed at new construction, so the contractor will need to fabricate and install them.
QUESTION #3: Is paragraph 7.9.1 supposed to reference “paragraphs 3.1.2 and 3.1.3” instead of “paragraphs 3.1.1 and 3.1.2, as 3.1.1 would mean a far greater amount of area?
SPECIFICATION ITEM NO.: 989
PARAGRAPH / SECTION NO: 7.9.1
TITLE: Hull Coating
ANSWER: Correct, paragraph 7.9.1 should refer to paragraphs 3.1.2 and 3.1.3.