Q and A 5.docx

DOCX document 13 KB Posted

Attached to
USNS NEWPORT (T-EPF 12) Mid-Term Availability (MTA)
Solicitation number
N3220521R4209
Issued by

About this file

This document contains questions and answers regarding solicitation N3220521R4209 from the Department of the Navy Military Sealift Command for the USNS NEWPORT (T-EPF 12) Mid-Term Availability (MTA). The solicitation requires coating and repair work on 19 heat exchangers, including fabrication and installation of cleaning fittings. It also requires coating approximately 380 square feet of bilge pockets and edge grinding of an estimated 13,640 linear feet of hull. One question seeks clarification on the number of heat exchangers, and the answer confirms there are 19 total. Another question addresses referencing the correct specification paragraphs for hull coating work. No pricing, response dates, or other contract details are provided in this questions and answers document.

View the file

Other files

File Type Posted
Amendment 0011 USNS NEWPORT MTA 21R4209.docx DOCX document
Amendment 0010 USNS NEWPORT MTA N3220521R4209.docx DOCX document
Q and A Response 7..docx DOCX document
Amendment 0009 USNS NEWPORT N3220521R4209.docx DOCX document
J - 2 Category A Items NEWPORT 21R4209 MTA..xlsx XLSX spreadsheet
J - 1 Work Item Specifications NEWPORT MTA 21R4209.docx DOCX document
J - 4 GFP NEWPORT 21R4209 MTA.xlsx XLSX spreadsheet
Amendment 0008 USNS NEWPORT MTA N3220521R4209.docx DOCX document
JA for USNS NEWPORT 2022 MTA RD.pdf PDF
J - 3 Category B Items NEWPORT 21R4209 MTA.xlsx XLSX spreadsheet
Amendment 0007 N3220521R4209.pdf PDF
Amendment 0006 N3220521R4209.pdf PDF
Amendment 0005 N3220521R4209.pdf PDF
Amendment 0004 N3220521R4209.docx DOCX document
Q and A 4.docx DOCX document
N3220521R4209 Amendment 0003.docx DOCX document
Q and A 3.docx DOCX document
N3220521R4209 Amendment 0002.docx DOCX document
N3220521R4209 Amendment 0001.docx DOCX document
Q and A Responses 2..docx DOCX document
Q and A Responses 1.docx DOCX document
RELEASED SOLICITATION - USNS NEWPORT N3220521R4209.docx DOCX document
RELEASED SOLICITATION - USNS NEWPORT N3220521R4209.docx DOCX document
JA for USNS NEWPORT 2022 PSA RD.pdf PDF
J - 2 Category A Items NEWPORT 21R4209.xlsx XLSX spreadsheet
J - 11 Dry Dock Evaluation Form - NEWPORT 21R4209.docx DOCX document
J - 9 Disclosure of Lobbying Activities - NEWPORT 21R4209.doc DOC document
J - 13 Past Performance Questionnaire - NEWPORT 21R4209.docx DOCX document
J- 7 MSC Ship Repair Facility Survey - NEWPORT 21R4209.docx DOCX document
J - 14 Technical Data Non-Disclosure - NEWPORT 21R4209.docx DOCX document
J-6.zip ZIP file
J - 4 GFP NEWPORT 21R4209.xlsx XLSX spreadsheet
J - 10 Interport Differential - NEWPORT 21R4209.doc DOC document
SOLICITATION - USNS NEWPORT N3220521R4209.docx DOCX document
J - 12 Past Performance Data - NEWPORT 21R4209.doc DOC document
J - 1 Work Item (Specifications).docx DOCX document
J - 8 Request for Spec Clarification - NEWPORT 21R4209.doc DOC document
J - 3 Category B Items NEWPORT 21R4209.xls XLS spreadsheet
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N3220521R4209

QUESTIONS AND ANSWERS #5

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

QUESTION #1: 7.1.7.1- Is there an allowance for the amount of Belzona application is to be required?

7.2.1- How many linear feet of edge grinding is to be required?

SPECIFICATION ITEM NO.: 108

PARAGRAPH / SECTION NO: 7.1.7.1& 7.2.1

TITLE: Machinery Space Coating

ANSWER: 7.1.7.1 - 10 square feet per bilge pocket (380 sqft total)

7.2.1 - Estimate approximately 13640 linear feet. Note: This is an approximate estimate based on General Ship Drawings.

QUESTION #2: Paragraph 3.1.2 v. 3.2: Paragraph 3.1.2 calls for 15 heat exchangers while paragraph 3.2 adds up to 19. Please clarify how many units total are being worked.

SPECIFICATION ITEM NO.: 201

PARAGRAPH / SECTION NO: Multiple

TITLE: Heat exchangers

ANSWER: 3.1.2 is incorrect. 3.2 is correct. There are 19 total. No “cleaning in place” fittings were installed at new construction, so the contractor will need to fabricate and install them.

QUESTION #3: Is paragraph 7.9.1 supposed to reference “paragraphs 3.1.2 and 3.1.3” instead of “paragraphs 3.1.1 and 3.1.2, as 3.1.1 would mean a far greater amount of area?

SPECIFICATION ITEM NO.: 989

PARAGRAPH / SECTION NO: 7.9.1

TITLE: Hull Coating

ANSWER: Correct, paragraph 7.9.1 should refer to paragraphs 3.1.2 and 3.1.3.