Amendment 0009 USNS NEWPORT N3220521R4209.docx
DOCX document 30 KB Posted
- Solicitation number
- N3220521R4209
About this file
This document provides answers to questions received from potential offerors on solicitation N3220521R4209 for the USNS NEWPORT (T-EPF 12) Mid-Term Availability (MTA). The period of performance for the MTA is from April 25, 2022 to June 8, 2022. Work items and allowances in the 0000 series were revised to reflect the reduced period of performance of 45 days. The answers clarify that there will be no additional opportunity for ship checks. Specification work item 532 and its references, which were omitted from the original solicitation documents, have been resent to potential offerors via DoD Safe.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N3220521R4209
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION B - SUPPLIES OR SERVICES AND PRICES
The following have been added by full text:
Q AND A RESPONSES #6
QUESTIONS AND ANSWERS #6
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
QUESTION #1: Work Item 532 is included in the J-1 document and in the J-2 document, however no specification for Work Item 532 was available via download, nor were its references. Please provide a download link for Work Item 532 and its associated references.
SPECIFICATION ITEM NO.: 532
PARAGRAPH / SECTION NO: ALL
TITLE: Inspect Submersible Bilge Pumps
ANSWER: Work Items and References were resent via DoD Safe.
QUESTION #2: Due to the change in scope will the period of performance be amended as well? If so, will the service items, such as WI 0011, be amended to show updated allowances for that timeframe?
SPECIFICATION ITEM NO.: Multiple
PARAGRAPH / SECTION NO: Multiple
TITLE: Period of performance
ANSWER: The period of performance for the USNS NEWPORT MTA is 4/25/2022 – 6/8/2022. 0000 series work items were revised to reflect the reduction to 45 days.
QUESTION #3: Will an additional ship check be granted due to the descoping of the package from a PSA/DD to an MTA?
SPECIFICATION ITEM NO.: Solicitation
PARAGRAPH / SECTION NO: Solicitation
TITLE: Ship check
ANSWER: There will not be another chance for ship checks.
(End of Summary of Changes) image1.wmf