Attachment J-3 CAT B KANAWHA FY22 Rev A.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- USNS KANAWHA (T-AO 196) MTA
- Solicitation number
- N3220521R4008
About this file
This document contains a price breakdown worksheet for a mid-term availability solicitation for the USNS KANAWHA (T-AO 196). The solicitation is issued by the Department of the Navy Military Sealift Command for ship repair and maintenance services. The price breakdown worksheet provides estimated labor hours and material costs for various work packages in categories including general services, hull and structural repairs, steel replacement, auxiliary machinery piping replacement, and continuation of existing services. Response is requested by the date listed in the attached solicitation and supporting documents. Award will be made based on best value determination considering technical and pricing factors.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WorkPackage J-3 Report
| GOVERNMENT PRICE BREAKDOWN | |||||||||||||||
| CATEGORY "B" ITEMS | |||||||||||||||
| N32205-21-R-4008 | |||||||||||||||
| Government's price will be broken down for each item of the specification, as follows: | |||||||||||||||
| GENERAL REQUIREMENT | QTY | UI | UNIT PRICE | TOTAL | PRIME CONTRACTOR | SUBCONTRACTOR | MANDATED SUB | OTHER COSTS | |||||||
| ITEM NO. | TITLE CAT B ITEM | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | PRICE | TOTAL PRICE | BASIS OF ESTIMATE | |||||
| CATEGORY "B" | |||||||||||||||
| 000 | GENERAL SERVICES AND REQUIREMENTS | ||||||||||||||
| 025 | PHYSICAL SECURITY AT PRIVATE CONTRACTOR FACILITY REV 28Nov18 | ||||||||||||||
| 7.11 | Cost To Maintain Physical Security At Private Contractor's Facility In Force Protection Condition Charlie | 1 | Day | ||||||||||||
| 7.11 | Cost To Establish Physical Security At Private Contractor's Facility In Force Protection Condition Charlie | 1 | Day | ||||||||||||
| 7.12 | Cost To Maintain Physical Security At Private Contractor's Facility In Force Protection Condition Delta | 1 | Day | ||||||||||||
| 7.12 | Cost To Establish Physical Security At Private Contractor's Facility In Force Protection Condition Delta | 1 | Day | ||||||||||||
| WI 025 SUBTOTAL | 4 | ||||||||||||||
| 026` | Final Vessel Cleaning | ||||||||||||||
| 7.1 | Cleaning Vessel | 1 | lot | ||||||||||||
| WI 026 SUBTOTAL | 1 | ||||||||||||||
| 030 | CONTINUATION OF SERVICES REV 04Jun20 | ||||||||||||||
| 7.1 | Extension of WI 010 OMT Office | 15 | Day | ||||||||||||
| 7.2 | Extension of WI 011 General Services For The Ship | 15 | Day | ||||||||||||
| 7.3 | Extension of WI 012 Information Services for Ship | 15 | Day | ||||||||||||
| 7.4 | Extenstion of WI 013 Project Planning and Monitoring | 15 | Day | ||||||||||||
| 7.5 | Extension of WI 016 Fire Protection and Ship's Safety Program | 15 | Day | ||||||||||||
| 7.6 | Extension of WI 019 Shipbaord Security | 15 | Day | ||||||||||||
| 7.7 | Extension of WI 020 Gas Free Certificates | 15 | Day | ||||||||||||
| WI 030 SUBTOTAL | 105 | ||||||||||||||
| 100 | HULL AND STRUCTURAL | ||||||||||||||
| 102 | KINGPOST REPAIR | ||||||||||||||
| 7.1.1 | FAS Station | 5 | Ea | ||||||||||||
| 7.1.2 | RAS Station | 2 | Ea | ||||||||||||
| WI 102 SUBTOTAL | 7 | ||||||||||||||
| 107 | STEEL REPLACEMENT | ||||||||||||||
| 7.1.1 | Steel Replacement | 10000 | LBS | ||||||||||||
| 7.1.2 | Rolled Steel Structural Shapes | 5000 | LBS | ||||||||||||
| 7.2.1 | Fillet Welds 6" or Less | 50 | EA | ||||||||||||
| 7.2.2 | Fillet Welds 7"- 12" | 50 | Ea | ||||||||||||
| 7.3.1 | Stricker Plate Replacement | 20 | Ea | ||||||||||||
| WI 107 SUBTOTAL | 15120 | ||||||||||||||
| 500 | AUXILIARY MACHINERY | ||||||||||||||
| 508 | MISC PIPING REPLACE | ||||||||||||||
| 7.1.1 | 8" schedule 80 pipe | 60 | ft | ||||||||||||
| 7.1.2 | 8" - 4 bolt flange flat face socket weld | 8 | ea | ||||||||||||
| 7.1.3 | 8" - 90 degree elbow | 4 | ea | ||||||||||||
| 7.1.4 | 6" schedule 80 Pipe | 80 | ft | ||||||||||||
| 7.1.5 | 6"- 4 bolt flange flat face socket weld | 8 | ea | ||||||||||||
| 7.1.6 | 6" - 90 degree Elbow | 4 | ea | ||||||||||||
| 7.1.7 | 5" schedule 80 Piping | 80 | ft | ||||||||||||
| 7.1.8 | 5" - 4 bolt flange flat face socket weld | 8 | ea | ||||||||||||
| 7.1.9 | 5" - 90 degree Elbow | 4 | ea | ||||||||||||
| 7.1.10 | 3" schedule 40 Piping | 80 | ft | ||||||||||||
| 7.1.11 | 3"- 4 bolt flange flat face socket weld | 8 | ea | ||||||||||||
| 7.1.12 | 3"- 90 degree Elbow | 4 | ea | ||||||||||||
| 7.1.13 | 2.5" schedule 40 Piping | 80 | ft | ||||||||||||
| 7.1.14 | 2.5"- 4 bolt flange flat face socket weld | 8 | ea | ||||||||||||
| 7.1.15 | 2.5"- 90 degree Elbow | 4 | ea | ||||||||||||
| WI 508 SUBTOTAL | 440 | ||||||||||||||
| TOTAL | 15676 |