20R3506 Attach_M_CONSOL.docx
DOCX document 17 KB Posted
- Attached to
- Long Term Tanker Time Charter Federal contract opportunity
- Solicitation number
- N32205-20-R-3506
About this file
This document outlines technical requirements for refueling at sea (CONSOL) station installations on vessels chartered under solicitation N32205-20-R-3506. The solicitation requests a long term time charter for tankers capable of performing CONSOL operations. The technical requirements specify equipment and configurations needed for the vessels to receive fuel from supply ships during underway replenishment operations. Details include installing two CONSOL receiving stations forward of living quarters to receive fuel from ROBB or NATO coupling delivery rigs simultaneously. Additional requirements address station equipment, testing, lighting, rigging drawings and replenishment procedures. The Navy will provide actual CONSOL station equipment while vessels are required to integrate structural and piping interfaces.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N32205-20-R-3506-0001.docx | DOCX document | |
| 20R3506 Attach_N_Request for Clarification_Question.docx | DOCX document | |
| 20R3506 Attach_H_ Wage Determination.pdf | ||
| 20R3506 Attach_A__GFP List.xlsx | XLSX spreadsheet | |
| 20R3506 Attach_B_Basic Pricing Data.xlsx | XLSX spreadsheet | |
| 20R3506 Attach_K_Specs_for_CBR-D_Decon_Station_.docx | DOCX document | |
| 20R3506 Attach_F_Tech Offer Worksheet.XLSX | XLSX spreadsheet | |
| 20R3506 Attach_L_Decon Station.PDF | ||
| 20R3506 Attach_O_DFARS 247-7026 Info Sheet.xls | XLS spreadsheet | |
| N32205-20-R-3506.docx | DOCX document | |
| 20R3506 Attach_J_MECSP Worksheet_.docx | DOCX document | |
| 20R3506 Attach_C_Crew Complement_.docx | DOCX document | |
| 20R3506 Attach_E_PWS (2_11_20).docx | DOCX document | |
| 20R3506 Attach_G_ATFP_CBRD_.docx | DOCX document | |
| 20R3506 Attach_I_SF LLL.pdf | ||
| 20R3506 Attach_D_ DD254.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT (M)
CONSOL
M-13.1 Vessel must be equipped upon delivery to perform Refueling at Sea (CONSOL only) operations.
M-13.2 A total of two (2) RAS receiving stations shall be installed that can receive a fueling rig with a ROBB or NATO coupling during Replenishment at Sea (RAS) operations. The capability to perform the simultaneous transfer of up to two (2) different fuel products shall be met. RAS stations shall be installed in fore and aft positions, forward of the house, with two (2) stations on one side either port or starboard.
M-13-3 Stations will be forward of the manifold (no more than half way between the forward tanks and manifold) and about similar distance between the manifold and the house (allowing sufficient room for safe working of cargo hoses, installation of hard points to accept spanwires, etc.). Exact location would be based on specific vessel configuration and in cooperation with Military Sealift Command.
M-13.4 Reference CONSOL drawings 2227933A (attached), Standard RAS Receiving Station Arrangement and Requirements, shall be used as guidance for installing RAS stations. Only rigging and fittings for the ROBB and NATO coupling configuration shall be installed. Since the probe receiver will not be required onboard, item numbers 1,2,5,6, and 7 listed on the reference drawing are not required to be sourced or installed. Appropriate reference drawing number for swivel joint assembly, Item 3 and reference drawing 3 is 805-2213159F.
M-13.5 Swivel joint assembly shall be installed so that center line of pivot is positioned iaw general notes 2 and 9 of drawing 2227933. Easing out line padeye, staple and cleat shall fabricated and installed/tested iaw general note 4 and drawing 6695696A. Eight-inch cleat shall be iaw drawing 804-2276338. Riding line and jigger tackle fittings shall be installed per general note 7 and procedures/views on sheet 4 of drawing 2227933. Riding line and jigger tackle cleats, items 19 & 22, shall be iaw drawing 803-2554187A. Jigger tackle and link, item 21, shall be iaw drawing 571-2227936D, Detail M.
M-13.6 All ships structures, including deck handrails, must be clear of the space defined as the CONSOL station maximum operating range: 30 degrees forward and aft, measured from the receiving station swivel joint center line, plus 12 inch side clearance (past the +/- 30 degrees). This requirement is documented in NAVSEA drawing 2213794 Rev D, general note 4, page 1, and as shown on “Locating Curve – Plan View”, page 2. Means to provide temporary lifelines when handrails are removed during operations must be provided iaw drawing 2227933A general note 8. Amount of removable handrail required for CONSOL operations determined by Plan View for ROBB fueling on sheet 4 of drawing 2227933A.
M-13.7 Design, install and test CONSOL station risers that meets the interface and location requirements shown in NAVSEA 2213794 Rev D. Interface flange to be 8 inch IPS in accordance with ASME B16.5. Location of flange face to be in accordance with “Locating Curve Plan View”, sheet 2 of NAVSEA drawing 2213794 Rev D. Riser height to be in accordance with NAVSEA drawing 2213794 Rev D sheet 1, Side Elevation; 48 +/- ½ inch from CL spanwire swivel assembly to CL of riser. Riser shall be designed to withstand a 24,000 lbs. pull without damage.
M-13.8 Testing: Spanwire attachment point (NATO long link), connect a test wire and fairlead outboard at 30 degrees forward and 30 degrees above horizontal. Apply a test load of 36,000 pounds to the test wire. Repeat for 30 degrees aft and 15 degrees below horizontal. All messenger inhaul padeyes to be tested to 9,000 pounds. Test easing out line padeye, staple and cleat to 5,300 lbs as an assembly, use-drawing 6695696 as guidance. Test riding line and jigger tackle padeyes and cleats to drawing 2556869. All static test loads shall be applied for 10-minute duration. After testing is complete, all components shall be inspected to ensure no damage or permanent distortion has taken place. After testing is complete, engraved stainless steel test label plates shall be installed near the tested component. Label plates shall provide name of fitting tested, static test load, drawing number which test was accomplished iaw, test date and location of test. Label plates shall be mechanically installed to ship’s structure with a silicone sealant barrier between the plate and structure to prevent corrosion. Copies of test documents shall be kept on board the ship.
M-13.9 Develop and provide station specific, detailed rigging drawings with written procedures. Drawing shall provide views documenting how and where to connect all rigging components, and describe in procedures how to receive an UNREP fuel delivery rig in accordance with NTTP 4-01.4, Underway Replenishment. The rigging drawing shall contain a detailed list, with part numbers, of all required components to perform CONSOL operations.
M-13.10 Night lighting shall be provided at each CONSOL station with illumination levels as specified in DOD-HDBK-289 Lighting on Naval Ships, paragraph 4.6.4 and Table XVII, RAS Illumination Levels. Lights to be installed with amber lenses; ship to be provided with a set of interchangeable red lenses for darkened ship conditions. Additionally, 25 Watt hull blue contour lights be provided located at the fore and aft extremes of that portion of the side parallel to the keel and a third light located at the mid-point of the other two lights. Capable of being visible at a distance of 3000 FT and not more than 24,000 FT. If permanently mounted and wired to the ship, contour lighting system must have an emergency power source. If not permanently mounted to the ship, battery power is acceptable and a SMS procedure shall be provided to install and remove contour and station lighting.
M-13.11 Ships will provide means to pull over the UNREP messenger with a variable speed of up to 150 fpm (if two speed motor is used a minimum speed of 75 fpm) with rated load of 4,000 lbs. If messenger line is not a direct pull to winch, additional tested anchorage points shall be installed and tested for use.
M-13.12 Actual RAS stations (hard point for the spanwire, piping to the cargo system, etc.) are provided by the owner. MSC will provide RAS equipment (station markers, boxes, probes, lights, paddles, etc).