Text version
Cat B Items
| Contractor's price will be broken down for each item of the specification, as follows: | ||||||||||||||||
| CATEGORY “B” ITEMS | ||||||||||||||||
| GENERAL REQUIREMENT | Price / Tank | QTY | UI | Unit Price | Total | PRIME Contractor | SUBCONTRACTOR | OTHER COSTS | ||||||||
| ITEM NO. | TITLE CAT B ITEM | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | Total Labor Hours | Total Material | TOTAL PRICE | ||||||
| CATEGORY "B" | ||||||||||||||||
| 025 | PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION BRAVO-DELTA | |||||||||||||||
| 7.11 | COST TO ESTABLISH PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION CHARLIE | 1 | DAY | |||||||||||||
| 7.12 | COST TO ESTABLISH PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION DELTA | 1 | DAY | |||||||||||||
| 7.11 | COST TO MAINTAIN PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION CHARLIE | 1 | DAY | |||||||||||||
| 7.12 | COST TO MAINTAIN PHYSICAL SECURITY AT PRIVATE CONTRACTOR'S FACILITY IN FORCE PROTECTION CONDITION DELTA | 1 | DAY | |||||||||||||
| WI 025 SUBTOTAL | ||||||||||||||||
| 030 | CONTINUATION OF SERVICES | |||||||||||||||
| 7.1 | Overhaul Management Team | 15 | DAY | |||||||||||||
| 7.2 | General Services For The Ship | 15 | DAY | |||||||||||||
| 7.3 | Information Technology Services | 15 | DAY | |||||||||||||
| 7.4 | Project Planning and Monitoring | 15 | DAY | |||||||||||||
| 7.5 | Fire Protection and Ship's Safety | 15 | DAY | |||||||||||||
| 7.6 | Shipboard Access and Security | 15 | DAY | |||||||||||||
| 7.7 | Gas Free Certificates | 15 | DAY | |||||||||||||
| WI 030 SUBTOTAL | ||||||||||||||||
| 107 | Structral Steel Repairs | |||||||||||||||
| 7.2.1 | Structure Steel Plate | 10,000 | LBS | |||||||||||||
| 7.2.2 | Structure Shapes | 5,000 | LBS | |||||||||||||
| 7.3.1 | 6" long crack or less cracked fillet welds | 50 | EA | |||||||||||||
| 7.3.2 | 7"-12" long crack or less cracked fillet welds | 50 | EA | |||||||||||||
| 7.3.3 | Pits Clad Welds | 50 | EA | |||||||||||||
| 7.4.1 | Sounding tube stricker plates | 20 | EA | |||||||||||||
| WI 107 SUBTOTAL | ||||||||||||||||
| 112 | Zinc Anodes | |||||||||||||||
| 7.2 | Zinc Anode Studs | 500 | Studs | |||||||||||||
| WI 112 SUBTOTAL | ||||||||||||||||
| 913 | DRYDOCKING AND UNDOCKING SHIP – ADDITIONAL DAYS | |||||||||||||||
| 7.1 | Submit unit price per day up to a maximum of fifteen (15) days to continue all services in accordance with parent item if directed | 15 | DAY | |||||||||||||
| WI 913 SUBTOTAL |
Total CAT "B"
| &14USNS LARAMIE (T-AO 203) | &14CONTRACTOR PRICE BREAKDOWN |
| &"Arial,Bold"CATEGORY "B" ITEMS | &14N32205-18-R-4007 |
ATTACHMENT J-3