RFP_QandA__2_Solicitation_N32205-17-R-4703.docx

DOCX document 26 KB Posted

Attached to
USNS YUMA Post Shakedown Availability & Dry Dock Federal contract opportunity
Solicitation number
N32205-17-R-4703
Issued by
Department of the Navy Military Sealift Command

About this file

Q&A #2 _ Solicitation N32205-17-R-4703

View the file

Other files for this federal contract opportunity

Other files attached to USNS YUMA Post Shakedown Availability & Dry Dock, newest first.
File Type Posted
RFP_QandA__3_Solicitation_N32205-17-R-4703.docx DOCX document
17-R-4703-0004.docx DOCX document
17-R-4703-0003.docx DOCX document
RFP_QandA__1_Solicitation_N32205-17-R-4703.docx DOCX document
17-R-4703-0002.docx DOCX document
17-R-4703-0001.docx DOCX document
J - 14 Technical Data Non-Disclosure - YUMA 17-R-4703.docx DOCX document
J - 2 Category A Items - YUMA 17-R-4703.xlsx XLSX spreadsheet
DD Form 1423-1 A105 JHSV.pdf PDF
DD Form 1423-1 A605 JHSV.pdf PDF
DD Form 1423-1 A108 JHSV.pdf PDF
DD Form 1423-1 A1002 JHSV.pdf PDF
DD Form 1423-1 A104 JHSV.pdf PDF
DD Form 1423-1 A911 JHSV.pdf PDF
Solicitation_N32205-17-R-4703_USNS_YUMA_(T-EPF_8)_PSA-DD.docx DOCX document
J - 3_Category B Items - YUMA 17-R-4703.xls XLS spreadsheet
J - 10 Interport Differential - YUMA 17-R-4703.doc DOC document
DD Form 1423-1 A903 JHSV.pdf PDF
DD Form 1423-1 A910 JHSV.pdf PDF
J - 11 Dry Dock Evaluation Form - YUMA 17-R-4703.docx DOCX document
DD Form 1423-1 A202 JHSV.pdf PDF
DD Form 1423-1 A110 JHSV.pdf PDF
J-4 GFP YUMA.pdf PDF
DD Form 1423-1 A301 JHSV.pdf PDF
DD Form 1423-1 A606 JHSV.pdf PDF
J - 8 Request for Spec Clarification - YUMA 17-R-4703.doc DOC document
DD Form 1423-1 A905 JHSV.pdf PDF
DD Form 1423-1 A502 JHSV.pdf PDF
DD Form 1423-1 A505 JHSV.pdf PDF
DD Form 1423-1 A401 JHSV.pdf PDF
DD Form 1423-1 A902 JHSV.pdf PDF
J - 12 Past Performance Data - YUMA 17-R-4703.doc DOC document
DD Form 1423-1 A603 JHSV.pdf PDF
DD Form 1423-1 A503 JHSV.pdf PDF
N104-17-R-4703_Redacted_J&A_1.PDF PDF
DD Form 1423-1 A912 JHSV.pdf PDF
DD Form 1423-1 A106 JHSV.pdf PDF
J - 13 Past Performance Questionnaire - YUMA 17-R-4703.docx DOCX document
J - 9 Disclosure of Lobbying Activities - YUMA 17-R-4703.doc DOC document
DD Form 1423-1 A504 JHSV.pdf PDF
DD Form 1423-1 A604 JHSV.pdf PDF
J - 7 MSC Ship Repair Facility Survey - YUMA 17-R-4703.docx DOCX document
DD Form 1423-1 A906 JHSV.pdf PDF
DD Form 1423-1 A102 JHSV.pdf PDF
DD Form 1423-1 A508 JHSV.pdf PDF
DD Form 1423-1 A904 JHSV.pdf PDF
DD Form 1423-1 A501 JHSV.pdf PDF
DD Form 1423-1 A103 JHSV.pdf PDF
SYNOPSIS_N32205-17-R-4703_USNS_YUMA_PSA-DD.docx DOCX document
USNS_YUMA_-_Sources_Sought_Notice.doc DOC document
Show all 50

USNS YUMA Post Shakedown Availability & Dry Dock has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-17-R-4703

QUESTIONS AND ANSWERS #2

The following are answers to questions received from potential offerors. The answers provide clarification only and do not constitute an amendment to the solicitation.

1. Item 0901: Two versions of Work Item 901 were provided, one dated 29 April 2016 and the other dated 24 Jan 2017. Please clarify which is to be used.

ANSWER: WI 901 dated 29 April 2016 has been revised. Utilize revised WI 901; to be provided via AMRDEC Safe.

2. Item 0601 paragraph 4.1 and 7.3: Statement of work in paragraph 7.3 states that the contractor shall take delivery of GFM listed in section 4.1 and install it in place of the deployed MES unit. However, section 4.0 states that there is no GFM. Is there or is there not any GFM? If so, please specify what will be provided.

ANSWER: There is no GFM for this work item. Contractor not to perform services at 7.3. Contractor to perform requirements listed in paragraph 7.3.1 and 7.3.2.

3. Item 0506: Are the requirements for insulation and heat tracing as stated in paragraphs 7.8 & 7.8.1 in addition to the insulation and heat tracing installed by work items 304 and 305?

ANSWER: Yes.

4. Item 0307 paragraph 7.2.1: Can a size, type, design etc. information be provided for the two (2) junction boxes required by paragraph 7.2.1? Paragraph 7.2.1 also requires calibration of system upon completion. Is this work to be accomplished by Wartsila?

ANSWER: Work to be accomplished by Wartsila. Junction box specifications to be provided via AMRDEC Safe.