0313_A_Shipyard_Support_for_UPS_Replacement.doc

DOC document 114 KB Posted

Attached to
ROH/DD USNS MCLEAN Summer 2016 Federal contract opportunity
Solicitation number
N32205-16-R-4306
Issued by
Department of the Navy Military Sealift Command

About this file

Revisions to WI 0313

View the file

Other files for this federal contract opportunity

Other files attached to ROH/DD USNS MCLEAN Summer 2016, newest first.
File Type Posted
Revised_WI_0116_PRESERVATION_OF_HOUSE_Amend1.docx DOCX document
Request_for_Spec_Clarification-0007.doc DOC document
521-8495205_B.pdf PDF
MCLEAN_Amndmt_0003_Zip_File.zip ZIP file
Revised_Solicitation_Amndmt_0002.doc DOC document
0416_A_VDR_UPGRADE_G1_to_G4_Amend_1.doc DOC document
0110_A_Anchor_Windlass_Foundation_Mod_Amend_1.docx DOCX document
MCLEAN_J_Zip.zip ZIP file
MCLEAN_Solicitation_FY16_ROH_DD.doc DOC document
N32205_16_R_4306_J A_1.PDF PDF
MCLEAN_Synopsis.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS AMELIA EARHART

(T-AKE 6)

ELECTRICAL

N32205-16-C-4301

15 February 2016

ITEM NO. 0313

Category “A” MSC/n756/adr/sa Shipyard Support for UPS Installation (T-AKE Transalt 434)

USNS WILLIAM MCLEAN

(T-AKE 12)

ELECTRICAL

N32205-16-R-4306

3 March 2016

ITEM NO. 0313

Category “A”

MSC/N756/PJR

Shipyard Support for UPS Installation

1.0 ABSTRACT:

This item describes the Shipyard Support for Government Furnished Contractor for the installation of a replacement UPS System for Engine Room Equipment.

2.0 REFERENCES/ENCLOSURES:

2.1 References:

2.1.1 MSC Drawing No. 320-8495201; Uninterruptible Power Supply (UPS) Replacement.

2.1.2 MSC Drawing No. 320-8499066; T-AKE Electrical System One-Line Diagram

2.2 Enclosure:

2.2.1 Shipyard Support Installation Plan

3.0 ITEM LOCATION/QUANTITY/DESCRIPTION

3.1 Locations/Quantity:

3.1.1 Locations: EDG Room (02-73-1)

Engineer Operating Station (3-66-2)

Engineers Storeroom (3-70-1)

Electrical Workshop (3-72-2) Passageway Engineers Office (2-67-2)

3.1.2 Quantity: See BOM

3.2 Item Description Data:

3.2.1 Bill of Material: (Government Furnished Material)

Item #
QTY
Description
Part Number
1
1
UPS #1 Control Cabinet
CPCABTLCP1
2
1
UPS #1 Distribution Cabinet
CPCDP-1P120LCDP1
3
1
UPS #2 Control Cabinet
CPCABTLCP2
4
1
UPS #2 Distribution Cabinet
CPCDP-1P120LCDP1
5
1
Isolation Transformer #1
ES5H37S
6
1
Isolation Transformer #2
ES5H37S
7
1
UPS #1
CPCHV25KVA120-MOD
8
1
UPS #2
CPCHV25KVA120-MOD
9
1
Battery Bank #1
CPC10BATT-130V
10
1
Battery Bank #2
CPC10BATT-130V
11
1
Battery Charger #1
ARE-M13035A
12
1
Battery Charger #2
ARE-M13035A
13
1
Battery Bank #1 Disconnect Switch
CPCDS-130VDC
14
1
Battery Bank #1 Disconnect Switch
CPCDS-130VDC
15
1
UPS #1 Foundation
16
1
UPS #2 Foundation
17
1
Battery Charger #1 Foundation
18
1
Battery Charger #2 Foundation
19
1
Isolation Transformer #1 Foundation
20
1
Isolation Transformer #2 Foundation
21
4
Deck Tubes for Isolation Transformers

3.2.2 Quantities given in the Bill of Materials are considered estimates. The Contractor shall provide reasonable additional material in order to install a fully functional system that meets the requirements of this specification.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS/SERVICES:

4.1 GE, Custom Panel and Controls, and materials listed paragraph 3.2.1.

5.0 NOTES

5.1 The contractor and all subcontractors regardless of tier shall consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7 and 23.

5.2 The contractor and all subcontractors regardless of tier are advised to review other work items under this contract, to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 0001.

5.3 This class of ships contains High Voltage (HV) electrical systems (6.6 kV). The contractor and subcontractors shall obey all posted and verbal instructions regarding safety and exclusion from High Voltage areas. At no time shall a contractor or subcontractor approach, work on, or enter a High Voltage area without proper authorization.

5.4 THE T-AKE CLASS ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK AND WHITE. THE CONTRACTOR SHALL ASSUME ALL ELECTRICAL CABLES ARE HOT UNTIL TESTED OTHERWISE. THE CONTRACTOR SHALL TEST ALL ELECTRICAL CABLES TO ENSURE THEY ARE DEAD PRIOR TO WORK ON THE ITEM.

5.5 All shipboard lockout tag out procedures shall be followed by the contractor.

6.0 QUALITY ASSURANCE REQUIREMENTS:

6.1 All Electrical work shall be performed in accordance with ABS, USCG, and IEEE-45.

7.0 STATEMENT OF WORK

7.1 Arrangement/Outfitting:

7.1.1 Provide Staging/Scaffolding as required below Engineers Storeroom and HV switchboards and above MDG’s.

7.1.2 Provide JLG, Lift, or staging in Helo Hanger to gain access to access trunk for Emergency Switchboard.

7.2 Structural:

7.2.1 Removals

7.2.1.1 Provide labor and materials to remove any foundations, brackets, Ventilation ducts that may be in way of the installation and removal of equipment.

7.2.2 Installations

7.2.2.1 Provide labor and materials to weld to deck GFM foundations for the following Equipment to be installed in Electric Shop

a. UPS CPCHV25KVA120-MOD #2

7.2.2.1.a.1 Shipyard to provide a ½” Steel plate to be welded on existing foundation and to allow the new foundation to be welded in place without having to remove insulation from below.

b. Battery Bank CPC10BATT-130V #2

7.2.2.1.b.1 Shipyard to provide a ½” Steel plate to be welded on existing foundation and to allow the new foundation to be welded in place without having to remove insulation from below.

c. Battery Charger ARE-M13035A #2

7.2.2.2 Provide labor and materials to weld to deck GFM foundations for the following Equipment to be installed in Engineers Storeroom

a. UPS CPCHV25KVA120-MOD #1

b. Battery Bank CPC10BATT-130V #1

c. Battery Charger ARE-M13035A #1

7.2.2.3 Provide labor and materials to weld GFM foundations for the following Equipment in passageway Engineers office 2-67-2.

a. Install Isolation Transformer #1

b. Install Isolation Transformer #2

c. Drill holes and install 4 each Deck Tubes for the isolation Transformers

7.3 Mechanical:

7.3.1 Removals

7.3.1.1 Provide Rigging Support to remove the following Equipment from EOS.

a. Remove #1 Propulsion UPS

b. Remove #2 Propulsion UPS

c. Remove #1 AMCS UPS

d. Remove #2 AMCS UPS

7.3.1.2 Provide Rigging Support to remove the following Equipment from Engineers Storeroom.

a. Remove #1 Main & SS Swbd Control Power UPS

b. Remove #2 Main & SS Swbd Control Power UPS

7.3.2 Installations

7.3.2.1 Provide Rigging Support to install the following Equipment in EOS

a. UPS #1 Control Cabinet, GFM, Item #1

b. UPS #1 Distribution Cabinet, GFM, Item #2

c. UPS #2 Control Cabinet, GFM, Item #3

d. UPS #2 Distribution Cabinet, GFM, Item #4

7.3.2.2 Provide Rigging Support to install the following Equipment in Engineers Storeroom.

a. Install Battery Bank #1 Rack, GFM Item #9

b. Install Battery Charger #1, GFM, Item #11

c. Install MCCS #1 UPS, GFM Item #7

7.3.2.3 Provide Rigging Support to install the following Equipment in Electricians Work Shop.

a. Install Battery Bank #2 Rack, GFM Item #10

b. Install MCCS #2 UPS, GFM Item #8

c. Install Battery Charger #2, GFM, Item #12

7.3.2.4 Provide Rigging Support to install the following Equipment in passageway Engineers office 2-67-2.

a. Install Isolation Transformer #1, GFM Item #5

b. Install Isolation Transformer #2, GFM Item #6

7.4 Modifications: None

7.5 Electrical

7.5.1 Removals – No Shipyard Support Required.

7.5.2 Installations – As required, Provide Welding Support for hangers, brackets, and Cable Bulkhead tubes to include gas free, fire watch, welder, and testing.

7.6 Electronics:

7.6.1 Removal – No Shipyard Support Required.

7.6.2 Installation – No Shipyard Support Required.

7.7 Preparation of Drawings: No Shipyard Support Required.

7.8 Testing and Inspecting: Shipyard to provide any necessary testing and inspection for all work they perform.

7.9 Painting: Paint all new and disturbed surfaces to match surrounding surfaces.

7.10 Marking: No Shipyard Support Required.

7.11 Manufacturer's Representative: GE and Custom Panel and Controls are providing direction and the UPS system to accomplish the installation under a separate contract. The intent of the work item is for the Shipyard to provide Support Services to accomplish the UPS upgrade installation.

7.11.1 POC: David Thornton GE Energy

Cell 804-955-0015

E-Mail David.thornton2@ge.com

8.0 GENERAL REQUIREMENTS: None additional.

Enclosure: 2.2.1

0313-1

Shipyard Support

Location Task Equipment RDD

Engine Room Staging Under Engineers Store Room 7/20/16

Electricians Work Shop Rigging (Removal) Equipment/cabinets as required 7/20/16

EOS Removal of Door and hand rail Allow access for UPS removals 7/21/16

EOS Rigging (Removal) PMS1 UPS 7/21/16

EOS Rigging (Removal) PMS2 UPS 7/21/16

Electricians Work Shop Welding Foundation UPS #2 7/21/16

Engine Room Staging Above MDG 1 -4 7/22/16

EOS Removal of False overhead Allow access for cable pulling 7/22/16

Engineers Store Room Rigging (Removal) Swbd UPS #1 7/23/16

Engineers Store Room Rigging (Removal) Swbd UPS #2 7/23/16

EOS Remove lagging in overhead For Transformer Foundations and Tubes 7/23/16

Purifier Room Remove lagging in overhead For Electrician Work Shop Foundations 7/23/16

EOS Rigging (Removal) AMCS1 UPS 7/23/16

EOS Rigging (Removal) AMCS2 UPS 7/23/16

Electricians Work Shop Rigging (Install) Battery Rack #2 7/25/16

Electricians Work Shop Cutting/Burning Sand Blaster 7/26/16

EOS Rigging (Install) UPS #1 Distribution Cabinet 7/26/16

EOS Rigging (Install) UPS #1 Control Cabinet 7/26/16

EOS Rigging (Install) UPS #2 Distribution Cabinet 7/26/16

EOS Rigging (Install) UPS #2 Control Cabinet 7/26/16

Electricians Work Shop Welding Foundation Battery Rack #2 7/26/16

Electricians Work Shop Provide angle suppot for Battery Rack Battery Rack #2 7/26/16

Electricians Work Shop Welding Foundation Battery Charger #2 7/27/16

Electricians Work Shop Prime Foundations Battery Rack, Battery Charger, and UPS 7/29/16

Stairwell 3-66-01 Welding Foundation Isolation Transformer #1 7/30/16

Stairwell 3-66-01 Welding Foundation Isolation Transformer #2 7/30/16

Stairwell 3-66-01 Welding Deck Tubes Isolation Transformer #1 7/30/16

Stairwell 3-66-01 Welding Deck Tubes Isolation Transformer #2 7/30/16

Electricians Work Shop Paint Top Coat of foundations Battery Rack, Battery Charger, and UPS 7/30/16

Purifier Room Install lagging in overhead For Electrician Work Shop Foundations 7/31/16

Stairwell 3-66-01 Prime Foundations Transformers and Deck Tubes 8/1/16

Stairwell 3-66-01 Paint Top Coat of foundations Transformers and Deck Tubes 8/2/16

Engineers Store Room Provide 1/2 Steel Plate, weld over existing UPS #1 8/2/16

Engineers Store Room Welding Foundation UPS #1 8/2/16

Engineers Store Room Provide 1/2 Steel Plate, weld over existing Battery Rack #1 8/2/16

Engineers Store Room Rigging (Install) Battery Rack #1 8/3/16

Engineers Store Room Welding Foundation Battery Rack #1 8/4/16

EOS Install lagging in overhead For Transformer Foundations and Tubes 8/5/16

Engineers Store Room Welding Foundation Battery Charger #1 8/5/16

Engineers Store Room Prime Foundations Battery Rack, Battery Charger, and UPS 8/8/16

Engineers Store Room Paint Top Coat of foundations Battery Rack, Battery Charger, and UPS 8/8/16

Hanger Bay JLG or staging for access trunk Emergency Switchboard 8/16/16

EOS Reinstallation of False overhead Allow access for cable pulling 8/23/16

USNS William McLean UPS Upgrade Shipyard Support Schedule