N32205-15-R-1007
USNS LARAMIE (T-AO 203)
REQUEST FOR SPECIFICATION CLARIFICATION
NAME OF CONTRACTOR: ___ _____________ __
SPECIFICATION ITEM NO.: __801_________________
PARAGRAPH / SECTION NO:_7.1.4____________ ___
TITLE: ___GALLEY RANGE EXHAUST SYSTEM CLEANING____ __
QUESTION:
Paragraph 7.1.4 states “Renew all fasteners and gaskets”.
Is the intent to replace fasteners and gaskets in areas disassembled to accomplish system cleaning or to replace all fasteners and gaskets in entire ducting system associated with paragraph 3.2.1 & 3.2.3?
ANSWER:
REPLACE FASTENERS AND GASKETS IN AREAS DISASSEMBLED TO ACCOMPLISH SYSTEM CLEANING.
ATTACHMENT J - 8