CLARIFICATION_QUESTION-RESPONSE-4.docx

DOCX document 25 KB Posted

Attached to
USNS CARL BRASHEAR (T-AKE 7) Regular Schedule Overhaul/Dry-Docking
Solicitation number
N32205-13-R-3017
Issued by

About this file

CLARIFICATION QUESTION RESPONSE - 4

View the file

Other files

File Type Posted
N32205-13-R-3017_Amendment_0005.doc DOC document
N32205-13-R-3017-0004.doc DOC document
N32205-13-R-3017-0003.doc DOC document
N32205-13-R-3017-0002.doc DOC document
0909_A_RENEW_MGCC_ANODES_rev.docx DOCX document
0903_A_Polish_Bow_Thruster_Propeller.doc DOC document
CLARIFICATION_QUESTION-RESPONSE-3.docx DOCX document
CLARIFICATION_QUESTION-RESPONSE-2.docx DOCX document
N32205-13-R-3017-0001.doc DOC document
CLARIFICATION_QUESTION-RESPONSE.docx DOCX document
J-ATTACHMENTS.zip ZIP file
N32205-13-R-3017.doc DOC document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-13-R-3017

QUESTIONS AND ANSWERS

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

1. WI 525 Para 7.3 require a replacement 108 ft3 cylinder. Contractor needs to know if this is to be fitted with a Kidde ‘N-gauge’ or a standard gauge?

ANSWER:

The new 108 ft3 cylinder shall be fitted with a Kidde “N-Gauge”.

2. Contractor has been informed by Manufactures representative “NavTech Electronics” that item 0402 is covered in its entirety in item 0401. Contractor recommends canceling item 0402. Please advise.

ANSWER:

Government agrees with Manufacturer’s Representative and Contractor. Work Item 0402 shall be cancelled.