CLARIFICATION_QUESTION-RESPONSE-3.docx

DOCX document 22 KB Posted

Attached to
USNS CARL BRASHEAR (T-AKE 7) Regular Schedule Overhaul/Dry-Docking
Solicitation number
N32205-13-R-3017
Issued by

About this file

Clarification question responses - 3

View the file

Other files

File Type Posted
N32205-13-R-3017_Amendment_0005.doc DOC document
CLARIFICATION_QUESTION-RESPONSE-4.docx DOCX document
N32205-13-R-3017-0004.doc DOC document
N32205-13-R-3017-0003.doc DOC document
N32205-13-R-3017-0002.doc DOC document
0909_A_RENEW_MGCC_ANODES_rev.docx DOCX document
0903_A_Polish_Bow_Thruster_Propeller.doc DOC document
CLARIFICATION_QUESTION-RESPONSE-2.docx DOCX document
N32205-13-R-3017-0001.doc DOC document
CLARIFICATION_QUESTION-RESPONSE.docx DOCX document
J-ATTACHMENTS.zip ZIP file
N32205-13-R-3017.doc DOC document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-13-R-3017

QUESTIONS AND ANSWERS

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

1. For estimating purposes how many square feet should the contractor consider to mechanically clean to SSPC-SP11 profile on the 8 ea RAS stations?

ANSWER:

Contractor shall assume 300 square feet per RAS station.