Attch_02_Contract_Surveillance_Plan.docx

DOCX document 44 KB Posted

Attached to
4. 11. 3 Ship and Air Integrated Warfare (SAIW) Division Program Management Support Services
Solicitation number
N00421-16-R-0049
Issued by

About this file

Attachment 02 - Contract Surveillance Plan

View the file

Other files

File Type Posted
Attch_07_COR_Designation.docx DOCX document
P4_Streamlined_Rates_for_Order_Pricing.xlsx XLSX spreadsheet
Attch_01_Wage_Determinations.docx DOCX document
Attch_05_Authorized_Subcontractors.docx DOCX document
P6_Prime_Cost_Summary_Spreadsheet.xls XLS spreadsheet
Attch_04_OCI_List.docx DOCX document
P3_Fully_Burdened_Labor_Rates.xls XLS spreadsheet
P7_Sub_Cost_Summary_Spreadsheet.xls XLS spreadsheet
Exhibit_A_CDRLs.xlsx XLSX spreadsheet
Attch_02_DD-254.pdf PDF
P2_Contractor_Performance_Assessment_Questionnaire.pdf PDF
Attch_03_Data_Item_Transmittal_Form.docx DOCX document
N00421-16-R-0049_REVISED_DRAFT_Solicitation.docx DOCX document
Attch_06_Authorized_Key_Personnel.doc DOC document
P1_Past_Performance_Information_Form.pdf PDF
REVISED_DRAFT_N00421-16-R-0049.docx DOCX document
Attch_05_OCI_List.docx DOCX document
P1_Past_Performance_Information_Form.pdf PDF
P4_Streamlined_Rates_for_Order_Pricing.xlsx XLSX spreadsheet
Attch_01_Wage_Determinations.docx DOCX document
Attch_06_Authorized_Subcontractors.docx DOCX document
P7_Sub_Cost_Summary_Spreadsheet.xls XLS spreadsheet
P3_Fully_Burdened_Labor_Rates.xls XLS spreadsheet
P2_Contractor_Performance_Assessment_Questionnaire.pdf PDF
Attch_07_Authorized_Key_Personnel.doc DOC document
Attch_03_Contract_Surveillance_Plan.docx DOCX document
P6_Prime_Cost_Summary_Spreadsheet.xls XLS spreadsheet
Attch_08_COR_Designation.docx DOCX document
Attch_04_Data_Item_Transmittal_Form.docx DOCX document
Attch_02_DD-254.pdf PDF
Exhibit_A_CDRLs.xlsx XLSX spreadsheet
P1_Past_Performance_Information_Form.pdf PDF
Attch_05_Authorized_Key_Personnel.doc DOC document
Attch_07_Locator_Form.doc DOC document
Attch_04_OCI_List.docx DOCX document
Attch_06_Authorized_Subcontractors.docx DOCX document
Attch_01_DD-254.pdf PDF
P5_Prime_Cost_Summary_Spreadsheet.xls XLS spreadsheet
Attch_03_Data_Item_Transmittal_Form.docx DOCX document
Attch_09_COR_Designation.docx DOCX document
N00421-16-R-0049_DRAFT_Solicitation.docx DOCX document
P3_Fully_Burdened_Labor_Rates.xls XLS spreadsheet
P6_Sub_Cost_Summary_Spreadsheet.xls XLS spreadsheet
Attch_08_Wage_Determinations.docx DOCX document
P4_Streamlined_Rates_for_Order_Pricing.xlsx XLSX spreadsheet
P2_Contractor_Performance_Assessment_Questionnaire.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N00421-16-R-0049 Enclosure (1)

N00024-12-R-XXXX

Enclosure (3) Contract Surveillance Plan (CSP) for Ship & Air Integrated Warfare(SAIW) Management Support

1. Purpose This Contract Surveillance Plan (CSP) is a Government developed and applied document used to make sure the systematic quality assurance methods are used in the administration of the contract for Management Support to the SAIW Division. The intent is to ensure that the contractor performs in accordance with the performance metrics and the Government receives the quality of services called for in the contract.

This contract is for technical, professional, and management support services to support the SAIW Division of the Rapid Capability Engineering & Integration Department, NAVAIR, St. Inigoes, MD. The contractor shall provide support in the areas of Contract Management, Systems Engineering, Project Management, Organizational Management, Administrative, and Hardware Acquisition Support.

This contract will have cost plus fixed fee labor CLINs and Cost CLINs for Other Direct Charges (ODCs) (Material and Travel). The contract will be for a five year ordering period. A properly executed CSP will assist the Government in achieving the objectives of this procurement.

2. Authority Authority for issuance of this CSP is provided under Contract Section E – Inspection and Acceptance, which provides for inspections and acceptance of the services and documentation called for in the contract, which will be executed by the Contracting Officer or a duly authorized representative.

3. Scope To fully understand the roles and responsibilities of the parties, it is important to first define the distinction in terminology between Quality Control Plan and the CSP. The contractor, and not the Government, is responsible for the Quality Control Plan, which defines the management and quality control actions necessary to meet the quality standards set forth in the contract.

The CSP on the other hand, is put in place to provide Government surveillance oversight of the contractor’s efforts to assure that they are timely, effective, and are delivering the results specified in the order.

4. Government Resources The following definitions for Government resources are applicable to this plan:

Contracting Officer (CO): A person duly appointed with the authority to enter into (Procuring Contracting Officer (PCO)) contract or administer (Administrative Contracting Officer (ACO)) contracts and make related determinations and findings on behalf of the Government. The PCO for this contract is Mr. Thomas E. Stann, AIR-2.5.1.3. The ACO will be designated in the resulting contract. Contracting officers are designated via a written warrant that sets forth limitations of authority.

Contracting Officer Representative (COR): An individual appointed in writing by the PCO to act as their authorized representative to assist in administering the contract. The COR will be appointed in the resulting order. The limitations of authority are contained in the letter of appointment.

Alternate Contracting Officer Representative (ACOR): An individual appointed in writing by the PCO to act as their authorized representative, in the absence of the COR, to assist in administering the contract. The ACOR will be appointed in the resulting contract. The limitations of authority are contained in a written letter of appointment.

Government Project Leads: The COR designates individual Government Project Leads to assist in administering of specific efforts under the contract.

5. Responsibilities The following Government resources shall have responsibility for the implementation of this CSP:

Contracting Officer: The Contracting Officer ensures performance of all necessary actions for effective contracting, ensures compliance with the terms of the contract and safeguards the interests of the United States in the contractual relationship. It is the Contracting Officer that assures the Contractor receives impartial, fair and equitable treatment under the contract. The Contracting Officer is ultimately responsible for the final determination of the adequacy of the contractor’s performance Contracting Officer Representative (COR): The COR is responsible for technical administration of the contract and assures proper Government surveillance of the contractor’s performance. The COR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the contractor deems may affect contract price, terms or conditions shall be referred to the Contracting Officer for action.

Alternate Contracting Officer’s Representative (ACOR): The ACOR is responsible for technical administration of the contract and assures proper Government surveillance of the contractor’s performance. The ACOR is not empowered to make any contractual commitments or to authorize any changes on the Government’s behalf. Any changes that the contractor deems may affect contract price, terms or conditions shall be referred to the Contracting Officer for action.

Government Project Leads: The Government Project Lead is responsible for assisting in administering of specific efforts under the contract. A Government Project Lead cannot, in any manner, alter the scope of the contract, make commitments or authorize any changes on the Government’s behalf.

6.Methods of QA Surveillance
a.Contractor Performance Assessment Reporting System (CPARS): The marketplace for advanced research and development, systems engineering, and life-cycle support of electronics, communications, and information systems services is very competitive. As such, the successful offeror has a vested interest in the Government-generated CPARS under this contract.
b.CSP: An evaluation using the CPARS format will be performed quarterly. This evaluation will be one determinant in issuing future orders. The Government will address the quality of product or service, schedule, cost control, business relations, management, and other important areas for this procurement. Some of the monitoring methods to be used will be Government observation, review of reports, customer feedback, and review of CDRLs. As this information may affect future source selections throughout DoD as well as the continuation of the order, the annual Government assessment will be used appropriately as an additional performance oversight and communication tool with the CSP. The below listed methods of surveillance shall be used by the COR, ACOR, and government project leads in the technical administration of this CSP. In addition to the below instructions, the form to be used for documentation of quality assurance surveillance is the CSP provided herein.
7.Surveillance

Enclosures (1) provides the checklist and means for the COR to document on a quarterly basis the results of the surveillance and shall be provided to the Contracting Officer on a quarterly basis.

8. Documentation In addition to providing quarterly reports to the Contracting Officer, the COR will maintain a complete Quality Assurance file. The file will contain copies of all reports, evaluations, recommendations, and any actions related to the Government’s performance of the quality assurance function, including the originals of the Surveillance Activity Checklist. All such records will be maintained for the life of the order. The COR shall forward these records to the Contracting Officer at termination or completion of the order.

9. Enclosures Enclosure (1) – Surveillance Activity Checklist

N00421-16-R-0049 Attachment 2

SURVEILLANCE ACTIVITY CHECKLIST

Quarterly Surveillance:

The COR will perform a quarterly assessment of Quality, Schedule, Cost Control, Business Relations, Management, and Other Areas as applicable utilizing the CPARS evaluation rating definitions.

Description
Surveillance

Method/ Measure Date Planned Date Completed

Quality
Schedule
Cost Control
Business

Relations Mgmt

Other

Provide Project Management Support IAW PBSOW Para 3.1.
100% Inspection by COR, ACOR, and/or Government Project Leads.
Provide Organizational Management Support IAW PBSOW Para 3.2.
100% Inspection by COR, ACOR, and/or Government Project Leads.
Provide Administrative Support IAW PBSOW Para 3.3.
100% Inspection by COR, ACOR, and/or Government Project Leads.
Provide Contract Management Support IAW PBSOW Para 3.4
100% Inspection by COR, ACOR, and/or Government Project Leads.
Provide Hardware Acquisition Support IAW PBSOW Para 3.5
100% Inspection by COR, ACOR, and/or Government Project Leads.
Provide Technical Support IAW PBSOW Para 3.6
100% Inspection by COR, ACOR, and/or Government Project Leads.
Provide Systems Engineering Support IAW PBSOW Para 3.7
100% Inspection by COR, ACOR, and/or Government Project Leads.

Contract Requirements in accordance with the Statement of Work

Contract requirements in accordance with the Contract Data Requirements Lists (CDRLS) Form DD 1423

Description
Surveillance

Method/ Measure Date Planned Date Completed

Quality
Schedule
Cost Control
Business

Relations Mgmt

Other

Monthly Progress Report A001
100% Inspection by COR, ACOR, and/or Government Project Leads.
Conference Minutes/Agendas A002
100% Inspection by COR, ACOR, and/or Government Project Leads.
Financial Progress Report A003
100% Inspection by COR, ACOR, and/or Government Project Leads.
Program/Project/Contract Management/Acquisition Status Report A004
100% Inspection by COR, ACOR, and/or Government Project Leads.
System Design/Impact/Feasibility Studies A005
100% Inspection by COR, ACOR, and/or Government Project Leads.
Task Close-Out Report A006
100% Inspection by COR, ACOR, and/or Government Project Leads.
Operations Security (OPSEC) Plan A007
100% Inspection by COR, ACOR, and/or Government Project Leads.
Segregation of Costs and Invoice Requirements Report A008
100% Inspection by COR, ACOR, and/or Government Project Leads.
Information Technology Personnel Security Report for NAVAIR Security A009
100% Inspection by COR, ACOR, and/or Government Project Leads.
Information Technology Personnel Security Report for COR A010
100% Inspection by COR, ACOR, and/or Government Project Leads.
Quality Management / Assurance Plan A011
100% Inspection by COR, ACOR, and/or Government Project Leads.

Enclosure (1) N00421-16-R-0049 Enclosure (1)

Annual Surveillance:

The COR will perform an annual assessment of overall contract performance utilizing the CPARS evaluation rating definitions and the quarterly summary of ratings. This annual assessment will occur on the anniversary date of the single award IDIQ effective date.

Description
Surveillance Method/

Measure

Date Planned
Date Completed
Summary Rating/Results
Quality of Product or Service
Review of Quarterly Ratings.
TBD
Schedule
Review of Quarterly Ratings.
TBD
Cost Control
Review of Quarterly Ratings.
TBD
Business Relations
Review of Quarterly Ratings.
TBD
Management
Review of Quarterly Ratings.
TBD
Other Areas
Review of Quarterly Ratings.
TBD