This is Amendment 0001 to solicitation N0025325Q0006, issued by the Naval Undersea Warfare Center in Keyport, WA on February 21, 2025. The amendment incorporates Wage Determination WA20250109 Mod 1 dated February 7, 2025 and provides answers to pre-proposal inquiries.

The amendment clarifies several technical requirements through Q&A responses: drawings are not currently available but will be provided to the contract awardee; epoxy flooring must extend up the wall rather than using cove base; existing floor coating does not need to be completely removed but must bond according to manufacturer specifications; one qualified individual may serve as Site Superintendent, SSHO and Quality Control Manager; adjacent doors will be closed during work; and the epoxy flooring must have characteristics similar to Sherwin Williams Resuflor 3746 high performance epoxy, including impact/abrasion resistance, durability, chemical resistance to Otto fuel, USDA facility suitability, and antimicrobial agent compatibility. The amendment does not extend the original proposal due date.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is issued to incorporate Wage Determination WA20250109 Mod 1 dated 07 February 2025 and to provide answ ers to Pre-Proposal Inquiries (PPI). The point of contact for this amendment is Michelle Farrales at michelle.a.farrales.civ@us.navy.mil and James Wasson at james.k.w asson.civ@us.navy.mil.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Feb-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0025325Q0006

X 9B. DATED (SEE ITEM 11)

30-Jan-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Feb-2025

CODE

NAVAL UNDERSEA WARFARE CENTER

ATTN: MICHELLE FARRALES

MICHELLE.A.FARRALES.CIV@US.NAVY.MIL

610 DOWELL STREET, BLDG 206

KEYPORT WA 98345

N00253 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N0025325Q0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been added by full text:

PPI AND ANSWERS

1. Could you provide scaled drawings?

Drawings are not currently available. Approval for public release is not expected to complete prior to the proposal due date. Drawings will be available to the contract awardee.

2. Will cove base replacement be required?

There is not a Cove Base. The epoxy will need to extend up the wall.

3. C11_ N0025325Q0006, Page 5, Paragraph I, Statement of Work states, “The project will require the contractor to grind the existing flooring, patch cracks in existing concrete and apply a new epoxy floor coating”. During the site walk on 2/11/2025, it was mentioned that the existing surface did not need to be completely removed, prior to applying the new epoxy floor coating. Will the government confirm that the existing floor coating needs to be completely removed prior to applying the new epoxy floor coating?

Existing floor coating does not need to be completely removed; however, it does need to bond and be applied in conformance to manufacturer specifications.

4. C11_ N0025325Q0006, Page 23, Paragraph 1, General Requirements of the RFP states “A full-time site Superintendent and a full-time Quality Control (QC) representative are required to be on site for the duration of the project. The Superintendent may serve as the Site Safety and Health Officer (SSHO) as long as all requirements in Section 5.4 (Governmental Safety Requirements) are met”. If qualified for all three managerial roles, will the government accept one individual from the Contractors firm to act as the Site Superintendent, SSHO and Quality Control Manager?

This is acceptable.

5. Will the government confirm that the doors adjacent to the work zone will be closed for use by the building occupants during the duration of project?

Confirmed, the doors adjacent to the work area will be closed for use during the project.

N0025325Q0006

6. At the site walk it was noted that the epoxy flooring material was required to be approved for use with Otto Fuel and tested and approved by the Government. Please Provide a list of manufacturers with tested and approved products.

Yes. It shall have characteristics similar to Sherwin Williams Resuflor 3746 high performance epoxy. Salient characteristics are:

• Impact and abrasion resistant

• Durable, easy to clean

• Chemical resistant to OTTO fuel

• Suitable for use in USDA inspected facilities

• Available with an antimicrobial agent (GP8746 series)

• Tint bases can be tinted using Maxitoner @ 50% tint strength

(End of Summary of Changes)