This is a Questions and Answers document providing clarifications to prospective offerors on the NETSAFA International Training Center Support solicitation (N0018927RD001), a 100% small business set-aside CPFF task order under Seaport NxG. The Q&A addresses five substantive issues raised by potential contractors regarding submission procedures, deadlines, late submission policies, proprietary data handling, and size standard applicability.
Regarding submission procedures, an amendment clarified that Step Two questions and quotes should be submitted via email to the designated contracting officers (Mr. Kinkade and Mr. Damanskis), with subcontractor cost breakdowns sent by separate email to Mr. Kinkade. The question deadline was amended to 16 November 2026 at 1600 EST, occurring after viability determinations to allow viable vendors to submit additional questions without a separate question period. The Government will not apply the FAR 15.3 "late is late" rule to submissions. Subcontractors may submit proprietary or cost breakdown information directly to the Government, and if email file size limitations exist, quoters may submit entire quotes through PIEE with timeliness based on system time stamps; email submissions' timeliness is determined by receipt in the Contracting Officer's inbox. Finally, the Government confirmed that NAICS Code 541330 Exception 1 does not apply to this requirement, as the specialized military aviation and weapons-system engineering services identified are not the primary purpose of the contract, making the $25.5 million size standard appropriate.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question # | Question | Response |
| 1 | Section A (Step Two) states that questions and quotes from viable firms are to be submitted "via the Seaport NxG portal," while Section L directs that quotes be submitted by email to Mr. Kinkade and Mr. Damanskis, and that subcontractor cost breakdowns be sent by separate email to Mr. Kinkade. Our understanding is that the legacy SeaPort portal is no longer accepting task order submissions. Please confirm the method the Government will use to receive Step Two questions and quotes, and whether an amendment will conform Sections A and L. | An Amednment to Section A and L has been issued. Please see the attached Solicitation Amendment with red text signifying any changes. |
| 2 | Question deadline. Section A states that Step Two questions are due 1600 EST on 11 November 2026, while Section L requests that questions be received by 1600 EST on 6 November 2026. Please confirm which date governs, and whether a separate question period will be provided to firms determined viable after Step One. | An Amednment to Section A and L has been issued to correct the question deadline to 16 November. This deadline will be post-viability determination allowing viable vendors to submit further questions, there will not be a seperate question period. Please see the attached Solicitation Amendment with red text signifying any changes. |
| 3 | Late submissions. Block 9 of the cover page refers to Section L provisions 52.214-7 or 52.215-1 for late submissions, while the Fair Opportunity section states that the FAR 15.3 "late is late" rule does not apply. Please clarify how the Government will treat submissions received after the stated due times. | The "Late is Late" rule does not apply. |
| 4 | Proprietary subcontractor data. Section L requires subcontractors to provide un-sanitized cost build-ups in Microsoft Excel. If submission is by email, may subcontractors transmit their data directly to the Government, and may offerors and subcontractors use DoD SAFE (or another Government-preferred secure transfer method) for large or proprietary files? Please also confirm how the Government will document time of receipt for files sent by these methods. | Subcontractors may submit any proprietary or cost breakdown information directly to the government. However, it is the prime contractor's responsibility to evaluate and include all costs in their submissions. The Government will not accept submissions through DoD SAFE. If a quoter is unable to submit a quote via email due to file/attachment size limitations, the quoter may submit the entire quote through PIEE. Notice of Solicitation N0018927RD001 has been posted within the PIEE system (11/3). All required elements of a complete quote must be received by the Government by the stated deadline. For quotes/documents submitted via email, timeliness will be based on the time the email is received in the Contracting Officer's inbox. For quotes/documents submitted via PIEE, timeliness will be based on the system time stamp. |
| 5 | Given the specialized military aviation and weapons-system requirements identified in the PWS, did the Government consider applying NAICS 541330, Exception 1, rather than the general Engineering Services size standard? If so, would the Government clarify its rationale for determining that the $25.5 million size standard is appropriate? If Exception 1 was not considered, would the Government reevaluate the applicable size standard and consider amending the solicitation to reflect the $47 million threshold? | Exception 1 to NAICS Code 541330 is not applicable for this contract opportunity. Although similar engineering services are identified, they are not the primary purpose for this requirement. |