This document is a presentation by Orr Partners and the Navy Museum Development Foundation (NMDF) detailing the project plan for developing the new National Museum of the United States Navy (NMUSN) adjacent to the Navy Yard. The project involves a multi-phase approach with three primary focus areas: design, construction, and coordination. For the design phase, NMDF will issue a Request for Qualifications (RFQ) to select a Museum Building Designer, evaluating firms based on museum design experience, collaboration abilities, NAVFAC building requirements, team strength, and conceptual ideas. The selection process will involve creating a shortlist, issuing an RFP, and conducting interviews to choose the final designer.
The construction phase will use a Design-Bid-Build delivery method, with a General Contractor hired during the design phase to provide pre-construction services like cost estimating, constructability consultation, and exhibit design coordination. Comprehensive project coordination will involve multiple stakeholders and systems, including the Naval History and Heritage Command (NHHC), NAVFAC, security, exhibit designers, IT systems, furniture, code/fire alarm, and parking. The project aims to develop a new national museum through a structured, collaborative approach involving private sector expertise and naval organizational coordination.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
June 4, 2025
PROJECT ROLES
Project Roles
Design
Construction
Coordination Under Contract to NMDF as overall Project Manager
Responsible for the design & construction of Museum Building
Navy Museum Development Foundation (NMDF) working with Navy History & Heritage Command (NHHC) for the development of the new National Museum of the United States Navy (NMUSN) adjacent to the Navy Yard.
Responsible for the design & construction of Exhibits
• Design will be procured & executed via a private sector process
• Selected firm will be under contract to NMDF
• Orr will conduct the process on behalf of and in conjunction with
NMDF and in close collaboration with NHHC
Brief Outline of the Selection Process
• A Request for Qualifications (RFQ) will be issued to interested firms
• Firms will be evaluated based on several criteria including but not limited to:
• Experience with museums, military museums & DC entitlement process
• Ability to collaborate with Exhibit Designers under contract to NHHC
• Knowledge of NAVFAC building requirements
• Strength of team
• Conceptual ideas for the new museum
DESIGN
Project Roles
Design
Construction
Coordination
Selection Process (cont.)
• NMDF will create a short list based on results of the RFQ evaluation and move to RFP process
• Short-listed firms will be invited to prepare a proposal that includes
• Proposed fee
• Details of their proposed project team
• Some or all firms that submit a proposal will be invited to interview
• NMDF will select the Museum Building Designer based on interviews and proposals
DESIGN
Project Roles
Design
• Construction will be procured via a private sector process
• Delivery Method will be Design-Bid-Build
• Expect a General Contractor will be hired during the Design Phase to provide Pre-Construction Services including but not limited to:
• Cost Estimating
• Constructability & procurement consultation
• Exhibit design & construction consultation
• Potential for some early release construction packages
• Successful Pre-Con GC will likely be invited to participate in the Bidding Process once Museum Design Documents are complete
CONSTRUCTION
Project Roles
Design
COMPREHENSIVE COORDINATION
Security IT Systems
Furniture
Exhibit Designers
Code/Fire Alarm Parking
Project Roles
Design
File details come from the government source that posted it. Updated .