This document is an amendment to a solicitation for MK 70 Booster Ballast Hardware Kits. The purpose of the amendment is to 1) answer questions received in response to the original solicitation, and 2) extend the solicitation closing date.

The key details are:

  • The solicitation number is N0017424SN0053.
  • The contract is for the fabrication, acceptance, inspection, and delivery of MK 70 Booster Ballast Hardware Kits.
  • The solicitation closing date has been extended from August 8, 2024 to August 15, 2024.
  • The applicable engineering change orders and paint/primer requirements have been provided in response to vendor questions.
  • The contract will be awarded on a firm-fixed price basis to the lowest priced technically acceptable offer.
  • The contracting agency is the Department of the Navy, Naval Sea Systems Command.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to 1) answ er questions received in response to the solicitation issuance and 2) extend the solicitation closing date.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Aug-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0017424R0088

X 9B. DATED (SEE ITEM 11)

02-Jul-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Aug-2024

CODE

NSWC IHD C02

4081 N. JACKSON RD

BLDG 841

INDIAN HEAD MD 20640-5116

N00174 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES_

The purpose of this amendment is to 1) answer questions received in response to the solicitation issuance and 2) extend the solicitation closing date as follows.

1. Questions received in response to the solicitation issuance are answered below:

Question 1: Some of the drawings state that they are affected by ECOs. Please send the engineering change orders listed in N0017424SN0053 Table 2.

Answer 1: The applicable ECOs (7) are attached to this amendment.

Additionally, Section 3.1.1 Engineering Change Orders, Table 2 calls out an ECO for drawing number

1030-2042-001. This drawing does not have an outstanding ECO as drawing 1030-2042-001 Rev A supersedes the ECO mentioned in the table. Table 2 was updated to remove the ECO below. Please see the attached revised SOW.

ECN-00000006713 1030-2042-001 Bracket Ballast Adapter

Question 2: Some of the drawings have a paint requirement that refers to “manufacturer’s instructions”. I cannot locate the actual paint requirement in the SOW. Can you advise to the paint callout of: paint 9492 and prime 9186? The following drawings have that call out:

1030-5043-001

1030-2044-001

1030-2046-001

1030-2048-001

1030-5052-001

1030-2052-001

1030-2054-001

Answer 2: 9186 and 9492 are Rust-oleum P/N’s (cage code provided on the DWG’s is 08882). Instructions are attached to this amendment.

Question 3: Please send drawing 130-5802 Rev. A to support applying cork to component C23816 per

SOW 3.1.3.

Answer 3: The SOW, Section 3.1.3, has been updated as follows:

1. Replaced Dwg 130-5802 Rev. A with Dwg 1030-5802B to reflect the updated drawing number. Please see the revised SOW attached.

The drawing (1030-5802B) and supporting document (Bond Cork To Metal PDF) are attached to this amendment.

2. The solicitation closing date is extended

FROM:

8 August 2024 3:00 p.m. EST

TO:

15 August 2024 3:00 p.m. EST

3. All other terms remain unchanged.

4. Direct questions to Diane Hicks at diane.d.hicks.civ@us.navy.mil.

mailto:diane.d.hicks.civ@us.navy.mil

File details come from the government source that posted it. Updated .