This document contains a vendor's exceptions and responses to technical requirements for a Request for Proposal (RFP) related to Shielded Mild Detonating Cords (SMDC). The vendor is requesting exceptions to several requirements in MIL-DTL-32154A and associated drawings, including first article testing, booster cup load, and test setup details. The vendor proposes alternative testing methods and equipment, citing continuous production history and safety concerns. The related federal contract opportunity is a solicitation (N0010423RK067) from the Department of the Navy Naval Supply Systems Command for SMDCs, with a limited drawing package available. The procurement is restricted to two vendors, Pacific Scientific Energetic Materials Company and Rockwell Collins, and a safety survey will be required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Legend | |
| Requirements to take exception to FAI sample run | |
| Requirements to take exception to Electrical Blasting Cap and SMDC Test Tips for safer HE TLX Test Tip and Purcussion Primer initiation | |
| Requirements to take exception to for customer specified test setup. Use Vendor test setup materials compliant to intent of customer setup | |
| Requirements to take exception to fitting nut torque over 90 in-lbs. | |
| No Color | Individual requirements to take exception to. |
| Requirement Details | Requirement Validation | Compliance | |||||||||
| Reqt. ID | Source / | ||||||||||
| Rationale(Rev) | Section / | ||||||||||
| Paragraph | Text Type | Text | Validation | ||||||||
| Status | Validation Notes | Reqt. Owner | Vendor Acceptance | ||||||||
| of Reqt. | Compliance | ||||||||||
| Status | Compliance Comments | IH Response | |||||||||
| 29 | MIL-DTL-32154A | 3.1 | Requirement | Unless otherwise specified by the contract or purchase order, an acceptable first article sample of 18 SMDC shall(0001) be required when more than 12 months have elapsed since the production of the latest accepted production lot. | N/A | No | N/A | Take Exception to requirement. Vendor has never been out of production of SMDC, continuous production of AH-64, 51134-XXX and various foreign military SMDCs. | Not Approved | ||
| 30 | MIL-DTL-32154A | 3.1 | Requirement | The sample shall(0002) be tested in accordance with 4.2. | N/A | No | N/A | Take Exception to requirement. Vendor has never been out of production of SMDC, continuous production of AH-64, 51134-XXX and various foreign military SMDCs. | Not Approved | ||
| 58 | MIL-DTL-32154A | 3.6 | Requirement | The booster shall(0023) contain 1+/- .1 grain of HNS pressed to 32,000 +/- 1,000 psi. | Invalid Requirement | Booster cup load of 1 ±.1 grain does not met Vendor established (12/1969 )Booster cup load. [1 ±.1 grain is 64.8± 6.5 mg, Vendor booster cup is 67±7 mg]. Appears in spec rounding to one digit in the requirement and possible rounding in actual grain to mg factor. | No | Not Compliant | Take exception, use Vendor booster cup load as is. Vendor booster cup load is standard load size for all SMDC, FCDC, ECRL and TLX. Changing load originally qualified in 1969 could effect .285-inch dimension from face of booster cup to ferrule flang on Vendor top assembly drawing and Navy drawing 841AS425 (redesign and qualification). | Approved | |
| 82 | MIL-DTL-32154A | 4.2 | Requirement | The first article sample selected in accordance with 3.1 shall(0036) be sequentially subjected to the following tests of MIL-D-21625 in the order listed: Temperature and Humidity Cycling (28 Days), Salt Spray, Vibration and Shock. | N/A | No | N/A | Take Exception to requirement. Vendor has never been out of production of SMDC, continuous production of AH-64, 51134-XXX and various foreign military SMDCs. | Not Approved | ||
| 83 | MIL-DTL-32154A | 4.2 | Requirement | After the completion of the sequential environmental treatments, the sample shall(0037) be inspected and x-rayed for damage. | N/A | No | N/A | Take Exception to requirement. Vendor has never been out of production of SMDC, continuous production of AH-64, 51134-XXX and various foreign military SMDCs. | Not Approved | ||
| 84 | MIL-DTL-32154A | 4.2 | Requirement | Any damages inflicted by the sequential environmental treatments which would adversely affect the performance of the item in service application shall(0038) be cause for the rejection of the first article sample. | N/A | No | N/A | Take Exception to requirement. Vendor has never been out of production of SMDC, continuous production of AH-64, 51134-XXX and various foreign military SMDCs. | Not Approved | ||
| 85 | MIL-DTL-32154A | 4.2 | Requirement | The sample shall(0039) be divided into two equal groups and fired in accordance with 4.7.2.1 and 4.7.2.2. | N/A | No | N/A | Take Exception to requirement. Vendor has never been out of production of SMDC, continuous production of AH-64, 51134-XXX and various foreign military SMDCs. | Not Approved | ||
| 86 | MIL-DTL-32154A | 4.2 | Requirement | The sample shall(0040) be acceptable with respect to functional testing if each firing meets the requirements of 3.10. | N/A | No | N/A | Take Exception to requirement. Vendor has never been out of production of SMDC, continuous production of AH-64, 51134-XXX and various foreign military SMDCs. | Not Approved | ||
| 140 | MIL-DTL-32154A | 4.4.2 | Requirement | The 9 inch segments of the detonating cord sample shall(0068) be temperature conditioned for not less than 8 hours nor greater than 24 hours, one segment each at -65° ± 5°F and +350° ± 5°F. | Proposed | Testing per ATP is only 4 hours | No | Not Compliant | Take Exception to requirement. 8 hours minimum is an old requirement. Current processes and requirements is 4 hours mininimum | Approved | |
| 141 | MIL-DTL-32154A | 4.4.2 | Requirement | Following temperature conditioning, each segment shall(0069) be fired by a commercial no. 6 electrical blasting cap and the detonation velocity measured to determine conformance to the requirements of 3.4.1. | Proposed | No. 6 EBC not used by Vendor, Vendor uses No. 8 | No | Not Compliant | Take Exception to requirement. New test setup does not use EBCs | Approved with conditions. RFV will be required. | |
| 163 | MIL-DTL-32154A | 4.7.2.1 | Requirement | The test specimen shall(0086) be fired in the manner depicted on NAVAIR drawing No. 841AS800. | Proposed | Refer to exceptions to Dwgs 841AS800-841AS806 below | No | Partially Compliant | Modified LAT setup, Refer to exceptions to Dwgs 841AS800-841AS806 below | Vendor must provide a copy of their LAT test set up and ATP. | |
| 166 | MIL-DTL-32154A | 4.7.2.2 | Requirement | The test specimen shall(0089) be fired in the manner depicted on NAVAIR drawing 841AS800. | Proposed | Refer to exceptions to Dwgs 841AS800-841AS806 below | No | Partially Compliant | Modified LAT setup, Refer to exceptions to Dwgs 841AS800-841AS806 below | Vendor must provide a copy of their LAT test set up and ATP. | |
| 199 | 841AS425AJ | Note 3 | Requirement | THE ALUMINUM FOIL-TYPE IDENTIFICATION PLATE SHALL BE IN ACCORDANCE WITH MIL-DTL-19834, TYPE I. | Proposed | Vendor nameplate does not comply to MIL-DTL-19834. | No | Not Compliant | Take exception to the MIL-DTL-19834 specification. Vendor nameplate is qualified for F-18 SMDC. | Approved | |
| 379 | 841AS450J | Entire Dwg | Requirement | Specification for Shielded Mild Detonating Cord Test Tip | Invalid Requirement | No | N/A | Take Exception to requirement. For safety Blasting caps no longer used, SMDC test tips replaced by HE TLX Test Tips with same 1 grain output as SMDC test tip. HE TLX Test Tip initiation is performed using a percussion primer. | Approved with conditions. RFV will be required. | ||
| 380 | 841AS450J | Entire Dwg | Requirement | Specification for Shielded Mild Detonating Cord Test Tip | Invalid Requirement | No | N/A | Take Exception to requirement. For safety Blasting caps no longer used, SMDC test tips replaced by HE TLX Test Tips with same 1 grain output as SMDC test tip. HE TLX Test Tip initiation is performed using a percussion primer. | Approved with conditions. RFV will be required. | ||
| 389 | 841AS800A | Note 6 | Requirement | FITTING NUT THREAD SIZE TORQUE(INCH POUNDS) | |||||||
| .688 .4375-20 UNF 80-100 | Invalid Requirement | Over torque for aluminum fitting nuts | No | N/A | Take Exception to requirement. Over torque for aluminum fitting nuts. Max torque is 90 in-lbs. MIL-DTL-32154, Para. 3.9.1 only requires 90 in-lbs test. | Approved. Proposed torque range is within the specification | |||||
| 390 | 841AS800A | Note 6 | Requirement | FITTING NUT THREAD SIZE TORQUE(INCH POUNDS) | |||||||
| .750 .5000-20 UNF 100-120 | Invalid Requirement | Over torque for aluminum fitting nuts | No | N/A | Take Exception to requirement. Over torque for aluminum fitting nuts. Max torque is 90 in-lbs. MIL-DTL-32154, Para. 3.9.1 only requires 90 in-lbs test | Not Approved. Proposed torque range is not IAW spec requirement | |||||
| 392 | 841AS800A | Note 8 | Requirement | FIRE TEST ASSEMBLY BY TAPING A COMMERCIAL NO.6 ELECTRIC BLASTING CAP TO THE APPLICABLE SMDC TEST TIP INSTALLED IN TIE TEE CONNECTOR AND APPLY A FIRING CURRENT OF 5.00±.25 AMPS TO THE BLASTING CAP LEAD WIRES FROM A24-28 VDC SOURCE. | Invalid Requirement | No | N/A | For safety Blasting caps no longer used, SMDC test tips replaced by HE TLX Test Tips with same 1 grain output as SMDC test tip. HE TLX Test Tip initiation is performed using a percussion primer. | Approved with conditions. RFV will be required. | ||
| 393 | 841AS800A | Note 8 | Requirement | THE OUTPUT END OF THE BLASTING CAP SHALL BE IN INTIMATE CONTACT AND LONGITUDINALLY ALIGNED WITH THE EXPLOSIVE CORE OF THE DETONATING CORD PROTRUDING FROM THE SMDC TEST TIP. | Invalid Requirement | No | N/A | For safety Blasting caps no longer used, SMDC test tips replaced by HE TLX Test Tips with same 1 grain output as SMDC test tip. HE TLX Test Tip initiation is performed using a percussion primer. | Approved with conditions. RFV will be required. | ||
| 394 | 841AS800A | Note 8 | Requirement | ALTERNATE THE DONOR SMDC TEST TIP BETWEEN FIRINGS SUCH THAT AN APPROXIMATELY EQUAL NUMBER OF FIRINGS IS PERFORMED AT EACH CONDITIONING TEMPERATURE, BY DETONATING THE SMDC TEST TIP IN-LINE WITH THE SMDC TEST SPECIMEN AND BY DETONATING THE SMDC TEST TIP AT 90' WITH THE SMDC TEST SPECIMEN. | Invalid Requirement | No | N/A | For safety Blasting caps no longer used, SMDC test tips replaced by HE TLX Test Tips with same 1 grain output as SMDC test tip. HE TLX Test Tip initiation is performed using a percussion primer. | Approved with conditions. RFV will be required. | ||
| 397 | 841AS800A | Note 10 | Requirement | STANDARD SMDC LOT ACCEPTANCE TEST SPECIMEN SHALL BE IN ACCORDANCE WITH NAVAIR DWG 841AS425, SHEET 9. | Invalid Requirement | No | N/A | Sheet 9 on Dwg 841AS425AJ is a list of where used for the customer SMDC. Assumption is it should be Sheet 3 of 841AS425AJ. Vendor is compliant to Sheet 3 of 841AS425J. | Concur | ||
| 398 | 841AS801A | Requirement | SENSITIVITY TEST FITTING DRAWING | Invalid Requirement | No | N/A | Vendor will use Sensitivity Test Fittng Drawing # 80017. Sensitivity Test Fittng 80017 qualified to Boeing 74B80225 SMDCs equivalent to the Navy 841ASA425 SMDCs. Vendor Sensitivity Test Fittng complies with Navy Drawing 841AS801A | Approved. Drawing must be provided to verify concurrence. | |||
| 399 | 841AS802- | Requirement | CONNECTOR TEE DRAWING | Invalid Requirement | No | N/A | Vendor will use Standard SMDC configuration Connector Tee, PN 21738-2. Tee PN 21738-2 compliant to all dimesions shown on 841AS802, except additional design rounds bottom face to a full radius and some corners to .25 radius. | Vendor must provide a copy of their DWG PN 21738-2 | |||
| 401 | 841AS804- | Requirement | SMDC DENT BLOCK HOLDER DRAWING | Invalid Requirement | No | N/A | Customer design is an old design not used by Vendor. Vendor will use Dent Block Holder Drawing # 80397. Dent Block Holder 80397 qualified to Boeing 74B80225 SMDCs equivalent to the Navy 841ASA425 SMDCs. Vendor holder does not require a threaded port for the SMDC. | Vendor must provide a copy of their DWG PN 80397. How to secure the booster tip against to the dent block? | |||
| 402 | 841AS805- | Requirement | SENSITIVITY FITTING HOLDER DRAWING | Invalid Requirement | No | N/A | Customer design does not hold sensitivity fitting in and can allow sensitivity fitting halves to move apart changing internal volume. Vendor will use Sensitivity Holder, Vendor TN 12800-1, which is desiged to capture and keep sensitivity fittings from coming apart. | Vendor will need to provide more information about this. |