About this file

N00033-12-R-2002 Amendment 0002

View the file

Other files

File Type Posted
Attachment_C_GFE_List.pdf PDF
Attachment_L-1_Basic_Pricing_Data.xls XLS spreadsheet
N00033-12-R-2002_A0001.doc DOC document
Attachment_L-2_Crew_Complement_Form.xls XLS spreadsheet
Attachment_L-5_Insurance_Affirmation.doc DOC document
Attachment_E_Mission_Essential_Contractor_Services.pdf PDF
Attachment_C_GFE_List.pdf PDF
Attachment_L-1_Basic_Pricing_Data.xls XLS spreadsheet
Attachment_L-2_Crew_Complement_Form.xls XLS spreadsheet
Attachment_D-1_WD_2010-0147_Rev1.pdf PDF
N00033-12-R-2002.doc DOC document
Attachment_D-2_WD_2010-0148_Rev1.pdf PDF
Attachment_B_EDI_TP_Agreement.docx DOCX document
Attachment_L-3_Past_Performance_Datasheet.doc DOC document
Attachment_A_DD254.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

A0002 A. Sections C and L of the solicitation are amended to reflect changes to the vessel draft requirements and the dimensions of the small boats to be carried aboard. Attachment C is replaced to reflect the change to the dimensions of the small boats to be carried aboard.

1. The maximum navigational draft of the vessel is increased to 25ft from 15ft.

2. The length of the small boats to be carried is decreased to 12.5m from 15m.

B. The response to Question 2 provided in Amendment 0001 is hereby rescinded and modified as shown below:

Q2.

The vessel specifications stipulated in Section C-2.4 requires a maximum draft of 15 ft. Will the Government accept a vessel that has a deeper laden draft but offers a significantly greater speed?

A2.

The maximum vessel draft is 25 ft, and Section C-2.4 is amended to reflect the higher maximum draft.

SUMMARY OF CHANGES

Additions and insertions to the sections shown below are in bold. Deletions are shown with a strikethrough.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

PERFORMANCE WORK STATEMENT

C-2.0

VESSEL REQUIREMENTS

C-2.4 Maximum Draft: 15ft25ft (navigational draft)

C-2.9 Deck Space Requirements. The Contractor shall provide a minimum of 3,600 square feet of open deck to accommodate the following GFE:

C-2.9.2 Equipment Stowage Space. The Government will provide eight (8) 20' x 8.7' x 8' (LWH) containers, four (4) 15m12.5m x 3m craft, and one (1) standard 108" x 88" (LXW) ISU box with a minimum of 5' wide walkways between container doors and around the craft. Access to all containers, box, and craft shall be from the deck level or internal storage area to accommodate eight (8) (20’ x 8.7’ x 8’) (LWH) containers. The Contractor shall provide power for the ISU and five (5) containers in the following circuit sizes and quantities: 110v, 60Hz, 10A and three (3) 110v, 60Hz, 20A, per container. The Contractor shall provide power for the remaining three (3) containers in the following circuit sizes and quantities: 60A service (220/110v, 3-phase, 60Hz).

C-2.13 Small Boat Launch, Recovery and Storage System. The Contractor shall provide redundant launch and recovery capabilities for four (4) 15m12.5m x 3m craft with a minimum of 2m draft. The launch and recovery systems shall be capable of lifting/supporting 30,000 pounds (includes boat, personnel and equipment) per small boat. The Contractor shall also provide:

- Two (2) 110v 30 A outlets near the launch and recovery system. Each outlet should be sealed to prevent salt water intrusion.

- A freshwater supply/hose near the launch and recovery system.

- The ability to launch or recover up to four (4) small boats in ten (10) minutes or less per boat.

- Small boat fueling capability at each stowage position.

- Capacity for 8,000 gallons MOGAS

- Storage for one (1) ISU 90 Mechanic Pallet 8’ x 9’ x 8’ (LWH) Small boat stowage locations require access to either the ship's crane or a smaller crane capable of 2,000 lb lift capacity or a 10' (w) x 18' (h) rolling overhead chain hoist 2,000 LB capacity (ability to pull engines inside).

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been modified:

SECTION L

L-7 GENERAL PROPOSAL REQUIREMENTS

L-7.1.2 Volume I should contain the following, with no pricing information:

Title Page, Cover Letter, Table of Contents The title page shall meet the requirements of FAR 52.215-1(c)(2). If the offeror wishes to restrict disclosure of information in its proposal, it may include the legend permitted by FAR 52.215-1(e). Although a cover letter is not required, offerors may submit one, and it should be placed after the title page. A table of contents shall be provided after the title page (and cover letter, if applicable), listing the chapters, sections, subsections, page numbers, etc.

Completed Specialtime Boxes Offerors shall provide Specialtime Boxes identifying the vessel and providing the Offeror’s DUNS, CAGE, and TIN. Offerors shall complete and provide Boxes 2, 3, 7 – 12, and 23 – 64 from Part B of this solicitation. Offerors shall include in their submission a fuel grade from the list of fuel grades in Section M-2.3 of the solicitation. Offerors shall include two dates in Box 24; (1) the earliest date on which the proposed vessel could commence performance as outlined in F-1.1, and (2) the estimated date on which the vessel will be ready for delivery as outlined in F-1.2.

Technical Proposal

Offerors shall fully describe the vessel proposed for this contract. Offerors must address how the vessel meets the minimum vessel requirements in the solicitation and attachments. Offerors shall submit detailed plan view ship drawings.

The technical proposal must demonstrate compliance with the following portions of Section C:

Berthing C1.1, C2.12
The vessel will have the capacity to berth, support, and feed twenty-nine (29) Government personnel with the ability to surge to forty-four (44) Government personnel for a maximum of 90 days.
Underway Replenishment C1.1, C2.1.2
The vessel shall have the capability to conduct Underway Replenishment (UNREP) with USS/USNS logistical ships.
Endurance C2.1
The support vessel must be capable of supporting at-sea operations for 90 days without resupply.
Minimum Range C2.1.1
8,000 NM
Seakeeping (including small boats) C2.2
The support ship shall be able to operate up to and including Sea State 5. Vessel must support small boat operations (fueling, launch and recovery) up to and including Sea State 3.
Speed C.2.3
10 kts
Draft C2.4
15ft25ft maximum (Navigational draft)
Sponsor Conference room C2.5
The Contractor shall furnish a dedicated and lockable planning conference space for fifteen (15) personnel with desk space to accommodate fifteen (15) GFE laptop computers with four (4) GFE computer screens and two (2) GFE printers. The space shall include tables, chairs, and multiple power outlets/strips to support GFE computer and data display equipment, . The space shall also include as well as one (1) 220v source for a GFE shredder.
Workout Room C2.5.2
The Contractor shall provide a 500 sq ft workout room. The space shall have an overhead height of greater than or equal to 9 feet for at least 100 sq ft.
Communications Room Requirements C2.5.3
The Contractor shall furnish a dedicated and lockable communications room (built to ICD 705 standards). The room shall with accommodate the following equipment:

- Four (4) server racks (GFE)

- Two (2) desks (CFE)

The room shall have the following characteristics:

- Two (2) CAT-VI patch panels (CFE)

- (2) desks (CFE)

- Four (4) 30A circuits (CFE)

- Four (4) 20A circuits (CFE)

Medical space C2.5.4
A dedicated mdeical space with room for one bed and one exam table.
Force Protection Space C.2.6.1
The Contractor shall provide surface areas to post a minimum of 6 weapons mounts (to support 360 degree overlapping fields of fire) in support of the requirement force protection posture.
Alarm/Intrusion Detection System C2.6.4
The Contractor shall provide visual and audible alarm protection to the Conference Room, Communications Center and Ready Service Lockers (RSLs). Installation shall consist of sensors connected at each door of the operations and communication Centers and attached spaces. The Contractor shall provide a remote alarm monitoring station that shall be located within the communications Center with a back-up system for the RSLs/ordnance magazines located on bridge.
Antennas C.2.8
The Contractor shall provide space and power for mounting GFE provided antennas as close as possible to unobstructed line of sight for 360 degrees of azimuth and 90 degrees of elevation.
Deck space requirements C2.9
The Contractor shall provide a minimum of 3600 square feet of open deck to accommodate the GFE listed in paragraphs 2.9.1, 2.9.2 and 2.9.3.
Water supply C2.10
The Contractor shall provide a minimum of 2,760 gallons of potable water production to support the 44 personnel plus crew living onboard (minimum 40 GPD per person) and for daily fresh water wash down of embarked equipment, gear and machinery (1,000 GPD). Water must be able to reach all parts of the mission deck for fresh water wash down.
Low Pressure (LP) Air Lines C2.11
The Contractor shall provide two LP air lines from the ship service air system with a retractable reel system with standard air nozzles and 100 ft hoses.
Small boat launch, recovery and storage system C2.13
The Contractor shall provide redundant launch and recovery capabilities for four (4) 15m12.5m x 3m craft with a minimum of 2m draft. The launch and recovery systems shall be capable of lifting/supporting 30,000 pounds (includes boat, personnel and equipment) per small boat. The Contractor shall also provide:

- Two (2) 110v 30 A outlets near the launch and recovery system. Each outlet should be sealed to prevent salt water intrusion.

- A freshwater supply/hose near the launch and recovery system.

- The ability to launch or recover up to four (4) small boats in ten (10) minutes or less per boat.

- Small boat fueling capability at each stowage position.

- Capacity for 8,000 gallons MOGAS

- Storage for one (1) ISU 90 Mechanic Pallet 8’ x 9’ x 8’ (LWH)

- Small boat stowage locations require access to either the ship's crane or a smaller crane capable of 2,000 lb lift capacity or a 10' (w) x 18' (h) rolling overhead chain hoist 2,000 LB capacity (ability to pull engines inside).

Small Boat Fueling C2.13.1
The Contractor shall provide an internal fueling/filtering system for MOGAS (LL-100) with an 8,000-gallon capacity, or install two (2) GFE Bryant Fuel system (USCG approved) containers. Each container is 20’ x 8’ x 8’ (LWH) with a 4,000 gallon capacity. If the Contractor uses the GFE Bryant Fuel system containers, it shall provide a shelter for each container and hardwire each container into the vessel electrical distribution system.
Diesel Fuel capacity C2.13.2
The Contractor shall provide three (3) No. 2 diesel fueling stations on the main deck adjacent to the boat storage location to support small boat fueling. The Contractor must provide the required hoses and nozzles.
Rotary wing support C2.14
The Contractor shall provide a clear deck area of 30 feet x 30 feet and clear, unobstructed vertical airspace to be used as a Flight Deck. The Flight Deck must be reachable by a crane capable of repositioning a 500 lb aircraft from its stowed position as well as related equipment and materials
Rotary Wing Fueling C2.14.1
The Contractor shall provide an internal fueling/filtering system for aviation fuel (JP5) (capable of fueling aircraft at flight deck location) with a 2,000-gallon capacity, or install one GFE Bryant Fuel system (USCG approved) container. The container shall be 10’ x 8’ x 8’ (LWH) with a 2,000 gallon capacity.
Firefighting Foam C2.15
The Contractor shall provide AFFF in the vicinity of the fueling stations.
Cranes C2.16
The Contractor shall provide a minimum of one ABS classed crane capable of lifting 30,000 pounds at an adequate distance to load full expanse of open deck area from pier or underway in a minimum of Sea State 3.
Bryant Fuel System Ballistic Protection C2.17
If required, the Contractor shall install ballistic protection to the exterior of all three GFE provided Bryant Fuel Systems. The sides of each fuel container shall be protected with .375 inch thickness steel armor, and the top of the container shall be protected with .25 inch thickness steel armor. All steel armor shall meet the requirements of the MIL-DTL-46100E for class-I-High-Hardness Steel Armor plate.