About this file

N00033-12-R-2002 Amendment 0001

View the file

Other files

File Type Posted
N00033-12-R-2002_A0002.doc DOC document
Attachment_C_GFE_List.pdf PDF
Attachment_L-1_Basic_Pricing_Data.xls XLS spreadsheet
Attachment_L-2_Crew_Complement_Form.xls XLS spreadsheet
Attachment_L-5_Insurance_Affirmation.doc DOC document
Attachment_E_Mission_Essential_Contractor_Services.pdf PDF
Attachment_C_GFE_List.pdf PDF
Attachment_L-1_Basic_Pricing_Data.xls XLS spreadsheet
Attachment_L-2_Crew_Complement_Form.xls XLS spreadsheet
Attachment_D-1_WD_2010-0147_Rev1.pdf PDF
N00033-12-R-2002.doc DOC document
Attachment_D-2_WD_2010-0148_Rev1.pdf PDF
Attachment_B_EDI_TP_Agreement.docx DOCX document
Attachment_L-3_Past_Performance_Datasheet.doc DOC document
Attachment_A_DD254.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

A0001 A. Solicitation Attachments L-1 and L-2 are hereby replaced to correct the following issues:

1. Attachment L-1:

The document header is changed to reflect “Attachment L-1,” rather than “Attachment B.” Lines 1 and 2 each pricing sheet are corrected to refer to “Attachment L-2” rather than “Attachment C.”

2. Attachment L-2:

An additional sheet is added for Option Period One.

B. The following questions have been submitted. Answers appear below each question.

Q1.

Please advise if there is an incumbent vessel for this requirement and if so what her current daily charter hire rate is.

A1.

The incumbent vessel’s current daily rate is $20,000.

Q2.

The vessel specifications stipulated in Section C-2.4 requires a maximum draft of 15 ft, will the Government accept a vessel that has a deeper laden draft but offers a significantly greater speed?

A2.

No. The maximum draft of 15 ft is a firm requirement.

Q3.

The vessel specifications stipulated in Section C-2.1 requires the capability for Underway replenishment "CONREP" however doesn't stipulate to which NAVSEA standard. Please advise/confirm.

A3.

All Underway Replenishments (UNREP) will be in accordance with NTTP 4-01.4 Publication, NAVY TACTICS, TECHNIQUES, AND PROCEDURES UNDERWAY REPLENISHMENT. The publication is available upon request.

Q4.

If the laydays stipulated in Box 5, 21 May 2012 to 29 June 2012, does not offer sufficient time to convert a vessel to meet the specific contract needs, will the Government consider later delivery dates?

A4.

Mission constraints prevent the Government from considering a later delivery date under this requirement.

Q5.

Is a stern elevator capable of lifting up to 60,000 lbs an acceptable way to meet the requirement in C-2.13?

A5.

If a stern elevator can meet the requirements of Section C-2.13, either alone or as part of a larger system, then the Government will consider it acceptable.

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 12-Mar-2012 02:00 PM to 13-Mar-2012 02:00 PM.

(End of Summary of Changes)