This is a Draft Statement of Work for the dismantlement and disposal of the EX-LONG BEACH (CGN 9), a decommissioned nuclear-powered guided-missile cruiser currently located at Puget Sound Naval Shipyard and Intermediate Maintenance Facility in Bremerton, Washington.

The contract consists of four contract line items (CLINs): CLIN 0001 requires preparation and transport of the vessel via heavy lift vessel or submersible barge to the dismantlement site on a firm fixed price (FFP) basis; CLIN 0002 requires complete dismantlement and disposal of the vessel on an FFP basis; CLIN 0003 specifies data deliverables per the Contract Data Requirements List at no separate charge; and CLIN 0004 provides an incentive fee for radiological regulatory compliance, with the government to define the price. The contractor must transport two defueled reactor vessels to a commercial low-level radioactive waste disposal site and complete all dismantlement at a U.S. facility within the continental United States. Key requirements include preparation of a Decommissioning Work Plan submitted to the Nuclear Regulatory Commission (NRC) for approval, demonstration of capability to manage low-level radioactive waste and hazardous materials at licensed commercial facilities, establishment of physical and information security controls for propulsion plant spaces and unclassified naval nuclear propulsion information, and compliance with NRC regulations through an interagency framework agreement. The contractor must provide full-time on-site key personnel including a Project Manager, Environmental/Safety & Health Manager, Radiological Controls Manager, Production Superintendent, and Facility/Information Security Officer. Additional obligations include monthly progress reports, site release surveys, final radiological condition certification for unrestricted use, payment of the incentive fee upon completion contingent on avoidance of NRC-identified violations, and cooperation with Navy on-site representatives for project oversight throughout the period of performance.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N0002427R4164

DRAFT

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

CLIN

Number

Transport EX-LONG BEACH to Dismantlement Site

FFP

Prepare and transport EX-LONG BEACH (CGN 9) to the dismantlement site via heavy lift vessel, submersible barge or other conveyance.

FOB: Destination

PSC CD: 1905

NET AMT

Dismantle and Dispose

FFP

Dismantle and Dispose of EX-LONG BEACH (CGN 9)

CLIN

Data Items

FFP

Prepare and deliver data in accordance with Exhibit A, Contract Data Requirements List, DD Form 1423. NOT SEPARATELY PRICED.

1 Each

Incentive Fee

FFP

Incentive Fee for Radiological Regulatory Compliance Incentives. (See Note A).

GOVERNMENT TO DEFINE PRICE.

NOTE A: INCENTIVE FEE (APPLICABLE TO CLIN 0004)

1. To provide an incentive for the Contractor’s successful completion of the dismantlement/disposal of the EX-LONG BEACH. The predetermined incentive will be reduced if monetary penalties, such as fines if this were NRC-regulated work, are assessed under the Notional Framework during the contract period of performance. The payment of the incentive fee shall be subject to the following evaluation criteria:

a. To be eligible for the full payment of the incentive fee, the Contractor shall complete dismantlement and disposal of the EX-LONG BEACH without incurring NRC-identified infractions carrying a recommendation of financial penalty.

b. Should the NRC assess Contractor violation(s) during the period of performance carrying a recommendation of a financial penalty, the incentive fee will be reduced as recommended by the NRC. For example, if the NRC recommends a $50,000 financial penalty for an infraction, the incentive fee shall be reduced by $50,000. Each additional incidence of a violation carrying a recommendation of a financial penalty will result in further incentive fee reduction by the amount recommended by the NRC.

2. The Contractor shall be paid the incentive fee amount earned pursuant to this clause upon completion of the dismantlement and disposal of the EX-LONG BEACH and submittal of proper invoices to the cognizant Payment Office.

3. The amount of the incentive fee to be paid to the Contractor is a unilateral decision made solely at the discretion of the Government.

Section C - Descriptions and Specifications

STATEMENT OF WORK

1. BACKGROUND / PURPOSE

EX-LONG BEACH (CGN 9) was decommissioned in 1995 following over 30 years of service and later transferred to Puget Sound Naval Shipyard and Intermediate Maintenance Facility (PSNS&IMF) in Bremerton, Washington for disposition. From 2012 – 2015, the ship was prepared and modified for long term waterborne storage having completed partial dismantlement that removed both her bow and stern sections. EX-LONG BEACH has two reactor plants housed in two propulsion plants inside the ship. As part of the decommissioning process, the nuclear fuel was removed from the two reactor plants and management of nuclear fuel is not included in the Contract Scope of Work. EX-LONG BEACH is now obsolete with no further use planned. Vessel remains pier-side at PSNS&IMF in Bremerton, Washington. The Navy requires preparation of EX-LONG BEACH for transport, transportation from PSNS&IMF in Bremerton, Washington to the disposal site (Item 0001), and complete dismantlement and disposal (Item 0002). The Navy has established a process with the NRC for technical and contractual implementation of NRC regulations that will govern the disposal of EX-LONG BEACH.

2. GENERAL REQUIREMENTS

The Contractor shall provide all personnel, equipment, tools, vehicles, materials, facilities, supervision, and other industrial equipment and services necessary to meet the requirements of this Contract and perform the scope of work described in a manner which is safe for workers and the environment, and complies with all applicable Federal, State, and local laws and regulations.

The Contractor shall provide evidence of continued availability of such facilities for the duration of the Contract period of performance by ownership, existing lease, or letter from the facility owners indicating a statement of intent to utilize such facilities for scrapping operations, as well as evidence that site specific permits are currently in effect or can be obtained prior to the start of subject Contract.

The Contractor shall comply with NRC radiological regulations and decommissioning plan requirements similar to oversight provided to an NRC licensee completing the decommissioning of a commercial nuclear power plant or materials site.

The Contractor shall employ qualified personnel who are capable of performing the requirements of the contract, including subcontractors and key personnel. Contractor personnel, including subcontractor personnel and consultants, shall be sufficient to accomplish the scope of work. In addition, the Contractor shall employ and maintain the appropriate personnel, organizational and administrative controls necessary to ensure that performance meets or exceeds all contract specification requirements hereunder.

2.1. The Contractor shall prepare a Decommissioning Work Plan (DWP) for EX-LONG BEACH dismantlement and disposal. The DWP shall be submitted to the Nuclear Regulatory Commission (NRC) to obtain their recommendation that NAVSEA provide the Contractor approval to proceed with completion of the Dismantlement and Disposal (D&D) Contract requirements.

2.2. The Contractor shall obtain and maintain valid permits and/or licenses required to execute the Contract scope of work, with the exception of the radiological work performed in the ship or at the project site, which shall be performed under the Regulatory Framework the NRC and Navy have established via Interagency Agreement (Attachment J-4). Permits necessary for performing the scope of work could include, but are not limited to permits for generating, and shipping for disposal of, polychlorinated biphenyls (PCB) waste, asbestos, and other hazardous materials at the dismantlement site. The Government will not be a co-signee on any permits or licenses obtained by the Contractor.

2.3. The Contractor shall prepare, load, and transport EX-LONG BEACH from the Puget Sound to the dismantlement site. Transportation over public waterways outside the Puget Sound area shall be via heavy-lift vessel or transport barge.

2.4. The Contractor shall transport two (2) defueled reactor vessels (and internal structures) to a commercial low-level radioactive waste disposal site capable of accepting the waste up to Class C as needed.

• The Contractor may procure suitable shipping containers meeting NRC requirements for transporting the two (2) defueled reactor vessels and the internal structures.

• The Contractor may elect to transport the reactor vessels via alternate methods meeting NRC and

DOT requirements. Further, the Government calculates that the unshielded reactor vessels will have radiation levels of less than 1 rem/hr at 3m (49 CFR 173.427).

• The Contractor may also alternatively segment the reactor vessels and internal structure prior to packaging into smaller suitable containers meeting applicable NRC/DOT requirements.

2.5. The Contractor shall complete the dismantling of the EX-LONG BEACH at a facility within the United States of America. The Contractor shall remove and properly dispose of radiological and/or hazardous materials/wastes in accordance with applicable Federal, State, and local laws and regulations.

Radiological and/or hazardous materials/wastes shall be disposed of within the United States of America.

2.6. The contractor shall process Demilitarization (DEMIL) requirements IAW DoD MIL 4160.28 Vol 2 Section 4 of the DEMIL instruction. Except for the specific prohibitions delineated in the Contract, the Contractor may process and sell all non-radiological and non-hazardous scrap and reusable equipment/material removed from the EX-LONG BEACH.

2.7. The Contractor shall provide all personnel, equipment, tools, vehicles, materials, facilities, supervision, and other industrial equipment and services necessary to meet the requirements of this Contract and perform the scope of work described, in a manner, which is safe for workers and the environment, and complies with all applicable Federal, State, and local laws and regulations. The Contractor shall provide evidence of continued availability of such facilities for the duration of the Contract period of performance by ownership, existing lease, or letter from the facility owners indicating a statement of intent to utilize such facilities for scrapping operations, as well as evidence that site specific permits are currently in effect or can be obtained prior to the start of subject Contract.

During dismantlement and disposal, the Contractor is allowed to use any onboard equipment to support the contract. The equipment is provided “as is” with the contractor making an assessment of usefulness and safety, as well as covering any repair and testing prior to use.

2.8. The Contractor shall develop and implement a detailed schedule, including measurable milestones that include identification of all critical path work, to accomplish the Statement of Work in accordance with CDRL A001. The schedule shall include planned start and completion dates and a timeline for each phase of the dismantling, hazardous material removal and disposal in accordance with Exhibit A, including but not limited to, all tasks required for vessel dismantling including demilitarization of residual military equipment and property, identification and safe removal & disposal of hazardous materials/wastes, vessel dismantling, scrap processing, and sale and shipment of scrap and reusable equipment/material.

2.9. The Contractor shall ensure a completed and NRC verified final radiological condition of the dismantlement and disposal work site for unrestricted use upon completion of the contracted work in accordance with the DWP and NRC requirements.

2.10. Project Support Requirements

2.10.1. The Contractor shall provide public outreach support services on behalf of the project within the locality of the project throughout the period of performance of the project. Public outreach is required to be coordinated with the Navy. The Navy will review all materials prepared for the public (to include local government offices, elected officials, and non-governmental organizations) which must be provided to the Navy for review no later than 48 hours prior to use.

2.10.2. The Contractor shall immediately refer requests for briefings or reports regarding the project from Federal Government officials, including Executive Branch Departments and Members and/or offices of the Legislative Branch to the COR for action (within 1 business day). The Navy will retain responsibility for developing and coordinating responses to these entities and may elect to require the Contractor to participate in the response. This requirement is not to be construed as to withhold or await Navy approval to release information requested by regulatory agencies such as NRC, EPA, or OSHA or similar State-level agencies as it pertains to project performance or inspection visits.

3. APPLICABLE DOCUMENTS

Unless otherwise specified by the technical standards of this Contract, the Contractor shall perform the contract requirements in accordance with applicable Federal and State laws/regulations. The Navy will provide Government Furnished Information (GFI) to assist the offerors in preparing bids, including available technical documentation, select sampling results, drawings, and technical manuals for the EX- LONG BEACH. The Contractor shall maintain access to the online Document Library where this GFI will be stored until the Contractor certifies their own IT system to store this information. Technical documents provided via the Document Library are provided for background and represent when the ship was operational and/or during the inactivation availability. The references listed below are documents that will be used in performance of completing the contract requirement and included as Section J attachments.

References:

• Interagency Framework for Regulation of EX-LONG BEACH Dismantlement and Disposal (Attachment J-7)

• NUREG 1757, Vol 1 [latest version] and Vol 2 [latest version] (Attachment J-8)

• U.S Navy Towing Manual (SL740-AA-MAN-010) (Attachment J- 9)

• NRC Inspection Manual Chapters 2561 [latest version] and 2690 [latest version] (Attachment J-10)

• NN-801 Control and Protection of Unclassified Naval Nuclear Propulsion Information

(Attachment J-11)

• DOD Controlled Unclassified Information (CUI) (Attachment J-5)

• DoD MIL 4160.28 Vol 2 Section 4 of the DEMIL instruction

4. SPECIFIC REQUIREMENTS

4.1. ITEM 0001 – Transport EX-LONG BEACH to Dismantlement Site

4.1.1. Preparations for Transport

4.1.1.1. The Contractor shall provide the Navy the Transportation and Tow plan for review, and deliver a submission/status report to specified points of contact. (CDRL A007)

4.1.1.2. The Contractor shall perform transportation via heavy lift vessel, submersible barge or other conveyance considering the EX-LONG BEACH is not capable of open ocean towing. The Contractor’s plan for transportation shall be in accordance with Chapter 8 of the U.S. Navy Towing Manual (SL740- AA-MAN-010, Attachment J-9).

4.1.1.3. The Contractor’s transportation plan shall address at least the following:

a. Identification of required permits, including regulatory authority for those permits, and reasonable timelines to obtain approved permits.

b. Required conditions of the EX-LONG BEACH prior to receiving the vessel from the Navy, prior to commencing transport, including but not limited to ballasting requirements, tank levels, hull inspections and repairs.

c. Transfer of possession of the EX-LONG BEACH at a location near PSNS&IMF, Bremerton.

Identification of the location for the transfer of possession, to which the Contractor and Government shall mutually agree.

d. Loading the EX-LONG BEACH at a location near PSNS&IMF, Bremerton onto the method of conveyance to the dismantlement and disposal facility.

e. Fire and flooding monitoring and prevention measures.

f. Method of securing the EX-LONG BEACH for stability during the transport and heavy weather conditions.

Note: An Acceptance Survey, in accordance with U.S. Navy Towing Manual 8-8.2 (pgs 8-95), shall be conducted no later than 30 days prior to the anticipated tow date.

4.1.1.4. The Contractor shall coordinate with the Navy for acceptance of the vessel at the agreed upon site near PSNS&IMF.

4.1.1.5. The Contractor shall prepare the EX-LONG BEACH for loading and transportation to the dismantlement site.

4.1.1.6. The Contractor shall provide copies of all transportation related permits to the Navy for information.

4.1.2. Transportation

4.1.2.1. Upon Navy approval of the Request to Transfer Possession, the Operational Plan, the Physical and Information Security Plan, the Transportation and Tow Plan, and the Contractor providing objective evidence that the Performance Bond and LLRW disposal easement are in effect, the Navy will tow the vessel to a mutually agreed upon site near PSNS&IMF, Bremerton.

4.1.2.2. The Contractor shall load the EX-LONG BEACH onto the selected method of conveyance.

Transfer of possession of the EX-LONG BEACH will occur at a location near PSNS&IMF, Bremerton at a mutually agreeable location to the Government, and the Contractor.

4.1.2.3. The Contractor shall transport the EX-LONG BEACH via the selected method of conveyance to the dismantlement and disposal site.

4.2. ITEM 0002 – Dismantle and Dispose of EX-LONG BEACH

4.2.1. The Contractor shall develop a comprehensive Operational Plan for accepting possession of the vessel from the Navy in accordance with CDRL A017. The Operational Plan shall be delivered to the Navy for approval no later than 45 days prior to the target date for departure of EX-LONG BEACH for transport to the Contractor’s facility and will be incorporated into the Contract as Attachment J-15.

The plan shall ensure compliance with the special requirements in this Statement of Work and shall include measures to address any procedures and techniques to be used. In addition, the plan shall include measures to prevent flooding or sinking, including procedures for maintaining list, trim and stability while dismantling, environmental remediation, and recycling operations are being accomplished, maintaining vessel security throughout the performance period, and the prevention of cutting slag and other contaminants from entering the water.

4.2.1.1. The Contractor shall also demonstrate to the Government at the Contractor’s facility readiness to receive EX-LONG BEACH in accordance with the Operational Plan no later than 15 days prior to the target date for departure of EX-LONG BEACH for transport to the Contractor’s facility.

4.2.1.2. The detailed Operational Plan for Dismantling and Recycling of EX-LONG BEACH shall address at least the following elements:

4.2.1.2.1. Plans and procedures for taking over operational control of the vessel from the Navy, including measures in place for safety of personnel and the vessel;

4.2.1.2.2. Movement of the vessel within the Contractor’s facility or sub-contractor’s facilities to include plans and procedures for placing EX-LONG BEACH in a dry-dock, slip, or other berth within the Contractor’s facility;

4.2.1.2.3. Mooring configuration, including safeguarding the vessel during severe weather (Heavy Weather plan may be incorporated by reference, as applicable);

4.2.1.2.4. Security and access control measures in place at the Contractor’s facility prior to delivery of the vessel to prevent unauthorized access (may be incorporated by reference, as applicable);

4.2.1.2.5. Fire Protection Plan (may be incorporated by reference, as applicable);

4.2.1.2.6. Partially dismantling the vessel;

4.2.1.2.7. Removing and disposing of hazardous materials/wastes;

4.2.1.2.8. Sale of scrap and reusable items.

4.2.1.3. The Contractor shall include in their Operational Plan specific details for dry-docking, slip or other method for dismantling the underwater hull in an environmentally safe manner. Existing ship hull blanks and preservation system shall not be damaged by recycling operations including docking, undocking or ship grounding. The plans shall include methods for ensuring vessel stability during the cutting process, final dismantlement of underwater hull, and measures to prevent flooding or sinking.

In addition, plans shall include measures for preventing cutting slag and other contaminants from entering the water.

4.2.1.4. The Contractor shall provide the following full-time on-site key personnel in their management organization: Project Manager; Environmental, Safety & Health Manager(s); Radiological Controls/Radiation Health Manager; Production Superintendent and Facility/Information Security Officer (FSO). The replacement of any key personnel identified in the Contractor’s technical proposal shall require approval by the Government. The key personnel shall be U.S. citizens.

4.2.2. The Contractor shall submit a Physical and Information Security Plan in accordance with CDRL A008 to the Navy for approval 45 days prior to EX-LONG BEACH departing its current location.

4.2.3. The Contractor shall provide an easement or other contractual right for the Navy to dispose of 500,000 cubic feet of Low-Level Radioactive Waste (LLRW) from EX-LONG BEACH at commercial sites authorized to accept such waste. This easement shall be in place no later than the day of departure of EX-LONG BEACH from its location.

4.2.4. Decommissioning Work Plan

4.2.4.1. The Contractor shall prepare a Decommissioning Work Plan (DWP) for EX-LONG BEACH dismantlement and disposal in accordance with CDRL A014. The DWP shall be submitted to the Nuclear Regulatory Commission (NRC) to obtain their recommendation for the Navy to approve to complete the requirements of the Dismantlement and Disposal (D&D) Contract.

4.2.4.1.1. The Contractor shall prepare a Decommissioning Work Plan (DWP) in accordance with NUREG-1757 (Attachment J-8) and the clarifications in the Interagency Agreement and regulatory framework (Attachment J-7) in accordance with CDRL A014. The DWP shall be include at a minimum the following sections:

a. Description of dismantlement and disposal site conditions.

b. Description of planned decommissioning activities.

c. Planned preparatory work.

d. Worker health and safety plans (the Accident Prevention Plan may be incorporated by reference, as applicable).

e. Radiation protection program plans, including As Low As Reasonably Achievable

(ALARA);

f. Radioactive and mixed waste management plans.

g. Environmental monitoring and protection programs.

h. Quality assurance programs.

i. Survey procedures.

j. Final site status survey and release plan.

k. Demobilization activities

l. Identification of key personnel and description of experience in completing projects of similar scope/magnitude.

m. Fire Prevention Plan – in accordance with 10 CFR Section 50.48, Part 50 Appendix A & R, NRC Information notice 23-04 and Ref guide 1.191 rev 1.

n. Heavy Weather Plan to support the protection of radiological materials IAW IAA.

o. Emergency Response Plan consistent with NUREG 3.67 and Attachment J-7

4.2.4.1.2. The contractor shall address the following with the DWP:

a. The Contractor will conduct all work in a manner that prevents or mitigates the potential for release of radioactivity to the environment. The Contractor must apply appropriate environmental monitoring and effluent management programs to achieve the overall goals of no adverse effect on human health and the environment. Environmental monitoring (baseline and ongoing) is required for all work locations, in-water, pierside and on land.

b. No unvalidated decommissioning modeling or new technology will be used by the Contractor. Note that innovative decommissioning methods are welcome but will likely add time and resources to the review/approve the DWP.

c. The Contractor shall perform all radiological dismantlement and sizing evolutions in Contractor established radiologically controlled areas either inside the volume of the ship (i.e., within the hull) or inside a weather protected containment volume. Radiological work area ventilation should be HEPA filtered and maintain the work area negative relative to external areas and the environment.

d. Any radiological work conducted in an off-hull location shall be conducted over an impermeable surface and within a negatively ventilated HEPA-filtered weather protected area.

e. Temporary facilities associated with radiological work or radioactive material storage should be engineered to account for potential adverse weather conditions at the work site.

Radiological material storage areas shall be over impermeable surfaces.

f. Work planning should only allow storage of materials in full strength shipping containers when material is stored outside of the ship or containment volume (i.e., awaiting shipping).

The volume of onsite packaged radioactive waste should be minimized by prompt shipment to disposal vendors.

g. To minimize cost, and time associated with decontamination and radiological release procedures, for material identified as potentially radiologically impacted, the Contractor shall dispose of the material as LLRW when cost effective and radiation exposure is maintained As Low As Reasonably Achievable (ALARA). When cost effective, material may be surveyed for release and unrestricted use consistent with the requirements of 10 CFR 20, NUREG 1757, and applicable NRC Guidance (e.g., IE Circular 81-07).

h. The Contractor shall not dispose of radioactive material via release in effluents or via release to a sanitary sewer.

i. The Contractor shall demonstrate how the management of mixed waste will be in compliance with Federal and State requirements (e.g., provide storage requirements, handling requirements, training requirements, and reporting requirements

j. The Contractor shall restore the site to an acceptable radiological condition supporting unrestricted use.

k. DWP configuration management procedures and the threshold for changes requiring formal NRC review and Navy approval.

4.2.4.1.3. The Contractor shall submit their DWP to NRC for review and Navy approval in accordance with the Interagency Agreement and regulatory framework (Attachment J-7) and deliver a submission/status report to specified points of contact in accordance with CDRL A014. The DWP will be reviewed consistent with the procedures described in the Interagency Agreement and regulatory framework (Attachment J-7).

4.2.4.1.4. Upon approval of the DWP by the Navy, the DWP shall be incorporated into the Contract as technical requirements for completing the Contract Scope of Work and without change in the contract price or delivery schedule.

4.2.4.1.5. The Contractor may recommend via formal submittal(s) to the NRC and Navy to conduct decommissioning activities within the vessel following transfer of possession and transport of the ship to the contractor at its facility (Section 4.2.1) and prior to approval of the DWP. The Contractor’s proposed decommissioning activities prior to DWP approval will be reviewed by the NRC and approved by the Navy. However, no decommissioning activities that would disturb contamination or radiologically impacted materials will be conducted until NRC review and Navy approval of the contractor’s DWP.

4.2.5. Facilities and Licensing Requirements

4.2.5.1. The facility at which the EX-LONG BEACH will be dismantled shall be located within the United States*.

Notes:

* US Department of Defense facility clearance (e.g., to process classified material) is not required.

** The Government will not be a co-permittee on any permits or licenses obtained by the Contractor or a co-generator of any of these waste materials.

4.2.5.2. The Contractor shall demonstrate capability to safely dispose of all the low-level radioactive waste expected to be generated during the dismantlement of the EX-LONG BEACH at NRC or Agreement State licensed commercial facilities. The Contractor shall be responsible for determining how and where the radioactive waste would be disposed of and making appropriate arrangements for the disposal, consistent with applicable compacts and requirements.

Note: The Government does not intend to authorize the use of Federal waste disposal sites as part of this Contract. The Contractor is authorized to use the waste volume easement or other contractual radioactive waste disposal right for waste generated during EX-LONG BEACH dismantlement (Section 4.2.3).

4.2.5.3. The Contractor shall demonstrate capability to safely dispose of all hazardous waste expected to be generated during the dismantlement of the EX-LONG BEACH at licensed commercial facilities.

The Contractor shall be responsible for determining how and where the hazardous waste would be disposed of and making appropriate arrangements for the disposal, consistent with applicable requirements.

4.2.5.4. The Navy intends to establish an on-site presence of representatives to monitor Contractor performance for the total period of project performance. The Navy On-Site Representative (OSR) organization will also assist the Navy in implementing the Regulatory Framework the NRC and Navy have established via Interagency Agreement (Attachment J-7).

4.2.5.5. The Navy OSR organization will ensure the Contractor performs IAW contract requirements and provides well communicated production schedules and current key event milestones. Furthermore, the OSR will monitor contractor compliance with requirements and approved procedures for the following, but not limited to:

a. Operational plan and key event schedule performance;

b. DWP requirements including radiological check points and briefings;

c. Environmental and Occupational Safety and Health laws and regulations;

d. Approved ES&H management, Quality Assurance, Physical and Information security procedures;

e. Implementation of the Heavy Weather and Accident Prevention plan.

4.2.5.6. Navy OSR Authorities under this Contract:

a. Notify Contractor personnel and/or management when Contractor performance is inconsistent with the contract or approved procedures. Parallel notifications will also be provided to the Contracting Officer, Navy, and/or NRC (as applicable).

b. Issues or concerns with Contractor work being executed or planned for in accordance with approved procedures and/or the contract will be raised with the Contracting Officer, Navy, and/or NRC (as applicable) for resolution with Contractor management.

c. Ensure Contractor actions in response to an emergency are in accordance with the contract and approved procedures (i.e., protect personnel, the public, and the environment).

d. During observation of an act that could reasonably result in personnel injury or harm to the environment, promptly engage with the work team, pause operations, and allow the Contractor to validate appropriate safety precautions are in place and take any necessary action consistent with the contract, approved procedures, and/or appropriate regulations. Pauses to address these concerns shall not be considered changes to the Contract.

4.2.5.7. The Contractor shall keep the Navy OSR organization apprised of project activities, including but not limited to plans for upcoming work, issues or problems requiring resolution, inspections or inquiries from external entities, public affairs inquiries and visiting local, state and community government officials. The Contractor shall allow identical to Contractor personnel for access of the Navy OSR team to the facility and vessel, routine project related meetings, agendas, reports, and status updates.

4.2.5.8. The Contractor shall provide facilities supporting Government oversight of the Contractor, including the Navy OSR organization. These facilities shall be provided on-site within the vicinity of the EX-LONG BEACH (as close as reasonably achievable). Required minimum capabilities include:

a. Office space with sufficient HVAC, electrical power, and off-site internet connectivity (10 MB/s or greater) sufficient for up to eight (8) personnel. These office spaces shall be separate from Contractor office spaces.

b. Provide at least eight (8) parking spaces in the vicinity of the office location.

c. Conference/meeting space for up to fifteen (15) personnel separate from Contractor conference/meeting spaces.

d. Access to separate male and female toilet facilities.

Note: Portable office trailers are acceptable to meet this requirement if permanent facilities are not constructed at the EX-LONG BEACH dismantlement and disposal site. The contractor is responsible for providing furniture, office equipment (1 copier, 1 video screen, 4 desktop monitors with laptop connection capability, phones), WIFI and Internet connectivity, etc. for the Government oversight activities. The Contractor is not responsible for providing computers, printers, or other IT assets.

4.2.6. Regulated and Hazardous Waste

4.2.6.1. The Contractor shall remove and properly dispose of radiological and/or hazardous materials/wastes in accordance with applicable Federal, State, and local laws and regulations.

4.2.6.2. The Government will not be a co-permittee on any permits or licenses obtained by the Contractor or a co-generator of any waste material.

4.2.6.3. The Contractor shall demonstrate capability to safely dispose of all of the low-level radioactive waste expected to be generated during the dismantlement of the EX-LONG BEACH at NRC or Agreement State licensed commercial facilities. The Contractor shall be responsible for determining how and where the radioactive waste would be disposed of and making appropriate arrangements for the disposal, consistent with applicable compacts and requirements.

Note: The Government does not intend to authorize the use of Federal waste disposal sites as part of this Contract. The Contractor is authorized to use the waste volume easement of other contractual radioactive waste disposal right for waste generated during EX-LONG BEACH dismantlement.

4.2.7. Regulatory Framework for Conduct of Radiological Work

4.2.7.1. The Naval Nuclear Propulsion Program (NNPP), a joint Navy and Department of Energy Program, also referred to as Naval Reactors, or within Naval Sea Systems Command (NAVSEA) as the Naval Nuclear Propulsion Directorate (NAVSEA 08), is responsible for the public health and safety associated with the disposition of defueled nuclear-powered ships of the U.S. Navy per the Atomic Energy Act of 1954, as amended (AEA). Naval Reactors has statutory regulatory authorities and responsibilities to the Navy and Department of Energy as described in 50 U.S.C. §§ 2406, 2511). In preparation for this contracted work, the NNPP and U.S. Nuclear Regulatory Commission (NRC) have developed a plan for the NRC to provide support services to the Navy and the NNPP governed by a framework for oversight described in an Interagency Agreement (Attachment J-7, approved version for CVN 65, CGN 9 version is expected to be similar when approved). This Interagency Agreement (IAA) and Regulatory Framework supports the Navy in applying NRC standards and regulations via this Contract for the conduct of radiological work in the same manner as if this scope of work were performed by an NRC licensee in the NRC-regulated sector. Further, this Interagency Agreement and regulatory framework provides for NRC inspections of the Contractor’s work under published NRC inspection procedures as if the scope of work were performed at a site implementing an NRC license termination plan.

4.2.7.2. The Contractor shall conduct all radiological work in compliance with the regulatory framework described in the Interagency Agreement (Attachment J-7).

4.2.7.3. The Contractor shall refer to the responsibilities of the “licensee” when performing work subject to NRC regulations

4.2.7.4. The Contractor shall receive and implement any and all corrective actions or other direction provided by the NRC under the regulatory framework described in the Interagency Agreement (Attachment J-7).

4.2.7.5. The Navy will neither add or subtract from the NRC recommended corrective actions or other direction provided by the NRC under the regulatory framework described in the Interagency Agreement (Attachment J-7), with one exception. For significant response actions or public affairs interaction, as the regulator for the project radioactive materials, if needed or requested by the NRC the Navy will coordinate with the NRC and direct action via the Navy’s authority under the AEA and public law consistent with the National Response Framework.

4.2.7.6. The target durations of NRC and Navy reviews of Contractor deliverables described in the Interagency Agreement (Attachment J-7) are notional timelines and are only provided as a guide in support of project planning. A lack of response should not be construed for NRC or Navy concurrence or approval of deliverables.

4.2.8. Physical Security Requirements

4.2.8.1. The Contractor shall have facility controls in place to prevent physical access by unauthorized persons to the vessel, or equipment, components, and/or structures requiring demilitarization. The Contractor shall establish a system of checks, inspections, surveys, and assessments to ensure physical security of the facility and vessel is maintained.

4.2.8.2. The Contractor shall implement controls to ensure that access to the propulsion plant spaces, and equipment, or components removed from the propulsion plants within the vessel are limited to US Citizens.

4.2.8.3. The Contractor shall implement controls to ensure that access to passive protection structures within the hull are only accessible to US Citizens.

Note: Employees that are dual-nationals (i.e., hold citizenship with the United States and another foreign country) must be identified in writing to the Navy no later than 15 business days prior to the earliest date where the employee may have access to spaces and equipment defined in 4.2.8.2 and

4.2.8.3. The Navy reserves the right to restrict dual-national employees from access to the spaces and equipment defined in 4.2.8.2 and 4.2.8.3.

4.2.8.4. The Contractor shall implement controls to prevent and mitigate any unauthorized access to the vessel, propulsion plants, or other areas requiring information protection from drones.

4.2.8.5. The Contractor shall implement written plans and operating procedures for all facility physical security programs in accordance with CDRL A008.

4.2.9. Information Security Requirements

4.2.9.1. The Contractor shall safeguard Controlled Unclassified Information (CUI) and Unclassified Naval Nuclear Propulsion Information (U-NNPI) provided as GFI for performance of this contract in accordance with DoD Instruction 5200.48 (Controlled Unclassified Information) and NN-801 (Control and Protection of Unclassified Naval Nuclear Propulsion Information), respectively.

4.2.9.2. The Contractor shall adhere to the guidelines of NN-801, as obligated under contract, which fulfills supplier and sub-tier supplier requirements of OPNAVINST N9210.3 for the protection of U- NNPI noted elsewhere in this contract.

4.2.9.3. The contractor and any sub-contractors with access to the vessel or materials, equipment, and/or components from the vessel requiring demilitarization or from the propulsion plants, shall be certified to access Controlled Unclassified Information (CUI) and Unclassified Naval Nuclear Propulsion Information (U-NNPI) by completing the following:

a. Provide to the Contracting Officer on signed corporate letterhead an overview of the contractor or sub-contractor, to include services that may be applicable to ex-LONG BEACH disposal, corporate structure, locations of headquarters and major satellite offices, and links to public corporate website(s). Further, provide written certification that the contractor or sub-contractor firm is based in the United States and organized under U.S.

laws. Firms organized under U.S. laws with foreign ownership, control, or influence (FOCI) must clearly identify the extent of foreign citizen involvement in relation to the ex‑LONG BEACH disposal project, and that the firm formally agrees to prevent foreign nationals access to U-NNPI*.

b. Provide a list of persons by name that will participate in the ex-LONG BEACH disposal project and require access to U-NNPI (and other forms of CUI) and certify that these personnel are U.S. Citizens, with the method of validating U.S. citizenship clearly identified by the certifier in accordance with CDRL A009. Individuals with dual citizenship must be clearly identified, with the understanding that such individuals may not be permitted access to ex-LONG BEACH, CUI, or U-NNPI without first notifying the Navy**.

Note: Employees that are dual-nationals (i.e, hold citizenship with the United States and another foreign country) must be identified in writing to the Navy no later than 15 business days prior to the earliest date where the employee may have access to CUI or U-NNPI. The Navy reserves the right to restrict dual-national employees from access to CUI or U-NNPI.

Notes: *The certifications described above must be signed on corporate letterhead by a company officer (e.g., company president, business unit vice president, or equivalent if privately owned) or facility security officer if the firm possesses a facility security clearance granted by the Defense Counterintelligence and Security Agency (DCSA) or other authorized Government agency.

**The Navy is not requesting vendors provide personally identifiable information (PII) or other privacy protected information about these personnel.

c. Complete a security agreement [Form NN-677 found in Enclosure (1) of NN-801] for protection of U-NNPI, signed by a company officer (or equivalent if privately owned), or facility security officer if the firm possesses a DSCA facility security clearance.

d. As part of completing the Form NN-677 above, vendors are required to attach a signed copy of DD-Form 2345 (Military Critical Technical Data Agreement), which is routed and approved by the Defense Logistics Agency (DLA) Joint Certification Program (JCP);

proof of current/active registration through the DLA JCP is also acceptable in lieu of the signed DD-Form 2345. Instructions for completing the DD-Form 2345 can be found at:

https://www.dla.mil/Logistics-Operations/Services/JCP/

Note: The EX-LONG BEACH contains no physical equipment or arrangements that are controlled as classified. As such, the Navy expects that the activities supporting completion of this project, including the physical dismantlement work, as well as the preparation of contract proposals, technical work documents, and submittals provided for Government review, do not require specific classified information controls or classification. However, some of the technical documentation describing the EX-LONG BEACH contains U-NNPI. NNPI is all information, classified or unclassified, concerning the design, arrangement, development, manufacture, testing, operation, administration, training, maintenance, and repair of the propulsion plants of Navy nuclear-powered ships and prototypes including the associated shipboard and shore-based nuclear support facilities. Sensitive unclassified military technology is protected by several Federal statutes and export control regulations. Naval Nuclear Propulsion technology is subject to these controls. Hence, U-NNPI is protected and subject to these controls. The designation U-NNPI indicates that although the information is unclassified, it is subject to special handling controls, restricted access and distribution (export controls) and marking requirements and is not releasable to the general public without prior approval by the Government.

4.2.10. Control and Protection of Controlled Unclassified Information (CUI) and Unclassified Naval Nuclear Propulsion Information (U-NNPI) on Information Technology Systems

4.2.10.1. Following Contract award, the Contractor shall certify an Information Technology system for the processing of Controlled Unclassified Information (CUI) in accordance with DoD Instruction 5200.48 (Controlled Unclassified Information) and the processing of Unclassified Naval Nuclear Propulsion Information (U-NNPI) in accordance with the requirements of NN-801 to support performance of this contract.

4.2.10.2. Following Contract award, the Contractor shall provide compliant means to transmit CUI and U-NNPI to/from the Government via the Microsoft Office product suite (i.e., Microsoft 365, Outlook, Teams, etc.).

4.2.10.3 The Contractor shall maintain a current Cybersecurity Maturity Model Certification (CMMC)

Level TBD for the duration of this contract in accordance with DFARS 252.204-7021. This requirement applies to all Contractor and subcontractor information systems that process, store, or transmit Controlled Unclassified Information (CUI) in the performance of this contract, including but not limited to naval ship drawings, Navy/NAVSEA Standard Items, and technical manuals.

4.2.11. Physical and Information Security Plan

4.2.11.1. The Contractor shall deliver a Physical and Information Security Plan for Navy approval in accordance with CDRL A008, per sections 4.2.8 and 4.2.9, demonstrating methods, procedures, and controls to prevent unauthorized access to the vessel, components and equipment removed, from the vessel prior to demilitarization, components and equipment from the propulsion plants, propulsion plant spaces, and other forms of Controlled Unclassified Information (CUI) and Unclassified Naval Nuclear Propulsion Information (U-NNPI).

4.2.11.2. The Physical and Information Security plan will be approved by the Navy prior to the Navy commencing the transfer of possession of EX-LONG BEACH to the Contractor. The Physical and Information Security plan shall be submitted for approval no less than 45 days prior to the anticipated date of departure.

4.2.11.3. The Contractor shall demonstrate to the Government at the Contractor’s facility that elements necessary to support the Physical and Information Security Plan upon acceptance of possession of EX- LONG BEACH. This demonstration shall occur no later than 15 days prior to the target departure date of EX-LONG BEACH to the Contractor’s facility and may be scheduled to occur concurrently with the demonstration of the Operational Plan required elsewhere in this Contract.

4.2.11.4. Revisions to the Physical and Information Security plan that change the mitigations against unauthorized access described in 4.2.11.1 shall be submitted to the Navy for approval no later than 45 days prior to the changes being required, unless otherwise agreed to by the Navy. The Physical and Information Security plan shall also identify categories of administrative or other minor changes that may be submitted to the Navy for information; the Navy will review/approve this Physical and Information Security Plan revision control strategy as part of the initial review of the Physical and Information Security Plan.

4.2.11.5. The Contractor’s methods and procedures for control and protect of CUI and U-NNPI on Information Technology Systems (4.2.10) may be incorporated into the Physical and Information Security Plan by reference, as applicable.

4.2.12. Environmental, Safety and Health Requirements

4.2.12.1. The Contractor shall deliver an Environmental Management Plan demonstrating established measures and procedures for ensuring compliance with all applicable Federal, State, and local Environmental laws and regulations in accordance with CDRL A011. Activities subject to the Interagency Agreement and Regulatory Framework (Attachment J-7) may be consolidated into the DWP (Section 4.2.4) and referenced in the Environmental Management Plan in accordance with CDRL A011.

4.2.12.2. The Contractor shall deliver a Safety and Health Management Plan demonstrating established measures and procedures for ensuring worker safety and health in performing the work required for ship dismantling and hazardous material/waste removal and disposal in accordance with CDRL A011.

Activities subject to the Interagency Agreement and Regulatory Framework (Attachment J-7) may be consolidated into the DWP (Section 4.2.4) and referenced in the Safety and Health Management Plan in accordance with CDRL A011.

4.2.12.3. The Contractor shall conduct all work in a safe manner and shall furnish all safety equipment in accordance with Federal, State, and local laws and regulations.

4.2.12.4. The Contractor shall promptly report to the Government On-Site Representative (OSR), all available facts relating to any accident, incident, and/or injury to personnel (prime contractor or sub-contractor) or each instance of damage to Government property. Formal reports shall also be provided to the Navy under the Contractor’s Safety and Health Management Plan, which at a minimum includes timely reporting for all safety issues, including crane and rigging, fire safety issues, and truck/rail movement issues.

4.2.12.5. The Contractor shall correct any deficiencies identified by Federal, State, or local regulatory agencies without adjustment to the Contract price.

4.2.12.6. The Environmental Management and Safety and Health Management Plans do not require explicit approval by the Navy but must be accepted as complete and meeting the requirements above by the Navy and in place prior to acceptance of the vessel at the Contractor’s facility.

4.2.13. Fire Prevention and Emergency Response

4.2.13.1. For decommissioning activities subject to the Interagency Agreement and Regulatory Framework (Attachment J-7), fire prevention and safety will comply with the requirements applied to power reactors (10 CFR Part 50.48(f)) described in NRC Regulatory Guide 1.191,” Fire Protection Program for Nuclear Power Plants During Decommissioning and Permanent Shutdown” (ML011500010) and applicable information notices. Methods for meeting this requirement shall be reflected in the DWP (Section 4.2.4).

4.2.13.2. For all other activities under this contract, fire prevention and safety will be in accordance with applicable Federal, State, and local requirements.

4.2.13.3. The Contractor shall develop and deliver a Fire Prevention and Emergency Response Plan in accordance with CDRL A015.

a. The Contractor shall demonstrate an appropriate level of defense-in-depth protection against the threat of fires throughout the performance of all activities for this contract. Defense-in-depth for fire protection includes administrative controls, physical fire protection features, emergency response capabilities, and protection of radiologically controlled surfaces, systems, and components as necessary to prevent or mitigate the potential of an unacceptable release of radioactive materials.

b. The Contractor’s fire protection and emergency response program shall include outreach, coordination, and training with mutual aid and emergency response to include operational demonstration.

c. The Contractor must demonstrate capabilities that all fires can be met with immediate response from on-site personnel and capabilities at the incipient stage.

d. The Contractor’s emergency response plan will meet the requirements of Regulatory Guide 3.67 and Attachment J-7

4.2.13.4. The Contractor shall correct any deficiencies identified by Federal, State, or local regulatory agencies without adjustment to the Contract price.

4.2.13.5. The Contractor shall notify the Government On-Site Representative (OSR) in the event of any fire activity located at the disposal site immediately, within one hour, of the event. Follow on reports and event investigation to be submitted to the OSR within 24 hours.

4.2.13.6. The goal of the fire protection program envisioned during this project is to provide an appropriate level of defense-in-depth protection against the threat of fires. Defense-in-depth for fire protection involves a comprehensive program of administrative controls, physical fire protection features, emergency response capabilities, and protection of radiologically controlled…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .