USS ROSS_QA 7.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- N0002422R4422
About this file
This document contains questions and answers related to a federal solicitation for the USS ROSS (DDG 71) Extended Dry-Docking Selected Restricted Availability (EDSRA). The solicitation seeks ship repair services including maintenance, modernization, and repair. The Naval Sea Systems Command issued solicitation number N00024-22-R-4422 for the availability scheduled from July 2022 to November 2023 at East/Gulf Coast locations in the United States. Questions cover work item specifications, pricing details in attachments J-3, J-4 and Section B, and contractual limits. The Navy intends to make a single-award fixed price contract by July 2022. Offerors must register in SAM and PIEE to receive the solicitation and submit proposals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N00024-22-R-4422-0009 Conformed.pdf | ||
| USS ROSS_QA 8.xlsx | XLSX spreadsheet | |
| N00024-22-R-4422-0009.pdf | ||
| N00024-22-R-4422-0008.pdf | ||
| N00024-22-R-4422-0008 Conformed.pdf | ||
| N00024-22-R-4422-0007 Conformed.pdf | ||
| N00024-22-R-4422-0007.pdf | ||
| USS ROSS_QA 6.xlsx | XLSX spreadsheet | |
| USS ROSS_QA 5.xlsx | XLSX spreadsheet | |
| N00024-22-R-4422-0006.pdf | ||
| N00024-22-R-4422-0006 CONFORMED.pdf | ||
| N00024-22-R-4422-0005.pdf | ||
| N00024-22-R-4422-0005 CONFORMED.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PPI FORM
| USS ROSS (DDG 71) FY23 EDSRA N00024-22-R-4422 |
| Attachment S-3 Pre-Proposal Information (PPI) Form |
| MASTER TRACKER |
| Master # | Contractor | Question # | Date of Request: | Section | Work Items/CSWT # | Para. # | Page #: | Attach. # | Contractor Question | Government Response | |
| 118 | 2/17/22 | RFP | Solicitation | Reference page 70, Section B, Para. 9. "9. In the event of an extension due to excusable delay to the delivery date for the USS ROSS (DDG 71) FY22 EDSRA, the Contractor’s fully burdened ship repair labor rate shall be escalated by 0.29 % commencing 3 months after the Attachment J-3 “Contract Complete” date. Following the “Contract Complete” date identified in Attachment J-3 (Milestones), this rate shall be escalated quarterly through the 24th month, if necessary, and shall be used to negotiate all growth and new work. Note, in the event of an excusable delay, this escalation rate shall be applied only to growth and new work not previously identified in Attachment J-4 (Pricing Worksheet). The material burden rate shall not increase. | |||||||
| Please explain the calculation including all references to source material that support the government's identification of .29% as the escalation rate. | The escalation rate has been updated via Amendment 0008. Calculations inclusive of reference material are business sensitive. | ||||||||||
| 123 | 2/17/22 | RFP | Solicitation | Reference page 73, NOTE E |
"6.When the quantity of occurrences for Small Dollar Growth is depleted, the Small Dollar Growth process shall revert to the LOE to Completion process for remaining growth."
Please confirm for this stated scenario the government will decrement the same contractual limits of 101,981 labor hours or the $3,925,923 materials number identified on page 67, reference
"NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR
1. The Contractor agrees to provide the level of effort to completion (LOE to Completion) in the performance of growth CLINs in the execution of the USS ROSS (DDG 71) EDSRA:
a. 101,981 direct labor hours (labor hours) and $3,925,923 ($TBD fully burdened) materials to complete expected, within scope growth work on the USS ROSS (DDG 71) EDSRA work package under CLINS 0040 – 0083.
| Once the SDVG occurrences are used up, LOE2C will be used for remaining in-scope growth | |||
| 143 | 2/22/22 | Solicitation | Reference Page 67 of 189 |
NOTE A
NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR
1. The Contractor agrees to provide the level of effort to completion (LOE to Completion) in the performance of growth CLINs in the execution of the USS ROSS (DDG 71) EDSRA:
a. 101,981 direct labor hours (labor hours) and $3,925,923 ($TBD fully burdened) materials to complete expected, within scope growth work on the USS ROSS (DDG 71) EDSRA work package under CLINS 0040 – 0083.
Please confirm that 101,981 direct labor hours and $3,925,923 are the contractual limits the government is required to observe for all growth work and that once expended and/or if the government decides to not utilize an existing numbered growth CLIN the government will follow the FAR or DFAR changes clause for all other growth work. The number of labor hours and the material dollars for LOETC CLINs are specified in the solicitation and are based on detailed historical data collected from past availabilities.The language in Section B, Note A states that the mix of labor hours and material may be adjusted. Adjustments to the labor hour and material mix will be documented via weekly Technical Direction Letter (TDL) and subsequently unilaterally adjusted via contract modification.
In addition to the LOETC growth work, the successful offeror’s proposed fully burdened ship repair labor and material burden rates are incorporated into the contract for purposes of negotiating any additional growth work beyond the LOETC CLINs under the DFARS Over and Above Work clause, and any new work that arises during contract performance under the FAR Changes clause.
146 2/22/22 Solicitation Reference Page 67 of 189
4. LOE to Completion labor hours and material are within the scope and pricing of this contract and are not subject to an equitable adjustment under FAR 52.243-1 ‘Changes – Fixed Price’. The utilization of LOE to Completion is at the discretion of the Contracting Officer and subject to the schedule phasing identified in Note F.
| Request government identifies in this clause the contractual limits as identified in NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR, 1 to avoid potential conflict between this clauses and NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR, 1. | The Government does not understand this question as written. | |||
| 152 | 2/22/22 | Solicitation | Reference Page 70 of 189 |
9. In the event of an extension due to excusable delay to the delivery date for the USS ROSS (DDG 71) FY22 EDSRA, the Contractor’s fully burdened ship repair labor rate shall be escalated by 0.29 % commencing 3 months after the Attachment J-3 “Contract Complete” date. Following the “Contract Complete” date identified in Attachment J-3 (Milestones), this rate shall be escalated quarterly through the 24th month, if necessary, and shall be used to negotiate all growth and new work. Note, in the event of an excusable delay, this escalation rate shall be applied only to growth and new work not previously identified in Attachment J-4 (Pricing Worksheet). The material burden rate shall not increase.
Please confirm that the referenced percentage of allowable escalation is higher than all previous FY2021 awards issued by this contracting office.
| The escalation rate has been updated via Amendment 0008. | ||||||
| 167 | 2/28/22 | Attachment J-1 | 168-80-001 | 1.3, 2.2, & 4720 | There are major discrepancies with this item. Para 1.3.1 lists door 1-338-3, pc 22 as a left Hand Door, but the drawing show this door being a right hand. While, 1.3.2 Pc 3 & 1.3.3 Pc 6 identify as both Left handed doors in the spec, the 4720 identifies pc #007, right hand, & pc # 008, left hand, as being provided as GFM. These doors provided as GFM are not what is listed in para 1.3.1, 1.3.2, 1.3.3. Please review this spec, the drawing and the 4720 and provide documents that match so the Contractor can see what is required. | Work Item 168-80-001 listed in paragraph 1.3.1 was changed via Errata 5 to be a right hand door, the other two line items are correct, both are LH. The 4720 will be corrected to reflect the doors being changed by this ALT.” |
| 169 | 3/1/22 | 997-11-001 | 3.7 | We ask the Government to consider removing the requirement to have the ship docked within the first 10 percent of the contractual period. | Non-concur. The Government will not remove the requirement to have the ship docked within the first 10 percent of the contractual period. | |
| 190 | 3/1/22 | 863-51-001 | 3.3, 3.4 | How many flooding detectors are required? | The flood detectors are required for any spaces below the Design Water Line. This information is available in the work item reference | |
| 215 | 3/22/22 | RFP | Section B & J-4 | Section B & J-4 | There are a couple discrepancies noted on the J-4 - First - On the Work item tab, CLIN 0015 S/A number does not match the S/A number on Section B for the same CLIN. Please Fix Section B to match J-4. Second - On the same tab, Cell M137 does not have a formula for the Total sub. Please fix this and re-issue J-4 | This has been addressed via Amendment 0007. |
| 216 | 3/22/22 | SOLICITATION Section B and attachment J-4 | In amendment 6 a new J-4 and Section B were issued and both documents have the same errors that were previously reported in our question #138. Also found was a new header on the material & labor tab for New work rates. There is no place to enter all of these potential rates on the provided section B (note B, Para 7 of section B has a table for Growth & New work only) so you need to add blocks to fill in for separate growth and new work rates please. | This has been addressed via Amendment 0007. | ||
| 218 | 3/25/22 | 472-00-001 | 3.1-3.2 | Government's response to question 210 stated that GFM kit contains a total of 36 sheets of Type 3R tiles. However, Ref 2.2 (ORDALT KIT) Section 12.2 lists kit contents as 110 Type 3R tiles & 3 Type 18 tiles that are provided in kit for installation at shipyard. Please confirm that contractor is responsible only for the 36 total Type 3R tiles as stated in the answer to question 210. | Updated via Errata 6: Para 2.2 changed the Ordalt 80831 Change 4 to Change 6 |
Para 4.3 added: Kitted material contains 25 each of Type 3R and 3 each of Type 18.
image1.png