N00024-22-R-4422-0009 Conformed.pdf

PDF 2 MB Posted

Attached to
USS ROSS (DDG 71) Extended Dry-Docking Selected Restricted Availability (EDSRA)
Solicitation number
N0002422R4422
Issued by

About this file

This document provides details of a federal solicitation for ship repair and maintenance services. The solicitation is for the USS ROSS (DDG 71) FY22 Extended Dry-Docking Selected Restricted Availability (EDSRA) to be conducted on the East Coast of the United States. The availability is estimated at 16 months beginning in July 2022 and completing in November 2023. The work includes maintenance, modernization, and repair services. Interested parties must register in SAM.gov and the Procurement Integrated Enterprise Environment system to receive the full solicitation and submit proposals, which are due on or around July 2022. The requirement is not set aside for small businesses based on its size and complexity. The document directs offerors to the contract specialist for additional attachments and references containing distribution limitations.

View the file

Other files

File Type Posted
USS ROSS_QA 8.xlsx XLSX spreadsheet
N00024-22-R-4422-0009.pdf PDF
N00024-22-R-4422-0008.pdf PDF
USS ROSS_QA 7.xlsx XLSX spreadsheet
N00024-22-R-4422-0008 Conformed.pdf PDF
N00024-22-R-4422-0007 Conformed.pdf PDF
N00024-22-R-4422-0007.pdf PDF
USS ROSS_QA 6.xlsx XLSX spreadsheet
USS ROSS_QA 5.xlsx XLSX spreadsheet
N00024-22-R-4422-0006.pdf PDF
N00024-22-R-4422-0006 CONFORMED.pdf PDF
N00024-22-R-4422-0005.pdf PDF
N00024-22-R-4422-0005 CONFORMED.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 10:00 AM local time 18 Apr 2022

X

A X B X C X D

EX

X

G F 167 - 178

179 - 190 X H 191 - 195 james.hammersley@navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-A3 1 195

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N00024 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

JAMES M HAMMERSLEY 202-781-3149

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 77

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

78 - 114 115 - 116

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

117 - 120 121 - 127

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 128 - 138 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 139 - 140 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

141 - 165

PART II - CONTRACT CLAUSES

NAVAL SEA SYSTEMS COMMAND (HQ)

1333 ISAAC HULL AVE SE

WASHINGTON NAVY YARD DC 20376-2030

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.

N0002421FR62094

5. DATE ISSUED

28 Jan 2022

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N0002422R4422

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

CLIN

Number

1 Lot

OPTION TYCOM Base

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, and D - F

FOB: Destination

PURCHASE REQUEST NUMBER: N0002421FR62094

PSC CD: J998

NET AMT

OPTION PMS 407 Base (OMN) CLIN

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DOCKING

SELECTED RESTRICTED AVAILABILITY (EDSRA)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, and D - F FOB: Destination

OPTION PMS 407 BASE (OPN) CLIN

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DOCKING

SELECTED RESTRICTED AVAILABILITY (EDSRA)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A, B, and D - F FOB: Destination

OPTION PMS 407/TYCOM Prorate Base (OPN) CLIN

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DOCKING

SELECTED RESTRICTED AVAILABILITY (EDSRA)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2

See Notes A, B, and D - F

FOB: Destination

CDRL CLIN

FFP

FOB: Destination

OPTION TYCOM (Option Items)

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F

FOB: Destination

OPTION BMD / MDA

FFP

Antenna Array Temporary Staging (WI 991-11-001) for Use by Ship's Force; and AN/SPY-1 Antenna Array Face Resurface (WI 993-21-001) Support Service;

provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION PEO IWS / NSWC PHD

FFP

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Messing & Berthing Barge - Tow Service

FFP

Messing and Berthing Barge Long Distance Tow Service; provide (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Messing & Berthing Barge-Electrical Serv

FFP

Messing and Berthing Barge Electric Temporary Service in Contractor Plant;

provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Gonzalez (DDG 66) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Messing & Berthing Barge-Temp Service

FFP

Messing and Berthing Barge, Temporary Service, Inspection and Repair in Contractor Plant, Steam Barge; accomplish (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F

FOB: Destination

FFP

Messing and Berthing Barge, Temporary Service, Inspection and Repair in Contractor Plant, Electric Barge; accomplish (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

FFP

Messing and Berthing Barge Steam Temporary Service in Contractor Plant;

provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-88260K, Ent. Remote Mon HW

FFP

ShipAlt DDG51-88260K, Enterprise Remote Monitor Hardware Installation;

accomplish (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION OrdAlt 89524K OJ-663 CRO Monitor Upgrade

FFP

OrdAlt 89524K OJ-663 CRO Monitor Upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-86222K, NGF Bkft Ph 1 Alt

FFP

ShipAlt DDG51-86222K, NGF Backfit Phase One Alteration, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-96840K, Harpoon Weapon Sys

FFP

ShipAlt DDG51-96840K, Harpoon Weapon System Removal; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-81961K and 85114K, TTWCS

FFP

ShipAlt DDG51-81961K and 85114K, Tactical Tomahawk Weapon Control System (TTWCS) V5.4.0.2 and TC2S 5.0.1V7 Hardware; accomplish (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-81961K and 85114K, TTWCS

FFP

ShipAlt DDG51-81961K and 85114K, TTWCS V5.4.0.2 and TC2S 5.0.1V7, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-80255K, Replace Mag FDS

FFP

ShipAlt DDG51-80255K, Replace Magazine Fire Detection System; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Crew Living Space Hab / BENL-R1075

FFP

Crew Living Space Habitability Project (BENL-R1075) Installation; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Crew Living Space Hab / BENL-R9587

FFP

Crew Living Space Habitability Project (BENL-R9587) Installation; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Crew Living Space Hab / BCPO-S6212

FFP

CPO Living Space Habitability Project (BCPO-S6212) Installation; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Crew Sanitary Space Hab / HENL-R1076

FFP

Crew Sanitary Space Habitability Project (HENL-R1076) Installation; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Crew Sanitary Space Hab / HENL-R9588

FFP

Crew Sanitary Space Habitability Project (HENL-R9588) Installation; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION CPO Sanitary Space Hab / HCPO-S6214

FFP

CPO Sanitary Space Habitability Project (HCPO-S6214) Installation; accomplish

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Eng Change (EC) DDG51-90119K, Navy Cash

FFP

Engineering Change (EC) DDG51-90119K, Navy Cash Equipment Refresh, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-75360K, CBSP Tier 3, AIT

FFP

ShipAlt DDG51-75360K, CBSP Tier 3, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-80897K NMT-AN/WSC-9(V)X/KA

FFP

ShipAlt DDG51-80897K NMT-AN/WSC-9(V)X/KA, Alteration Installation Team (AIT) Support; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG-51-81798K, NAVMACS AIT

FFP

ShipAlt DDG-51-81798K, NAVMACS Technical Refresh Installation, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-84646K SSEE Mod SA 555 AIT

FFP

ShipAlt DDG51-84646K, SSEE Mod SA 555, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-85030K, GBS AIT

FFP

ShipAlt DDG51-85030K, Global Broadcast System (GBS) Receive Broadcast Manager (RBM), Alteration Installation Team (AIT) Support Service; provide

(OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-89715K, SSEE AIT

FFP

ShipAlt DDG51-89715K, Ships Signal Exploitation Equipment (SSEE) Increment F System, Alteration Installation Team (AIT) Support Service; provide (OPTION

ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-91014K, CANES AIT

FFP

ShipAlt DDG51-91014K, Consolidated Afloat Networks and Enterprise Services (CANES) HW2 Tech Refresh, Alteration Installation Team (AIT) Support Service;

provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-91027K, GPNTS(V)4, AIT

FFP

ShipAlt DDG51-91027K, GPNTS(V)4, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-95946K, C2P Tech Ref AIT

FFP

ShipAlt DDG51-95946K, C2P Tech Refresh, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt DDG51-86644K USW-DSS AIT

FFP

ShipAlt DDG51-86644K USW-DSS AN/UYQ-100(V)3 to AN-SQQ-89A (V) 15 Interface-CRUDES AIT Support Services; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION ShipAlt 94979K HM&E Condition System AIT

FFP

ShipAlt 94979K, HM&E Condition System, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

OPTION Ship Towing Service; provide

FFP

Ship Towing Service; provide (OPTION ITEM)

PREPARE FOR AND ACCOMPLISH REPAIR AND ALTERATIONS

ONBOARD USS ROSS (DDG 71) DURING FY23 EXTENDED DRY-

DOCKING SELECTED RESTRICTED AVAILABILITY (EDSRA) (Non-prorated WIs – See attachment J-4 for list)

The Contractor shall prepare for and accomplish repair and alterations during the Extended Dry-Docking Selected Restricted Availability (EDSRA) onboard USS Ross (DDG 71) as specified in the statement of work provided herein and in accordance with standard items, work item specification package drawings, test procedures, and other detailed data as included in Attachments J-1 and J-2.

See Notes A - F FOB: Destination

Growth associated with CLIN 0001

FFP

Growth associated with CLIN 0001. See Attachment J-4.

See Notes A, B, D, E, and F

FOB: Destination

OPTION Growth associated with CLIN 0001

FFP

Growth associated with CLIN 0001. See Attachment J-4.

See Notes A - F

FOB: Destination

FFP

Growth associated with CLIN 0001. See Attachment J-4.

See Notes A - F

FOB: Destination

FFP

Growth associated with CLIN 0001. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0002

FFP

Growth associated with CLIN 0002. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0003

FFP

Growth associated with CLIN 0003. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0003

FFP

Growth associated with CLIN 0003. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0004

FFP

Growth associated with CLIN 0004. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0004

FFP

Growth associated with CLIN 0004. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0006

FFP

Growth associated with CLIN 0006. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0007

FFP

Growth associated with CLIN 0007. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0007

FFP

Growth associated with CLIN 0007. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0008

FFP

Growth associated with CLIN 0008. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0009

FFP

Growth associated with CLIN 0009. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0010

FFP

Growth associated with CLIN 0010. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0011

FFP

Growth associated with CLIN 0011. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0012

FFP

Growth associated with CLIN 0012. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0013

FFP

Growth associated with CLIN 0013. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0014

FFP

Growth associated with CLIN 0014. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0015

FFP

Growth associated with CLIN 0015. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0016

FFP

Growth associated with CLIN 0016. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0017

FFP

Growth associated with CLIN 0017. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0018

FFP

Growth associated with CLIN 0018. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0019

FFP

Growth associated with CLIN 0019. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0020

FFP

Growth associated with CLIN 0020. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0021

FFP

Growth associated with CLIN 0021. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0022

FFP

Growth associated with CLIN 0022. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0023

FFP

Growth associated with CLIN 0023. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0024

FFP

Growth associated with CLIN 0024. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0025

FFP

Growth associated with CLIN 0025. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0026

FFP

Growth associated with CLIN 0026. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0027

FFP

Growth associated with CLIN 0027. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0028

FFP

Growth associated with CLIN 0028. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0029

FFP

Growth associated with CLIN 0029. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0030

FFP

Growth associated with CLIN 0030. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0031

FFP

Growth associated with CLIN 0031. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0032

FFP

Growth associated with CLIN 0032. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0033

FFP

Growth associated with CLIN 0033. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0034

FFP

Growth associated with CLIN 0034. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0035

FFP

Growth associated with CLIN 0035. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0036

FFP

Growth associated with CLIN 0036. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0037

FFP

Growth associated with CLIN 0037. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0038

FFP

Growth associated with CLIN 0038. See Attachment J-4.

See Notes A - F

FOB: Destination

OPTION Growth associated with CLIN 0039

FFP

Growth associated with CLIN 0039. See Attachment J-4.

See Notes A - F

FOB: Destination

AVAILABILITY PREPARATION - USS ROSS

FFP

The Contractor shall provide all labor, materials, facilities, supervision and equipment to meet the requirements outlined in Section C – Statement of Work, paragraph 9. All work shall be completed in accordance with all applicable local, State, Federal and Navy rules and regulations; whether they are explicitly written/referenced in this SF33 or not.

FOB: Destination

ADVANCED MATERIAL PROCUREMENT

FFP

The Contractor shall provide all labor, materials, facilities, supervision and equipment to meet the requirements outlined in Section C – Statement of Work, paragraph 10. All work shall be completed in accordance with all applicable local, State, Federal and Navy rules and regulations; whether they are explicitly written/referenced in this SF33 or not.

FOB: Destination

NOTE A

NOTE A: LEVEL OF EFFORT TO COMPLETION –SHIP REPAIR

1. The Contractor agrees to provide the level of effort to completion (LOE to Completion) in the performance of growth CLINs in the execution of the USS ROSS (DDG 71) EDSRA:

a. 101,699 direct labor hours (labor hours) and $3,922,873 ($TBD fully burdened) materials to complete expected, within scope growth work on the USS ROSS (DDG 71) EDSRA work package under CLINS 0040 – 0083.

2. The total LOE to Completion for the performance of the above growth CLINs shall be comprised of labor hours and the associated material required to support the expected, within scope growth. The mix of labor hours and material may be adjusted. Adjustments to the labor hour and material mix will be documented via weekly Technical Direction Letter (TDL) and subsequently unilaterally adjusted via contract modification. The Government reserves the right to reconcile the weekly TDLs via unilateral modification at the Administrative Contracting Officer’s (ACO) discretion.

3. LOE to completion obligations specified above shall only include effort performed in direct support of this contract and shall not include time and effort expended on such things as (local travel to and from an employee's usual work location), uncompensated effort while on travel status, truncated lunch periods, work (actual or inferred) at an employee's residence or other non-work locations.

4. LOE to Completion labor hours and material are within the scope and pricing of this contract and are not subject to an equitable adjustment under FAR 52.243-1 ‘Changes – Fixed Price’. The utilization of LOE to Completion is at the discretion of the Contracting Officer and subject to the schedule phasing identified in Note F.

5. If, in the opinion of the Contractor, any effort directed in the Growth Management Request Form (GMR) calls for effort outside the scope of the contract, the Contractor shall notify the Administrative Contracting Officer (ACO) in writing within two (2) working days after the receipt of any such direction. In the event of a cost dispute, the ACO may unilaterally authorize hours and material against LOE work. The Contractor shall not proceed with the work directed by the GMR unless and until the Contractor is notified by the ACO to proceed with the directed work. The Contractor is required to proceed with the directed work as directed by the ACO.

Thereafter, any remaining disagreement shall be addressed in accordance with FAR 52.233-1(Alt. 1) ‘Disputes.’

Additionally, if the cost of performing the disputed direction exceeds $100,000, the Contractor is required to comply with FAR 52.243-6 ‘Change Order Accounting.’

6. The labor hours and material requirements listed in Section B, Note A, paragraph 1 above are part of this contract. Prime contractor efforts shall be deducted from the labor hours allocated. Subcontractor efforts and materials shall be deducted from the materials allocated. The balance of labor hours and materials remaining in the LOE to Completion CLINs will be recouped by the Government via final contract modification at the end of the availability.

7. Only authorized direct production labor hours shall be deducted from the LOE to Completion direct labor hour ceiling set forth in Section B, Note A, paragraph 1 above. Per Note B paragraph 2 below, all non-production labor shall be included in the Contractor’s fully burdened labor rate. Non-production hours shall not be included in pricing submitted in support of growth issued under the LOE to Completion CLINs. Additionally, Contractor LOE to Completion pricing shall not include any allowance for technical representatives or for any other Government directed source unless specifically directed by the Contracting Officer.

8. Only authorized material dollars shall be deducted from LOE to Completion material reservation set forth in

Section B, Note A, paragraph 1 above. This material reservation consists of the total cost of materials and subcontractor efforts proposed. All subcontractor quotes shall be included in the Change Order Price Analysis (COPA) as per Section C, paragraph 1.13. Material dollars may include freight or duties if specifically itemized on the invoice for the material. The Contractor shall not be allowed to add material handling charges, overhead (including G&A), or profit into the settled cost of materials deducted from the material reservation.

9. The information received in the consolidated final report required by Section C paragraph 6.6 will be used by the ACO in the issuance of one contract modification based on the information received in the final report identified in Section C below, which will be a final settlement for all LOE to Completion labor hours and material dollars. Once the number of labor hours and materials for directed work has been settled, neither party shall be entitled to an adjustment because the expended labor hours and materials differ from the settled price.

This shall not preclude an adjustment otherwise permitted by law and regulation; e.g. fraud, product substitution, defective workmanship or materials. Each directed work shall receive approval by the SUPERVISOR and the ACO. (“SUPERVISOR” as defined in NAVSEA Standard Item (NSI) 009-01, paragraph 4.3, refers to the local Government activity responsible for the execution and contract administration of Navy maintenance and modernization work.)

NOTE B

NOTE B: FIXED SHIP REPAIR LABOR AND MATERIAL BURDEN RATES FOR GROWTH AND

NEW WORK

SCHEDULE OF PRICES / RATES: SHIP REPAIR LABOR RATE (FULLY BURDENED)

1. The Contractor’s fully burdened ship repair labor rate will be used for negotiating growth and new work to be performed under this contract. The contractor agrees that the number of hours included in its price proposal submitted in response to Requests for Contract Changes (RCCs), Growth Management Requests (GMRs) and Reservation Task Requests (RTRs) shall include only direct production hours. For these purposes, direct production hours are for skilled labor at the journeyman level expended in direct production including but not limited to the following functions:

Abrasive cleaning/blasting Fire Watch Welding Burning Brazing Carpentry Machinists (inside and outside) Electrical Work Electronic Work Engineering Design Support Lagging Ship-fitting Boiler-making Painting Sheet-metal Work Pipefitting Rigging General Labor Staging/Scaffolding Diesel Mechanics

2. The fully burdened ship repair labor rate proposed by the contractor listed in paragraph 7 below shall include all costs associated with support functions (whether charged directly or indirectly by the offeror’s accounting systems) provided in support of the direct production functions listed in paragraph 1 above.

Support functions shall be considered to be included in the offeror’s fully burdened ship repair labor rate for direct production hours. Labor hours for the below support functions shall not be separately proposed, including in support of subcontractors. Support functions include, and are not limited to, those types listed below:

Testing Quality Assurance Execution Planning Cleaning (except tank cleaning) Supervision (all types, including, but not limited to supervision of trades, support personnel and subcontractors) Security Surveying Administration Transportation Purchasing Staff Lofting Other indirect support Handling & Warehousing Safety/Environmental

Program Management

3. The fully burdened ship repair labor rate is a fixed hourly rate that includes all wages, (i.e. straight time, overtime, shift differential, holiday time, etc.), overhead, all other indirect costs, general and administrative expenses, Facilities Capital Cost of Money (FCCOM) and profit. The fully burdened ship repair labor rate represents a blended rate including labor transferred between divisions, subsidiaries, or affiliates of the contractor under a common control.

4. Consumable materials are goods used in the ordinary course of work performance such as office supplies, paper, rags, vehicle or equipment fuel costs, cleaning chemicals, disposable tools, welding rods, paint buckets, paint brushes, protective clothing, etc., that are consumed/used in the process of repair and do not become an integral part of the repaired vessel. Consumable material shall be included in the contractor’s fully burdened ship repair labor rate and not separately priced.

5. Physical materials are goods that become incorporated into the repaired vessel in the course of the repair, such as replacement steel, pipes, paint, and fasteners. The material burden rate applies to physical materials but not to consumable materials. The material burden rate will be applied to the actual cost of the physical material. Actual cost does not include handling charges, general and administrative cost, overhead, profit, or any other indirect cost.

6. For growth and new work contract changes involving subcontractors, subcontractor quotes will be treated as

Other Direct Costs (ODCs) and will be subject to the contract material burden rate shown in paragraph (7) below. Subcontractor quotes must be competitively acquired and submitted with the contractor’s COPA in response to RCCs, GMRs and RTRs issued by the Contracting Officer. At no time will the proposed total to be performed by the prime contractor combined with subcontractor quote, material quote, and applicable burdens be allowed to cost more than it would have, had the prime contractor directly provided all material and labor. The proposed total pricing restriction addressed in the preceding sentence does not apply in any case where the work is required to be performed by Original Equipment Manufacturers (OEMs), Government directed subcontractors, and/or Government authorized vendors. RCCs and RTRs that are subcontracted for material only (no associated labor required within the RCC) shall not be subject to the Material Burden Rate. Any material burden rate applied to new work shall be approved by the ACO, upon receipt of supporting documentation in accordance with FAR 15.404-3, Subcontract Pricing Considerations.

7. The contract fixed fully burdened ship repair labor rate and new work labor rates and material burden growth and new work rate are shown below. These fixed rates shall be used for negotiating growth and new work during the availability and up to three (3) months after the Attachment J-3 ‘Contract Complete’ date:

USS ROSS (DDG 71) FY23 EDSRA

Fully Burdened Ship Repair Growth Labor Rate TBD Fully Burdened Ship Repair New Work Labor TBD Material Burden Growth Rate TBD Material Burden New Work Rate TBD

8. In the event of a one-bid or directed availability, the Contracting Officer may negotiate the Fully Burdened

Ship Repair Labor Rate and Material Burden Rate (not to exceed the ceiling rate(s) identified above) with the offeror in accordance with FAR 15.4, Contract Pricing. The rates herein are not considered a Forward Pricing Rate Agreement (FPRA) and are identified solely for the purpose of establishing a ceiling.

9. In the event of an extension due to excusable delay to the delivery date for the USS ROSS (DDG 71) FY23 EDSRA, the Contractor’s fully burdened ship repair labor rate shall be escalated by 0.40 % commencing 3 months after the Attachment J-3 “Contract Complete” date.