Att_4_2205_Production_and_Delivery_Schedule Rev.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Synopsis for US Navy 8M and 11 M Rigid Inflatable Boat (RIB) and U. S. C. G. Special Purpose Craft Law Enforcement II
Solicitation number
N0002421R2205
Issued by

About this file

This document outlines a proposed production and delivery schedule for rigid inflatable boats to be procured by the Naval Sea Systems Command and United States Coast Guard over five years. The schedule details that up to 110 boats total would be delivered in batches of two per month on a recurring basis, with boats going to the Navy's Special Warfare units and the Coast Guard's law enforcement operations. Variants include 8-meter and 11-meter open center console and enclosed cabin boats. Delivery timelines range from 30 days after the previous boat up to 240 days after order placement, depending on whether production is continuous or if a break is required between orders. The schedule provides notional and proposed delivery dates for each potential boat by destination, number, and ordering period across the five-year contract period.

View the file

Other files

File Type Posted
Att_1_DRAFT Specification.pdf PDF
Att_9_DRAFT Past Performance Information.docx DOCX document
N00024-21-R-2205 DRAFT RFP.pdf PDF
Att_3_DRAFT Boat Initial Spare Parts List.xlsx XLSX spreadsheet
Att_4_DRAFT Production and Delivery Schedule.xlsx XLSX spreadsheet
Att_2_ DRAFT Specification Response Matrix.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Production Schedule

NSW SSC and USCG SPC-LE Production and Delivery Schedule (Production Base Contract)

Days After Contract Award (DAC)
ConfigurationDesign Maturity ReviewOrder
Major ItemsReceipt of Major ItemsStart
Hull FabricationInstall
EnginesSubmit
TDPConduct
PDITsDeliver
BoatNSW 11m OCC
*DeliveryNSW 8m OCC
*DeliveryUSCG 11m OCC

*Delivery

Boat 1NSW 11m OCC360 DAC
Boat 2USCG 11m OCCN/AN/AN/A360 DAC
Boat 3NSW 11m OCC390 DAC
Boat 4USCG 11m OCC390 DAC
Boat 5NSW 8m OCCN/AN/AN/A420 DAC
Boat 6USCG 11m OCCN/AN/AN/A420 DAC
Boat 7NSW 11m OCCN/AN/AN/A450 DAC
Boat 8USCG 11m OCCN/AN/AN/A450 DAC
Boat 9NSW 11m OCCN/AN/AN/A480 DAC
Boat 10NSW 11m OCCN/AN/AN/A480 DAC
Boat 11NSW 11m OCCN/AN/AN/A510 DAC
Boat 12NSW 11m OCCN/AN/AN/A510 DAC
Boat 13NSW 11m OCCN/AN/AN/A540 DAC
Boat 14NSW 11m OCCN/AN/AN/A540 DAC
* Government desired delivery dates
Notes:1. Add the planned number of days after contract award for each of the events in the cells above
2. Design Maturity Review is a desired one time event.
3. Major Items include engines, trailers and raw material suppliers (aluminum)

4. PDITs only occur for Boats #1, 3, 4

N00024-21-R-2205 Attachment 4

Delivery Schedule

NSW SSC and USCG SPC-LE Proposed Production and Delivery Schedule (Delivery Base and Follow-On Delivery Orders)

ORDERING PERIOD 1
DELIVERY ORDER 1
NSW 11m OCC SSC (Unless otherwise noted)USCG 11m OCC SPC-LE
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Boat 1TBD360 DAYS AFTER ORDERBoat 1TBD360 DAYS AFTER ORDER
Boat 230 DAYS AFTER LAST BOATBoat 230 DAYS AFTER LAST BOAT
Boat 3 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 3TBD30 DAYS AFTER LAST BOAT
Boat 4TBD30 DAYS AFTER LAST BOATBoat 4TBD30 DAYS AFTER LAST BOAT
Boats 5-10 (2 per month)30 DAYS AFTER LAST BOAT
DELIVERY ORDER 2 (No Break in Production)
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Craft No.DestinationNotional Delivery Schedule
Proposed Delivery Schedule
Boat 11TBD30 DAYS AFTER LAST BOATBoat 5TBDSame date as NSW Boat #11
Boat 12 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 6TBD30 DAYS AFTER LAST BOAT
Boat 13 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 7TBD30 DAYS AFTER LAST BOAT
Boat 14TBD30 DAYS AFTER LAST BOATBoat 8TBD30 DAYS AFTER LAST BOAT
Boat 15TBD30 DAYS AFTER LAST BOATBoat 9TBD30 DAYS AFTER LAST BOAT
Boat 16 (8m OCC)TBD30 DAYS AFTER LAST BOATBoat 1030 DAYS AFTER LAST BOAT
Boat 17 (8m OCC)TBD30 DAYS AFTER LAST BOAT
Boat 18TBDSame date as boat 17
Boats 19-20TBD30 DAYS AFTER LAST BOAT
ORDERING PERIOD 2
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Boats 21-30 (boats 23-24 are 8m OCC)TBD30 DAYS AFTER LAST BOATBoats 11-20TBD30 DAYS AFTER LAST BOAT
Boats 21-30 (2 per month)TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Boat 21TBD240 DAYS AFTER ORDERBoat 11TBD240 DAYS AFTER ORDER
Boats 22-30 (boats 23-24 are 8m OCC)TBD30 DAYS AFTER LAST BOATBoats 12-20TBD30 DAYS AFTER LAST BOAT
Boats 21-30 (2 per month)30 DAYS AFTER LAST BOAT
ORDERING PERIOD 3
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Craft No.DestinationNotional Delivery Schedule (No Break in Production)
Proposed Delivery Schedule (No Break in Production)
Boats 31-40 (boats 33-34 are 8m Cabin)TBD30 DAYS AFTER LAST BOATBoats 31-40TBD30 DAYS AFTER LAST BOAT
Boats 41-50 (2 per month)30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Craft No.DestinationNotional Delivery Schedule (Break in Production)
Proposed Delivery Schedule (Break in Production)
Boat 31TBD240 DAYS AFTER ORDERBoat 31TBD240 DAYS AFTER ORDER
Boats 32-40 (boats 33-34 are 8m Cabin)TBD30 DAYS AFTER LAST BOATBoats 32-40TBD30 DAYS AFTER LAST BOAT
Boats 41-50 (2 per month)30 DAYS AFTER LAST BOAT
ORDERING PERIOD 4
Craft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule
NO BREAK in ProductionCraft No.DestinationNotional Delivery Schedule
NO BREAK in ProductionProposed Delivery Schedule

NO BREAK in Production

Boats 41-50 (boats 43-44 are 11m Cabin)TBD30 DAYS AFTER LAST BOATBoats 51-60TBD30 DAYS AFTER LAST BOAT
Craft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule
BREAK in ProductionCraft No.DestinationNotional Delivery Schedule
BREAK in ProductionProposed Delivery Schedule

BREAK in Production

Boat 41TBD240 DAYS AFTER ORDERBoat 51240 DAYS AFTER ORDERBoats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32
Boats 42-50 (boats 43-44 are 11m Cabin)TBD30 DAYS AFTER LAST BOATBoats 52-6030 DAYS AFTER LAST BOATBoats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32Boats 31-32
DEFINITIONS:DEFINITIONS:
BREAK in Production: If a Delivery Order is issued after 120 days from the date of delivery of the last boat on order. (Example: Last boat on current order delivery date: 15 July 2019, new order placed any time after 15 March 2019 would be defined as a BREAK in production. Boat 1 of the new Delivery Order would have a delivery date of 240 days after placement of new Delivery Order)

NO BREAK in Production: If a Delivery Order is issued before 120 days from delivery of last boat on order. (Example: Last boat on current order delivery date 15 July 2019, new order placed any time before 14 March 2019 would be defined as NO BREAK in production. Boat 1 on the new Delivery Order would have a delivery date of 15 August 2019)