Att_4_2205_Production_and_Delivery_Schedule Rev.xlsx
XLSX spreadsheet 23 KB Posted
- Solicitation number
- N0002421R2205
About this file
This document outlines a proposed production and delivery schedule for rigid inflatable boats to be procured by the Naval Sea Systems Command and United States Coast Guard over five years. The schedule details that up to 110 boats total would be delivered in batches of two per month on a recurring basis, with boats going to the Navy's Special Warfare units and the Coast Guard's law enforcement operations. Variants include 8-meter and 11-meter open center console and enclosed cabin boats. Delivery timelines range from 30 days after the previous boat up to 240 days after order placement, depending on whether production is continuous or if a break is required between orders. The schedule provides notional and proposed delivery dates for each potential boat by destination, number, and ordering period across the five-year contract period.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Att_1_DRAFT Specification.pdf | ||
| Att_9_DRAFT Past Performance Information.docx | DOCX document | |
| N00024-21-R-2205 DRAFT RFP.pdf | ||
| Att_3_DRAFT Boat Initial Spare Parts List.xlsx | XLSX spreadsheet | |
| Att_4_DRAFT Production and Delivery Schedule.xlsx | XLSX spreadsheet | |
| Att_2_ DRAFT Specification Response Matrix.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Production Schedule
NSW SSC and USCG SPC-LE Production and Delivery Schedule (Production Base Contract)
| Days After Contract Award (DAC) | ||||
| Configuration | Design Maturity Review | Order | ||
| Major Items | Receipt of Major Items | Start | ||
| Hull Fabrication | Install | |||
| Engines | Submit | |||
| TDP | Conduct | |||
| PDITs | Deliver | |||
| Boat | NSW 11m OCC | |||
| *Delivery | NSW 8m OCC | |||
| *Delivery | USCG 11m OCC |
*Delivery
| Boat 1 | NSW 11m OCC | 360 DAC | |||||
| Boat 2 | USCG 11m OCC | N/A | N/A | N/A | 360 DAC | ||
| Boat 3 | NSW 11m OCC | 390 DAC | |||||
| Boat 4 | USCG 11m OCC | 390 DAC | |||||
| Boat 5 | NSW 8m OCC | N/A | N/A | N/A | 420 DAC | ||
| Boat 6 | USCG 11m OCC | N/A | N/A | N/A | 420 DAC | ||
| Boat 7 | NSW 11m OCC | N/A | N/A | N/A | 450 DAC | ||
| Boat 8 | USCG 11m OCC | N/A | N/A | N/A | 450 DAC | ||
| Boat 9 | NSW 11m OCC | N/A | N/A | N/A | 480 DAC | ||
| Boat 10 | NSW 11m OCC | N/A | N/A | N/A | 480 DAC | ||
| Boat 11 | NSW 11m OCC | N/A | N/A | N/A | 510 DAC | ||
| Boat 12 | NSW 11m OCC | N/A | N/A | N/A | 510 DAC | ||
| Boat 13 | NSW 11m OCC | N/A | N/A | N/A | 540 DAC | ||
| Boat 14 | NSW 11m OCC | N/A | N/A | N/A | 540 DAC | ||
| * Government desired delivery dates | |||||||
| Notes: | 1. Add the planned number of days after contract award for each of the events in the cells above | ||||||
| 2. Design Maturity Review is a desired one time event. | |||||||
| 3. Major Items include engines, trailers and raw material suppliers (aluminum) |
4. PDITs only occur for Boats #1, 3, 4
N00024-21-R-2205 Attachment 4
Delivery Schedule
NSW SSC and USCG SPC-LE Proposed Production and Delivery Schedule (Delivery Base and Follow-On Delivery Orders)
| ORDERING PERIOD 1 | |||
| DELIVERY ORDER 1 | |||
| NSW 11m OCC SSC (Unless otherwise noted) | USCG 11m OCC SPC-LE | ||
| Craft No. | Destination | Notional Delivery Schedule | |
| Proposed Delivery Schedule | |||
| Craft No. | Destination | Notional Delivery Schedule | |
| Proposed Delivery Schedule |
| Boat 1 | TBD | 360 DAYS AFTER ORDER | Boat 1 | TBD | 360 DAYS AFTER ORDER |
| Boat 2 | 30 DAYS AFTER LAST BOAT | Boat 2 | 30 DAYS AFTER LAST BOAT | ||
| Boat 3 (8m OCC) | TBD | 30 DAYS AFTER LAST BOAT | Boat 3 | TBD | 30 DAYS AFTER LAST BOAT |
| Boat 4 | TBD | 30 DAYS AFTER LAST BOAT | Boat 4 | TBD | 30 DAYS AFTER LAST BOAT |
| Boats 5-10 (2 per month) | 30 DAYS AFTER LAST BOAT | ||||
| DELIVERY ORDER 2 (No Break in Production) | |||||
| Craft No. | Destination | Notional Delivery Schedule | |||
| Proposed Delivery Schedule | |||||
| Craft No. | Destination | Notional Delivery Schedule | |||
| Proposed Delivery Schedule |
| Boat 11 | TBD | 30 DAYS AFTER LAST BOAT | Boat 5 | TBD | Same date as NSW Boat #11 |
| Boat 12 (8m OCC) | TBD | 30 DAYS AFTER LAST BOAT | Boat 6 | TBD | 30 DAYS AFTER LAST BOAT |
| Boat 13 (8m OCC) | TBD | 30 DAYS AFTER LAST BOAT | Boat 7 | TBD | 30 DAYS AFTER LAST BOAT |
| Boat 14 | TBD | 30 DAYS AFTER LAST BOAT | Boat 8 | TBD | 30 DAYS AFTER LAST BOAT |
| Boat 15 | TBD | 30 DAYS AFTER LAST BOAT | Boat 9 | TBD | 30 DAYS AFTER LAST BOAT |
| Boat 16 (8m OCC) | TBD | 30 DAYS AFTER LAST BOAT | Boat 10 | 30 DAYS AFTER LAST BOAT | |
| Boat 17 (8m OCC) | TBD | 30 DAYS AFTER LAST BOAT | |||
| Boat 18 | TBD | Same date as boat 17 | |||
| Boats 19-20 | TBD | 30 DAYS AFTER LAST BOAT | |||
| ORDERING PERIOD 2 | |||||
| Craft No. | Destination | Notional Delivery Schedule (No Break in Production) | |||
| Proposed Delivery Schedule (No Break in Production) | |||||
| Craft No. | Destination | Notional Delivery Schedule (No Break in Production) | |||
| Proposed Delivery Schedule (No Break in Production) |
| Boats 21-30 (boats 23-24 are 8m OCC) | TBD | 30 DAYS AFTER LAST BOAT | Boats 11-20 | TBD | 30 DAYS AFTER LAST BOAT |
| Boats 21-30 (2 per month) | TBD | 30 DAYS AFTER LAST BOAT | |||
| Craft No. | Destination | Notional Delivery Schedule (Break in Production) | |||
| Proposed Delivery Schedule (Break in Production) | |||||
| Craft No. | Destination | Notional Delivery Schedule (Break in Production) | |||
| Proposed Delivery Schedule (Break in Production) |
| Boat 21 | TBD | 240 DAYS AFTER ORDER | Boat 11 | TBD | 240 DAYS AFTER ORDER |
| Boats 22-30 (boats 23-24 are 8m OCC) | TBD | 30 DAYS AFTER LAST BOAT | Boats 12-20 | TBD | 30 DAYS AFTER LAST BOAT |
| Boats 21-30 (2 per month) | 30 DAYS AFTER LAST BOAT | ||||
| ORDERING PERIOD 3 | |||||
| Craft No. | Destination | Notional Delivery Schedule (No Break in Production) | |||
| Proposed Delivery Schedule (No Break in Production) | |||||
| Craft No. | Destination | Notional Delivery Schedule (No Break in Production) | |||
| Proposed Delivery Schedule (No Break in Production) |
| Boats 31-40 (boats 33-34 are 8m Cabin) | TBD | 30 DAYS AFTER LAST BOAT | Boats 31-40 | TBD | 30 DAYS AFTER LAST BOAT |
| Boats 41-50 (2 per month) | 30 DAYS AFTER LAST BOAT | ||||
| Craft No. | Destination | Notional Delivery Schedule (Break in Production) | |||
| Proposed Delivery Schedule (Break in Production) | |||||
| Craft No. | Destination | Notional Delivery Schedule (Break in Production) | |||
| Proposed Delivery Schedule (Break in Production) |
| Boat 31 | TBD | 240 DAYS AFTER ORDER | Boat 31 | TBD | 240 DAYS AFTER ORDER | |
| Boats 32-40 (boats 33-34 are 8m Cabin) | TBD | 30 DAYS AFTER LAST BOAT | Boats 32-40 | TBD | 30 DAYS AFTER LAST BOAT | |
| Boats 41-50 (2 per month) | 30 DAYS AFTER LAST BOAT | |||||
| ORDERING PERIOD 4 | ||||||
| Craft No. | Destination | Notional Delivery Schedule | ||||
| NO BREAK in Production | Proposed Delivery Schedule | |||||
| NO BREAK in Production | Craft No. | Destination | Notional Delivery Schedule | |||
| NO BREAK in Production | Proposed Delivery Schedule |
NO BREAK in Production
| Boats 41-50 (boats 43-44 are 11m Cabin) | TBD | 30 DAYS AFTER LAST BOAT | Boats 51-60 | TBD | 30 DAYS AFTER LAST BOAT | |
| Craft No. | Destination | Notional Delivery Schedule | ||||
| BREAK in Production | Proposed Delivery Schedule | |||||
| BREAK in Production | Craft No. | Destination | Notional Delivery Schedule | |||
| BREAK in Production | Proposed Delivery Schedule |
BREAK in Production
| Boat 41 | TBD | 240 DAYS AFTER ORDER | Boat 51 | 240 DAYS AFTER ORDER | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 |
| Boats 42-50 (boats 43-44 are 11m Cabin) | TBD | 30 DAYS AFTER LAST BOAT | Boats 52-60 | 30 DAYS AFTER LAST BOAT | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 | Boats 31-32 |
| DEFINITIONS: | DEFINITIONS: | ||||||||||||||||||||||||||||||||||||||||||||||||
| BREAK in Production: If a Delivery Order is issued after 120 days from the date of delivery of the last boat on order. (Example: Last boat on current order delivery date: 15 July 2019, new order placed any time after 15 March 2019 would be defined as a BREAK in production. Boat 1 of the new Delivery Order would have a delivery date of 240 days after placement of new Delivery Order) |
NO BREAK in Production: If a Delivery Order is issued before 120 days from delivery of last boat on order. (Example: Last boat on current order delivery date 15 July 2019, new order placed any time before 14 March 2019 would be defined as NO BREAK in production. Boat 1 on the new Delivery Order would have a delivery date of 15 August 2019)