N00024-19-R-5380.pdf

PDF 952 KB Posted

Attached to
FY19-23 MK 41 Vertical Launching System (VLS) Canister Production
Solicitation number
N00024-19-R-5380
Issued by

About this file

This is a solicitation for the FY19-23 MK 41 Vertical Launch System (VLS) Canister Production contract. The Navy seeks to procure MK 41 VLS canisters, ancillary hardware, spares, and associated support equipment in support of US Navy, NATO SEASPARROW Missile Consortium, and Foreign Military Sales requirements from FY19 through FY23. Offerors must be a US company or independent US subsidiary to be considered for award, though foreign contractors may act as subcontractors. The export of defense articles is subject to ITAR requirements. Interested parties should check FedBizOpps for any updates to this notice.

View the file

Other files

File Type Posted
N00024-19-R-5380-0003_(Conformed).docx DOCX document
Attachment_22,_Step_Ladder_Pricing_4.18.2019.xls XLS spreadsheet
Attachment_26_-_DFARS_252.227-7018.xlsx XLSX spreadsheet
Attachment_25_-_DFARS_252.227-7017.xlsx XLSX spreadsheet
N00024-19-R-5380-0003_(Mod).docx DOCX document
19-R-5380_Bidders_Q&A_4.25.2019.xlsx XLSX spreadsheet
19-R-5380_Bidders_Q&A_4.16.2019.xlsx XLSX spreadsheet
N00024-19-R-5380-0002_(Mod).docx DOCX document
Exhibit_A_and_B,_N00024-19-R-5380_CDRL_4.9.2019.pdf PDF
N00024-19-R-5380-0002_(Conformed).docx DOCX document
Attachment_22,_Step_Ladder_Pricing_4.1.2019.xls XLS spreadsheet
Attachment_10,_Warranty_tracking_4.1.2019.xls XLS spreadsheet
Attachment_10,_Warranty_tracking_3.20.2019.xls XLS spreadsheet
N00024-19-R-5380-0001.docx DOCX document
Attachment_22,_Step_Ladder_Pricing_3.7.2019.xls XLS spreadsheet
N00024-19-R-5380-0001_(Conformed).docx DOCX document
19-R-5380_Bidders_Q&A_3.28.2019.xlsx XLSX spreadsheet
Attachment_1,_SOW_3.26.19.docx DOCX document
19-R-5380_Bidders_Q&A_3.19.2019.xlsx XLSX spreadsheet
RFP_Attachments.zip ZIP file
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 02:00 PM local time 15 May 2019

X

A X B X C X D

EX

X

G F 191 - 195

196 - 214 X H 215 - 218 robert.j.larkin@navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-A3 1 218

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N00024 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 2 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

ROBERT J. LARKIN 202-781-5478

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 96

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

97 - 113 114 - 118

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

119 - 125 126 - 145

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 146 - 151 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 152 - 154 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

155 - 188

PART II - CONTRACT CLAUSES

NAVAL SEA SYSTEMS COMMAND (HQ)

1333 ISAAC HULL AVE SE

WASHINGTON NAVY YARD DC 20376-2030

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

189 - 190

6. REQUISITION/PURCHASE NO.

N0002416NR43027

5. DATE ISSUED

14 Feb 2019

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N0002419R5380

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

CLIN

Number

Each

MK 13 MOD 0 Canisters w/ PHS&T

FFP

(FY 19)

Notes C and G FOB: Destination

PURCHASE REQUEST NUMBER: N0002416NR43027

PSC CD: 1440

NET AMT

OPTION MK 14 MOD 2 Canisters w/ PHS&T

FFP

(FY 19)

Notes B, C, and G FOB: Destination

MK 21 MOD 2 Canisters w/ PHS&T

FFP

(FY 18 and 19) Notes C and G FOB: Destination

OPTION MK 21 MOD 3 Canisters w/ PHS&T

FFP

(FY 19)

Notes B, C, and G FOB: Destination

OPTION MK 21 MOD 4 Canisters w/ PHS&T

FFP

(FY 19)

Notes B, C, and G FOB: Destination

OPTION MK 25 MOD 0 Canisters w/ PHS&T

FFP

(FY 19)

Notes B, C, and G FOB: Destination

MK 25 MOD 1 Canisters w/ PHS&T

FFP

(FY 18 and 19) Notes C and G FOB: Destination

MK 29 MOD 0 Canisters w/ PHS&T

FFP

(FY 19)

Notes C and G FOB: Destination

OPTION Renewed Expended MK 14 MOD 2 Canisters

FFP

Renewed Expended GFP MK 14 MOD 2 Canisters w/ PHS&T

(FY 19)

Notes B and C FOB: Destination

OPTION Renewed Expended MK 13 MOD 0 Canisters

FFP

Renewed Expended GFP MK 13 MOD 0 Canisters w/ PHS&T

(FY 19)

Notes B and C FOB: Destination

OPTION Renewed Expended MK 25

FFP

Note B

0111AA

OPTION Renewed Expended MK 25 MOD 0

FFP

Renewed Expended GFP MK 25 MOD 0 Canisters w/ PHS&T

(FY 19)

Notes B and D FOB: Destination

OPTION Renewed Expended MK 21 Canisters

0112AA

OPTION Renewed Expended MK 21 MOD 2 Canisters

FFP

Renewed Expended GFP MK 21 MOD 2 Canisters w/ PHS&T

(FY19)

Notes B and D FOB: Destination

0112AB

OPTION Renewed Expended MK 21 MOD 3 Canisters

FFP

Renewed Expended GFP MK 21 MOD 3 Canisters w/ PHS&T

(FY 19)

Notes B and D FOB: Destination

Coding Plug Assemblies

FFP

(FY 19)

Note C FOB: Destination

Coding Plug Assemblies

FFP

(FY 19)

Note C FOB: Destination

OPTION Explosive Bolts MK 7

FFP

Explosive Bolts, MK 7 MOD 0

(FY 19)

Notes B and C FOB: Destination

OPTION Impulse Cartridge

FFP

Impulse Cartridge Assembly, MK 236 MOD 1

(FY 19)

Notes B and C FOB: Destination

Lot

Explosive Bolts MK 8

FFP

Explosive Bolts, MK 8 MOD 0 for MK 25 MOD 0 and Mod 1 Canisters, (FY 18 and 19) Note C FOB: Destination

OPTION MK 41 VLS Canister Spares

0127AA

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO

(FY 19)

Notes B, D, and F FOB: Destination

0127AB

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO Missile Recertification

(FY 19)

Notes B, D, and F FOB: Destination

1 Each

OPTION Production Readiness Review

FFP

Preliminary and Final Production Readiness Reviews

(FY 19)

Note B FOB: Destination

OPTION Aft Closure First Article Test

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 13 MOD 0 Physical Configuration Audit

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 13 MOD 0 Forward Closure

FFP

MK 13 MOD 0 Forward Closure First Article Test

(FY 19)

Note B FOB: Destination

OPTION MK 21 MOD 2 Physical Configuration Audit

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 21 MOD 2 First Article Test

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 21 MOD 4 Physical Configuration Audit

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 21 MOD 4 First Article Test

FFP

(FY 19)

Note B

FOB: Destination

OPTION MK 25 MOD 1 Physical Configuration Audit

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 25 MOD 1 First Article Test

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 29 MOD 0 Physical Configuration Audit

FFP

(FY 19)

Note B FOB: Destination

OPTION MK 29 MOD 0 First Article Test

FFP

(FY 19)

Note B FOB: Destination

OPTION Explosive Bolts MK 10

FFP

Explosive Bolts, MK 10 MOD 0 for MK 21 MOD 2, MOD 3, MOD 4 and MK 29 MOD 0 Canisters

(FY 19)

Notes B and C FOB: Destination

OPTION MK VLS Launcher Support

0141AA

1 Lot

FFP

MK VLS Launcher Support Equipment Spares in Support of Canister Support Facility and WPNSTA Yorktown (USN)

(FY 19)

Note B FOB: Destination

0141AB

FFP

MK VLS Launcher Support Equipment Spares in Support of WPNSTA Seal Beach

(USN)

(FY 19)

Note B FOB: Destination

OPTION Interface Converter Ethernet

FFP

Interface Converter Ethernet Assemblies in Support of MK 21 MOD 4 Canisters

(USN)

(FY 19)

Notes B and C FOB: Destination

OPTION Resilient Shock Mounts

FFP

Resilient Shock Mounts for MK 41 VLS Canister PHS&T

(FY 19)

Notes B and C FOB: Destination

OPTION Canister Upgrade Kits

FFP

MK 25 MOD 0 to MOD 1 Canister Upgrade Kits

(FY 19)

Notes B and C FOB: Destination

Data

FFP

Not Separately Priced (NSP)

Note A

See Exhibit A, DD Form 1423 FOB: Destination

OPTION Provisioned Items Orders (PIO)

The combined value of all orders placed under this CLIN shall not exceed $25M Notes B and E

OPTION MK 13 MOD 0 Canisters w/ PHS&T

FFP

(FY 20)

Notes B, C, and G FOB: Destination

FFP

(FY 20)

Notes B, C, and G FOB: Destination

OPTION MK 21 MOD 2 Canisters w/ PHS&T

FFP

(FY 20)

Notes B, C, and G FOB: Destination

FFP

(FY 20)

Notes B, C, and G FOB: Destination

FFP

(FY 20)

Notes B, C, and G FOB: Destination

OPTION MK 25 MOD 0 Canisters w/ PHS&T

FFP

(FY 20)

Notes B, C, and G FOB: Destination

OPTION MK 25 MOD 1 Canisters w/ PHS&T

FFP

(FY 20)

Notes B, C, and G FOB: Destination

OPTION MK 29 MOD 0 Canisters w/ PHS&T

FFP

(FY 20)

Notes B, C, and G FOB: Destination

FFP

Renewed Expended GFP MK 14 MOD 2 Canisters w/ PHS&T

(FY 20)

Notes B and C FOB: Destination

FFP

Renewed Expended GFP MK 13 MOD 0 Canisters w/ PHS&T

(FY 20)

Notes B and C FOB: Destination

0211AA

FFP

Renewed Expended GFP MK 25 MOD 0 Canisters w/ PHS&T

(FY 20)

Notes B and D

0212AA

FFP

Renewed Expended GFP MK 21 MOD 2 Canisters w/ PHS&T

(FY 20)

Notes B and D FOB: Destination

0212AB

FFP

Renewed Expended GFP MK 21 MOD 3 Canisters w/ PHS&T

(FY 20)

Notes B and D FOB: Destination

OPTION Coding Plug Assemblies

FFP

(FY 20)

Notes B and C FOB: Destination

FFP

(FY 20)

Notes B and C FOB: Destination

FFP

Explosive Bolts, MK 7 MOD 0

(FY 20)

Notes B and C FOB: Destination

FFP

Impulse Cartridge Assembly, MK 236 MOD 1

(FY 20)

Notes B and C FOB: Destination

OPTION Explosive Bolts MK 8

FFP

Explosive Bolts, MK 8 MOD 0 for MK 25 MOD 0 and Mod 1Canisters

(FY 20)

Notes B and C FOB: Destination

0227AA

FFP

MK 41 VLS Canister Spares in Support of VLS Canister Support Facility, Weapons Stations, and of USN/FMS/NSPO.

(FY 20)

Notes B, D, and F FOB: Destination

0227AB

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO Missile Recertification.

(FY 20)

Notes B, D, and F FOB: Destination

FFP

(FY 20)

Note B FOB: Destination

FFP

(FY 20)

Note B FOB: Destination

FFP

(FY 20)

Note B FOB: Destination

FFP

(FY 20)

Note B FOB: Destination

FFP

(FY 20)

Note B FOB: Destination

FFP

Explosive Bolts, MK 10 MOD 0 for MK 21 MOD 2, MOD 3, MOD 4 and MK 29 MOD 0 Canisters

(FY 20)

Notes B and C FOB: Destination

0241AA

FFP

MK VLS Launcher Support Equipment Spares for Canister Support Facility and WPNSTA Yorktown (USN)

(FY 20)

Note B FOB: Destination

0241AB

FFP

MK VLS Launcher Support Equipment Spares for WPNSTA Seal Beach (USN)

(FY 20)

Note B FOB: Destination

FFP

Interface Converter Ethernet Assemblies in Support of MK 21 MOD 4 Canisters

(USN)

(FY 20)

Notes B and C FOB: Destination

FFP

Resilient Shock Mounts for MK 41 VLS Canister PHS&T

(FY 20)

Notes B and C FOB: Destination

FFP

MK 25 MOD 0 to MOD 1 Canister Upgrade Kits

(FY 20)

Notes B and C FOB: Destination

FFP

(FY 21)

Notes B, C, and G FOB: Destination

FFP

(FY 21)

Notes B, C, and G FOB: Destination

FFP

(FY 21)

Notes B, C, and G FOB: Destination

FFP

(FY 21)

Notes B, C, and G FOB: Destination

FFP

(FY 21)

Notes B, C, and G FOB: Destination

FFP

(FY 21)

Notes B, C, and G FOB: Destination

FFP

(FY 21)

Notes B, C, and G FOB: Destination

FFP

Renewed Expended GFP MK 14 MOD 2 Canisters w/ PHS&T

(FY 21)

Notes B and C FOB: Destination

FFP

Renewed Expended GFP MK 13 MOD 0 Canisters w/ PHS&T.

(FY 21)

Notes B and C FOB: Destination

0311AA

FFP

Renewed Expended GFP MK 25 MOD 0 Canisters w/ PHS&T

(FY 21)

Notes B and D FOB: Destination

0311AB

OPTION Renewed Expended MK 25 MOD 1

FFP

Renewed Expended GFP MK 25 MOD 1 Canisters w/ PHS&T

(FY 21)

Notes B and D FOB: Destination

0312AA

FFP

Renewed Expended GFP MK 21 MOD 2 Canisters w/ PHS&T

(FY 21)

Notes B and D FOB: Destination

0312AB

FFP

Renewed Expended GFP MK 21 MOD 3 Canisters w/ PHS&T

(FY 21)

Notes B and D FOB: Destination

FFP

(FY 21)

Notes B and C FOB: Destination

FFP

(FY 21)

Notes B and C FOB: Destination

FFP

Explosive Bolts, MK 7 MOD 0

(FY 21)

Notes B and C FOB: Destination

FFP

Impulse Cartridge Assembly, MK 236 MOD 1

(FY 21)

Notes B and C FOB: Destination

FFP

Explosive Bolts, MK 8 MOD 0 for MK 25 MOD 0 and MOD 1 Canisters

(FY 21)

Notes B and C FOB: Destination

0327AA

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO.

(FY 21)

Notes B, D, and F FOB: Destination

0327AB

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO Missile Recertification.

(FY 21)

Notes B, D, and F FOB: Destination

FFP

(FY 21)

Note B FOB: Destination

FFP

(FY 21)

Note B FOB: Destination

FFP

(FY 21)

Note B FOB: Destination

FFP

(FY 21)

Note B FOB: Destination

FFP

(FY 21)

Note B FOB: Destination

FFP

Explosive Bolts MK 10 MOD 0 for MK 21 MOD 2, MOD 3, MOD 4 and MK 29 MOD 0 Canisters

(FY 21)

Notes B and C FOB: Destination

0341AA

FFP

MK VLS Launcher Support Equipment Spares for Canister Support Facility and WPNSTA Yorktown (USN)

(FY 21)

Note B FOB: Destination

0341AB

FFP

MK VLS Launcher Support Equipment Spares for WPNSTA Seal Beach(USN)

(FY 21)

Note B FOB: Destination

FFP

Interface Converter Ethernet Assemblies in Support of MK 21 MOD 4 Canisters

(USN)

(FY 21)

Notes B and C FOB: Destination

FFP

Resilient Shock Mounts for MK 41 VLS Canister PHS&T

(FY 21)

Notes B and C FOB: Destination

FFP

MK 25 MOD 0 to MOD 1 Canister Upgrade Kits

(FY 21)

Notes B and C FOB: Destination

FFP

(FY 22)

Notes B, C, and G FOB: Destination

FFP

(FY 22)

Notes B, C, and G FOB: Destination

FFP

(FY 22)

Notes B, C, and G FOB: Destination

FFP

(FY 22)

Notes B, C, and G FOB: Destination

FFP

(FY 22)

Notes B, C, and G FOB: Destination

FFP

(FY 22)

Notes B, C, and G

FOB: Destination

FFP

(FY 22)

Notes B, C, and G FOB: Destination

FFP

Renewed Expended GFP MK 14 MOD 2 Canisters w/ PHS&T

(FY 22)

Notes B and C FOB: Destination

FFP

Renewed Expended GFP MK 13 MOD 0 Canisters w/ PHS&T.

(FY 22)

Notes B and C FOB: Destination

0411AA

FFP

Renewed Expended GFP MK 25 MOD 0 Canisters w/ PHS&T

(FY 22)

Notes B and D FOB: Destination

0411AB

FFP

Renewed Expended GFP MK 25 MOD 1 Canisters w/ PHS&T

(FY 22)

Notes B and D FOB: Destination

0412AA

FFP

Renewed Expended GFP MK 21 MOD 2 Canisters w/ PHS&T

(FY 22)

Notes B and D FOB: Destination

0412AB

FFP

Renewed Expended GFP MK 21 MOD 3 Canisters w/ PHS&T

(FY 22)

Notes B and D FOB: Destination

FFP

(FY 22)

Notes B and C

FFP

(FY 22)

Notes B and C FOB: Destination

FFP

Explosive Bolts, MK 7 MOD 0

(FY 22)

Notes B and C FOB: Destination

FFP

Impulse Cartridge Assembly, MK 236 MOD 1

(FY 22)

Notes B and C FOB: Destination

FFP

Explosive Bolts, MK 8 MOD 0 for MK 25 MOD 0 and Mod 1 Canisters

(FY 22)

Notes B and C FOB: Destination

0427AA

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO

(FY 22)

Notes B, D, and F FOB: Destination

0427AB

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO Missile Recertification

(FY 22)

Notes B, D, and F FOB: Destination

FFP

(FY 22)

Note B FOB: Destination

FFP

(FY 22)

Note B FOB: Destination

FFP

(FY 22)

Note B FOB: Destination

FFP

(FY 22)

Note B FOB: Destination

FFP

(FY 22)

Note B FOB: Destination

FFP

Explosive Bolts, MK 10 MOD 0 for MK 21 MOD 2, MOD 3, MOD 4 and MK 29 MOD 0 Canisters

(FY 22)

Notes B and C FOB: Destination

0441AA

FFP

MK VLS Launcher Support Equipment Spares for Canister Support Facility and WPNSTA Yorktown (USN)

(FY 22)

Note B FOB: Destination

0441AB

FFP

MK VLS Launcher Support Equipment Spares for WPNSTA Seal Beach (USN)

(FY 22)

Note B FOB: Destination

FFP

Interface Converter Ethernet Assemblies in Support of MK 21 MOD 4 Canisters

(USN)

(FY 22)

Notes B and C FOB: Destination

FFP

Resilient Shock Mounts for MK 41 VLS Canister PHS&T

(FY 22)

Notes B and C FOB: Destination

FFP

MK 25 MOD 0 to MOD 1 Canister Upgrade Kits

(FY 22)

Notes B and C FOB: Destination

FFP

(FY 23)

Notes B, C, and G FOB: Destination

FFP

(FY 23)

Notes B, C, and G FOB: Destination

FFP

(FY 23)

Notes B, C, and G FOB: Destination

FFP

(FY 23)

Notes B, C, and G FOB: Destination

FFP

(FY 23)

Notes B, C, and G FOB: Destination

FFP

(FY 23)

Notes B, C, and G FOB: Destination

FFP

(FY 23)

Notes B, C, and G FOB: Destination

FFP

Renewed Expended GFP MK 14 MOD 2 Canisters w/ PHS&T

(FY 23)

Notes B and C FOB: Destination

FFP

Renewed Expended GFP MK 13 MOD 0 Canisters w/ PHS&T.

(FY 23)

Notes B and C FOB: Destination

0511AA

FFP

Renewed Expended GFP MK 25 MOD 0 Canisters w/ PHS&T

(FY 23)

Notes B and D FOB: Destination

0511AB

FFP

Renewed Expended GFP MK 25 MOD 1 Canisters w/ PHS&T

(FY 23)

Notes B and D FOB: Destination

0512AA

FFP

Renewed Expended GFP MK 21 MOD 2 Canisters w/ PHS&T

(FY 23)

Notes B and D FOB: Destination

0512AB

FFP

Renewed Expended GFP MK 21 MOD 3 Canisters w/ PHS&T

(FY 23)

Notes B and D FOB: Destination

FFP

(FY 23)

Notes B and C FOB: Destination

FFP

(FY 23)

Notes B and C FOB: Destination

FFP

Explosive Bolts, MK 7 MOD 0

(FY 23)

Notes B and C FOB: Destination

FFP

Impulse Cartridge Assembly, MK 236 MOD 1

(FY 23)

Notes B and C FOB: Destination

FFP

Explosive Bolts, MK 8 MOD 0 for MK 25 MOD 0 and MOD 1 Canisters

(FY 23)

Notes B and C FOB: Destination

0527AA

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO

(FY 23)

Notes B, D, and F FOB: Destination

0527AB

FFP

MK 41 VLS Canister Spares in Support of USN/FMS/NSPO Missile Recertification

(FY 23)

Notes B, D, and F FOB: Destination

FFP

(FY 23)

Note B FOB: Destination

FFP

(FY 23)

Note B FOB: Destination

FFP

(FY 23)

Note B FOB: Destination

FFP

(FY 23)

Note B FOB: Destination

FFP

(FY 23)

Note B FOB: Destination

FFP

Explosive Bolts, MK 10 MOD 0 for MK 21 MOD 2, MOD 3, MOD 4 and MK 29 MOD 0 Canisters

(FY 23)

Notes B and C FOB: Destination

0541AA

FFP

MK VLS Launcher Support Equipment Spares for Canister Support Facility and WPNSTA Yorktown (USN)

(FY 23)

Note B FOB: Destination

0541AB

FFP

MK VLS Launcher Support Equipment Spares for WPNSTA Seal Beach (USN)

(FY 23)

Note B FOB: Destination

FFP

Interface Converter Ethernet Assemblies in Support of MK 21 MOD 4 Canisters

(USN)

(FY 23)

Notes B and C FOB: Destination

FFP

Resilient Shock Mounts for MK 41 VLS Canister PHS&T

(FY 23)

Notes B and C FOB: Destination

FFP

MK 25 MOD 0 to MOD 1 Canister Upgrade Kits

(FY 23)

Notes B and C FOB: Destination

SECTION B NOTES

NOTE A - Offeror shall provide information for the “Price Group and “Estimated Total Price” blocks of each data item Blocks 17 and 18 of the Contract Data Requirements List(s), attached hereto in JS-4.

NOTE B - Option Item to which Section I FAR clause 52.217-7 OPTION FOR INCREASED QUANTITY – SEPARATELY PRICED LINE ITEM (MAR 1989) (NAVSEA VARIATION I) (SEP 2009) is applicable and which is to be supplied only if and to the extent said Option is exercised.

NOTE C – Stepladder pricing is utilized at the CLIN level under this contract to provide the contractor an opportunity to propose different pricing for separate and distinct quantity ranges within each CLIN. Pricing utilized at contract award and option exercise shall be based solely on the pricing proposed by the contractor in Attachment 22. Stepladder CLINs may be unilaterally broken out by the Government into Sub Contract Line Items (SLINs) at time of award or option exercise to accommodate funding or delivery requirements. If this occurs, there shall be no change to unit price.

The Government reserves the right to unilaterally adjust the quantity and unit price of each stepladder Option CLIN in accordance with this Note (Note C), if and to the extent said Option CLINs are exercised.

For all CLINs with stepladder pricing, the Government may unilaterally exercise a given line item more than once prior to the latest option exercise date identified in clause FAR 52.217-7 (see Section I). Option CLINs with stepladder pricing may be exercised until the total quantity purchased equals the maximum quantity listed for that option CLIN in Attachment 22.

If any line item is exercised more than once within a 90 day period from the date the Option was initially exercised, the unit price of the CLIN shall be adjusted downward to reflect the appropriate stepladder unit price for the entire quantity purchased within that 90 day period and funds will be realigned, as necessary.

The following hypothetical example illustrates how pricing will be adjusted for option CLIN 0000 if the line item is unilaterally exercised more than once within a 90 day period:

CLIN 0000 Stepladder Qty Unit Price

100 – 200 $150 201 – 300 $120 301 – 400 $100

Upon first exercise of option, $22,500 is obligated to subline item (SLIN) 0000AA to provide funds to acquire a quantity of 150 units at a unit cost of $150.

150*$150 = $22,500

Upon second exercise of option, $12,500 is obligated to SLIN 0000AB to provide funds to acquire an additional 200 units for a total quantity of 350 units at a unit cost of $100.

350*$100 = $35,000

Following exercise of our first two options for CLIN 0000, our contract CLIN structure for CLIN 0000 is as follows:

CLIN SLIN UNIT COST EXTENDED PRICE FUNDED AMOUNT

0000 $100.00 $35,000 $35,000

0000 AA $150 $22,500 $22,500

0000 AB $62.50 $12,500 $12,500

NOTE D – Stepladder pricing at the Sub Contract Line Items (SLINs) level is utilized under this contract to provide the contractor an opportunity to propose different pricing for separate and distinct quantity ranges within each SLIN. Pricing utilized at contract award and option exercise shall be based solely on the pricing proposed by the contractor in Attachment 22.

For all SLINs with stepladder pricing, the Government will unilaterally exercise the line item once prior to the latest option exercise date identified in clause FAR 52.217-7 (see Section I).

NOTE E – Provisioned Item Orders (PIO) may be placed against this line item on a firm-fixed price basis. The Government reserves the unilateral right to issue multiple orders under this CLIN with the quantities, unit of issue, and pricing thereof to be established by mutual agreement of the parties in accordance with HQ C-1-0003 ITEM(S), 0199 - PROVISIONED ITEMS ORDERS (NAVSEA) (APR 2015).

NOTE F - The FMS Case Number for these CLINs will be provided at time of award or at time of option exercise.

NOTE G – The Government will only procure Items 0101, 0102, 0103, 0104, 0105, 0106, 0107, 0108, 0201, 0202, 0203, 0204, 0205, 0206, 0207, 0208, 0301, 0302, 0303, 0304, 0305, 0307, 0308, 0401, 0402, 0403, 0404, 0405, 0407, 0408, 0501, 0502, 0503, 0504, 0505, 0507, and 0508 in a combination that will procure no more than three thousand three hundred and twenty two (3,322) total production units.

Fiscal Year

PRODUCTION CLIN EXERCISED

NUMBER OF PRODUCTION

UNITS PROCURED

Total Units Authorized (NTE 3,322) : Total Units To Date: 0

This note will be unilaterally updated by the Contracting Officer upon exercise of any production options.

CLAUSES INCORPORATED BY FULL TEXT

HQ B-2-0004 EXPEDITING CONTRACT CLOSEOUT (NAVSEA) (DEC 1995)

(a) As part of the negotiated fixed price or total estimated amount of this contact, both the Government and the Contractor have agreed to waive any entitlement that otherwise might accrue to either party in any residual dollar amount of $500 or less at the time of final contract closeout. The term “residual dollar amount” shall include all money that would otherwise be owed to either party at the end of the contract, except that, amounts connected in any way with taxation, allegations of fraud and/or antitrust violations shall be excluded. For purposes of determining residual dollar amounts, offsets of money owed by one party against money that would otherwise be paid by that party may be considered to the extent permitted by law.

(b) This agreement to waive entitlement to residual dollar amounts has been considered by both parties. It is agreed that the administrative costs for either party associated with collecting such small dollar amounts could exceed the amount to be recovered.

HQ B-2-0017 REFUNDS (SPARES AND SUPPORT EQUIPMENT) (NAVSEA) (SEP 1990)

(a) In the event that the price of a spare part or item of support equipment delivered under this contract significantly exceeds its intrinsic value, the Contractor agrees to refund the difference. Refunds will only be made for the difference between the intrinsic value of the item at the time an agreement on price was reached and the contract price. Refunds will not be made to recoup the amount of cost decreases that occur over time due to productivity gains (beyond economic purchase quantity considerations) or changes in market conditions.

(b) For purposes of this requirement, the intrinsic value of an item is defined as follows:

(1) If the item is one which is sold or is substantially similar or functionally equivalent to one that is sold in substantial quantities to the general public, intrinsic value is the established catalog or market price, plus the value of any unique requirements, including delivery terms, inspection, packaging, or labeling.

(2) If there is no comparable item sold in substantial quantities to the general public, intrinsic value is defined as the price an individual would expect to pay for the item based upon an economic purchase quantity as defined in FAR 52.207-4, plus the value of any unique requirements, including delivery terms, inspection, packaging or labeling.

(c) At any time up to two years after delivery of a spare part or item of support equipment, the Contracting Officer may notify the Contractor that based on all information available at the time of the notice, the price of the part or item apparently exceeds its intrinsic value.

(d) If notified in accordance with paragraph (c) above, the Contractor agrees to enter into good faith negotiations with the Government to determine if, and in what amount, the Government is entitled to a refund.

(e) If agreement pursuant to paragraph (d) above cannot be reached, and the Navy's return of the new or unused item to the Contractor is practical, the Navy, subject to the Contractor's agreement, may elect to return the item to the Contractor. Upon return of the item to its original point of Government acceptance, the Contractor shall refund in full the price paid. If no agreement pursuant to paragraph (d) above is reached, and return of the item by the Navy is impractical, the Contracting Officer may, with the approval of the Head of the Contracting Activity, issue a Contracting Officer's final decision on the matter, subject to Contractor appeal as provided in the "DISPUTES" clause (FAR 52.233-1).

(f) The Contractor will make refunds, as required under this requirement, in accordance with instructions from the Contracting Officer.

(g) The Contractor shall not be liable for a refund if the Contractor advised the Contracting Officer in a timely manner that the price it would propose for a spare part or item of support equipment exceeded its intrinsic value, and with such advice, specified the estimated proposed price, the estimated intrinsic value and known alternative sources or item, if any, that can meet the requirement.

(h) This requirement does not apply to any spare parts or items of support equipment whose price is determined through adequate price competition. This requirement also does not apply to any spare part or item of support equipment with a unit price in excess of $100,000; or in excess of $25,000 if the Contractor submitted, and certified the currency, accuracy and completeness of, cost or pricing data applicable to the item.

HQ B-2-0022 CONTRACT SUMMARY FOR PAYMENT OFFICE (FIXED PRICE) (FEB 1997)

This entire contract is firm fixed price.

Section C - Descriptions and Specifications

Item 0101 and Option Items 0201, 0301, 0401 and 0501– MK 13 MOD 0 Canisters w/PHS&T:

The MK 13 MOD 0 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the Critical Item Performance Specifications (CIPS), Weapon Specification WS-20318, the MK 13 MOD 0 Canister Parameters Document, NAVSEA Drawing No. 7116148, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 13 MOD 0 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0102, 0202, 0302, 0402 and 0502– MK 14 MOD 2 Canisters w/PHS&T:

The MK 14 MOD 2 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the Critical Item Performance Specifications (CIPS), Weapon Specification WS-20318, the MK 14 MOD 2 Canister Parameters Document, NAVSEA Drawing No. 7251170, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 14 MOD 2 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Item 0103 and Option Items 0203, 0303, 0403 and 0503 – MK 21 MOD 2 Canisters w/PHS&T:

The MK 21 MOD 2 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the Critical Item Performance Specifications (CIPS), Weapon Specification WS-20318, the MK 21 MOD 2 Canister Parameters Document, NAVSEA Drawing No. 7251721, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 21 MOD 2 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0104, 0204, 0304, 0404 and 0504 – MK 21 MOD 3 Canisters w/PHS&T:

The MK 21 MOD 3 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the CIPS, Weapon Specification WS-20318, the MK 21 MOD 3 Canister Parameters Document, NAVSEA Drawing No. 8240134, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 21 MOD 3 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0105, 0205, 0305, 0405 and 0505 – MK 21 MOD 4 Canisters w/PHS&T:

The MK 21 MOD 4 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the CIPS, Weapon Specification WS-20318, the MK 21 MOD 4 Canister Parameters Document, NAVSEA Drawing No. 8408670, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 21 MOD 4 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0106 and 0206 – MK 25 MOD 0 Canister w/PHS&T:

The MK 25 MOD 0 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the CIPS, Weapon Specification WS-20318, the MK 25 MOD 0 Canister Parameters Document, NAVSEA Drawing No. 7116999, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 25 MOD 0 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Item 0107 and Option Items 0207, 0307, 0407 and 0507 – MK 25 MOD 1 Canister w/PHS&T:

The MK 25 MOD 1 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the CIPS, Weapon Specification WS-20318, the MK 25 MOD 1 Canister Parameters Document, NAVSEA Drawing No. 8408701, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 25 MOD 1 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Item 0108 and Option Items 0208, 0308, 0408 and 0508 – MK 29 MOD 0 Canister w/PHS&T:

The MK 29 MOD 0 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) delivered under this CLIN shall meet the requirements of the CIPS, Weapon Specification WS-20318, the MK 29 MOD 0 Canister Parameters Document, NAVSEA Drawing No. 8407574, and the Statement of Work, Attachment 1. The contractor shall warrant the MK 29 MOD 0 Canisters with PHS&T to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0109, 0209, 0309, 0409, and 0509 – Renewed GFP MK 14 MOD 2 Expended Canisters:

The contractor shall fabricate, construct, assemble, test and deliver MK 14 MOD 2 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) to meet the requirements of the Critical Item Performance Specification (CIPS), Weapon Specification WS-20318, and the MK 14 MOD 2 Canister Parameters Document, and ensure delivered canisters are in accordance with NAVSEA Drawing No. 7251170 and the Statement of Work, Attachment 1.

Attachment 3, Government Furnished Property, will be updated at option exercise and lists material the contractor shall use for renewing MK 14 MOD 2 Canisters under CLINs 0109, 0209, 0309, 0409 and 0509 in accordance with the following:

GOVERNMENT FURNISHED PROPERTY - EXPENDED MK 14 MOD 2 CANISTERS WITH PHS&T

The contractor shall take possession of the EXPENDED MK 14 MOD 2 Canisters, set forth in Attachment 3. Those assets will become the contractor’s property once received and no longer be considered GFP. The expended canisters will be provided in "as is" condition. The contractor will receive enough MK 14 MOD 2 expended assets to fulfill all requirements under these CLINs. The contractor may use components from the expended canister as long as the canister being delivered meets all requirements, including warranty.

Furthermore, the contractor shall be responsible for managing and disposing of any and all material remaining from the EXPENDED MK 14 MOD 2 Canisters not used in building canisters in accordance with all applicable Local, State and Federal laws and regulations. The material being disposed of shall be rendered inoperable for its intended military use. The EXPENDED MK 14 MOD 2 Canisters contain hazardous materials. The contractor is responsible for all costs associated with managing and disposing of these EXPENDED MK 14 MOD 2 Canisters.

Option Items 0110, 0210, 0310, 0410 and 0510 – Renewed GFP MK 13 MOD 0 Expended Canisters:

The contractor shall fabricate, construct, assemble, test and deliver MK 13 MOD 0 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) to meet the requirements of the Critical Item Performance Specification (CIPS), Weapon Specification WS-20318, and the MK 13 MOD 0 Canister Parameters Document, and ensure delivered canisters are in accordance with NAVSEA Drawing No. 7116148, and the Statement of Work, Attachment 1.

Attachment 3, Government Furnished Property, will be updated at option exercise and lists material the contractor shall use for renewing MK 13 MOD 0 Canisters under CLINs 0110, 0210, 0310, 0410 and 0510 in accordance with the following:

GOVERNMENT FURNISHED PROPERTY - EXPENDED MK 13 MOD 0 CANISTERS WITH PHS&T

The contractor shall take possession of the EXPENDED MK 13 MOD 0 Canisters, set forth in Attachment 3. Those assets will become the contractor’s property once received and no longer be considered GFP. The expended canisters will be provided in "as is" condition. The contractor will receive enough MK 13 MOD 0 expended assets to fulfill all requirements under these CLINs. The contractor may use components from the expended canister as long as the canister being delivered meets all requirements, including warranty.

Furthermore, the contractor shall be responsible for managing and disposing of any and all material remaining from the EXPENDED MK 13 MOD 0 Canisters not used in building canisters in accordance with all applicable Local, State and Federal laws and regulations. The material being disposed of shall be rendered inoperable for its intended military use. The EXPENDED MK 13 MOD 0 Canisters contain hazardous materials. The contractor is responsible for all costs associated with managing and disposing of these EXPENDED MK 13 MOD 0 Canisters.

Option Items 0111AA, 0211AA, 0311AA, 0411AA and 0511AA – Renewed GFP MK 25 MOD 0 Expended Canisters:

The contractor shall fabricate, construct, assemble, test and deliver MK 25 MOD 0 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) to meet the requirements of the Critical Item Performance Specification (CIPS), Weapon Specification WS-20318, and the MK 25 MOD 0 Canister Parameters Document, and ensure delivered canisters are in accordance with NAVSEA Drawing No. 7116999, and the Statement of Work, Attachment 1.

Attachment 3, Government Furnished Property, will be updated at option exercise and lists material the contractor shall use for renewing MK 25 MOD 0 Canisters under CLINs 0111AA, 0211AA, 0311AA, 0411AA and 0511AA in accordance with the following:

GOVERNMENT FURNISHED PROPERTY - EXPENDED MK 25 MOD 0 CANISTERS WITH PHS&T

The contractor shall take possession of the EXPENDED MK 25 MOD 0 Canisters, set forth in Attachment 3. Those assets will become the contractor’s property once received and no longer be considered GFP. The expended canisters will be provided in "as is" condition. The contractor will receive enough MK 25 MOD 0 expended assets to fulfill all requirements under these CLINs. The contractor may use components from the expended canister as long as the canister being delivered meets all requirements, including warranty.

Furthermore, the contractor shall be responsible for managing and disposing of any and all material remaining from the EXPENDED MK 25 MOD 0 Canisters not used in building canisters in accordance with all applicable Local, State and Federal laws and regulations. The material being disposed of shall be rendered inoperable for its intended military use. The EXPENDED MK 25 MOD 0 Canisters contain hazardous materials. The contractor is responsible for all costs associated with managing and disposing of these EXPENDED MK 25 MOD 0 Canisters.

Option Items 0311AB, 0411AB and 0511AB – Renewed GFP MK 25 MOD 1 Expended Canister:

The contractor shall fabricate, construct, assemble, test and deliver MK 25 MOD 1 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) to meet the requirements of the Critical Item Performance Specification (CIPS), Weapon Specification WS-20318, and the MK 25 MOD 1 Canister Parameters Document, and ensure delivered canisters are in accordance with NAVSEA Drawing No. 7116999, and the Statement of Work, Attachment 1.

Attachment 3, Government Furnished Property, will be updated at option exercise and lists material the contractor shall use for renewing MK 25 MOD 1 Canisters under CLINs 0311AB, 0411AB and 0511AB in accordance with the following:

GOVERNMENT FURNISHED PROPERTY - EXPENDED MK 25 MOD 1 CANISTERS WITH PHS&T

The contractor shall take possession of the EXPENDED MK 25 MOD 1 Canisters, set forth in Attachment 3. Those assets will become the contractor’s property once received and no longer be considered GFP. The expended canisters will be provided in "as is" condition. The contractor will receive enough MK 25 MOD 1 expended assets to fulfill all requirements under these CLINs. The contractor may use components from the expended canister as long as the canister being delivered meets all requirements, including warranty.

Furthermore, the contractor shall be responsible for managing and disposing of any and all material remaining from the EXPENDED MK 25 MOD 1 Canisters not used in building canisters in accordance with all applicable Local, State and Federal laws and regulations. The material being disposed of shall be rendered inoperable for its intended military use. The EXPENDED MK 25 MOD 1 Canisters contain hazardous materials. The contractor is responsible for all costs associated with managing and disposing of these EXPENDED MK 25 MOD 1 Canisters.

Option Items 0112AA, 0212AA, 0312AA, 0412AA and 0512AA – Renewed GFP MK 21 MOD 2 Expended Canisters:

The contractor shall fabricate, construct, assemble, test and deliver MK 21 MOD 2 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) to meet the requirements of the Critical Item Performance Specification (CIPS), Weapon Specification WS-20318, and the MK 21 MOD 2 Canister Parameters Documents, and ensure delivered canisters are in accordance with NAVSEA Drawing No. 8240134, 8240134 and the Statement of Work, Attachment 1.

Attachment 3, Government Furnished Property, will be updated at option exercise and lists material the contractor shall use for renewing MK 21 MOD 2 Canisters under CLINs 0112AA, 0212AA, 0312AA, 0412AA, and 0512AA in accordance with the following:

GOVERNMENT FURNISHED PROPERTY - EXPENDED MK 21 MOD 2 CANISTERS WITH PHS&T

The contractor shall take possession of the EXPENDED MK 21 MOD 2 Canisters, set forth in Attachment 3. Those assets will become the contractor’s property once received and no longer be considered GFP. The expended canisters will be provided in "as is" condition. The contractor will receive enough MK 21 MOD 2 expended assets to fulfill all requirements under these CLINs. The contractor may use components from the expended canister as long as the canister being delivered meets all requirements, including warranty.

Furthermore, the contractor shall be responsible for managing and disposing of any and all material remaining from the EXPENDED MK 21 MOD 2 Canisters not used in building canisters in accordance with all applicable Local, State and Federal laws and regulations. The material being disposed of shall be rendered inoperable for its intended military use. The EXPENDED MK 21 MOD 2 Canisters contain hazardous materials. The contractor is responsible for all costs associated with managing and disposing of these EXPENDED MK 21 MOD 2 Canisters.

Option Items 0112AB, 0212AB, 0312AB, 0412AB and 0512AB – Renewed GFP MK 21 MOD 3 Expended Canisters:

The contractor shall fabricate, construct, assemble, test and deliver MK 21 MOD 3 Canisters with Packaging, Handling, Storage and Transportation (PHS&T) to meet the requirements of the Critical Item Performance Specification (CIPS), Weapon Specification WS-20318, and the MK 21 MOD 3 Canister Parameters Documents, and ensure delivered canisters are in accordance with NAVSEA Drawing No. 8240134, 8240134 and the Statement of Work, Attachment 1.

Attachment 3, Government Furnished Property, will be updated at option exercise and lists material the contractor shall use for renewing MK 21 MOD 3 Canisters under CLINs 0112AB, 0212AB, 0312AB, 0412AB, and 0512AB in accordance with the following:

GOVERNMENT FURNISHED PROPERTY - EXPENDED MK 21 MOD 3 CANISTERS WITH PHS&T

The contractor shall take possession of the EXPENDED MK 21 MOD 3 Canisters, set forth in Attachment 3. Those assets will become the contractor’s property once received and no longer be considered GFP. The expended canisters will be provided in "as is" condition. The contractor will receive enough MK 21 MOD 3 expended assets to fulfill all requirements under these CLINs. The contractor may use components from the expended canister as long as the canister being delivered meets all requirements, including warranty.

Furthermore, the contractor shall be responsible for managing and disposing of any and all material remaining from the EXPENDED MK 21 MOD 3 Canisters not used in building canisters in accordance with all applicable Local, State and Federal laws and regulations. The material being disposed of shall be rendered inoperable for its intended military use. The EXPENDED MK 21 MOD 3 Canisters contain hazardous materials. The contractor is responsible for all costs associated with managing and disposing of these EXPENDED MK 21 MOD 3 Canisters.

Item 0113 and Option Items 0213, 0313, 0413, and 0513 – Coding Plug Assemblies:

The contractor shall fabricate, construct, assemble, test and deliver coding plug assemblies for each MK 13 MOD 0, MK 14 MOD 2, MK 15 MOD 1, MK 21 MOD 2, MK 21 MOD 3, MK 21 MOD 4 and MK 29 MOD 0 Canister in accordance with NAVSEA Drawing No. 6264000-19 and the Statement of Work, Attachment 1. The contractor shall warrant the coding plug assemblies to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Item 0119 and Option Items 0219, 0319, 0419, and 0519 – Coding Plug Assemblies:

The contractor shall fabricate, construct, assemble, test and deliver coding plug assemblies for each MK 25 MOD 0 and MK 25 MOD 1 Canister in accordance with NAVSEA Drawing No. 7117132 and the Statement of Work, Attachment 1. The contractor shall warrant the coding plug assemblies to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0124, 0224, 0324, 0424, and 0524 – MK 7 MOD 0 Explosive Bolt:

The contractor shall fabricate, construct, assemble, test and deliver MK 7 MOD 0 Explosive Bolts for each MK 21 MOD 2, MK 21 MOD 3, MK 21 MOD 4 and MK 29 MOD 0 Canister in accordance with NAVSEA Drawing No. 6261661 and the Statement of Work, Attachment 1. The contractor shall warrant the MK 7 MOD 0 Explosive Bolts to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for one year from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0125, 0225, 0325, 0425, and 0525 – MK 236 MOD 1 Impulse Cartridge Assembly:

The contractor shall fabricate, construct, assemble, test and deliver MK 236 MOD 1 Impulse Cartridge Assemblies for each MK 21 MOD 2, MK 21 MOD 3, MK 21 MOD 4 and MK 29 MOD 0 Canister in accordance with NAVSEA Drawing No. 7546126-1 and the Statement of Work, Attachment 1. The contractor shall warrant the MK 236 MOD 1 Impulse Cartridge Assemblies to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for one year from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Item 0126 and Option Items 0226, 0326, 0426 and 0526 - MK 8 MOD 0 Explosive Bolt:

The contractor shall fabricate, construct, assemble, test and deliver each lot of 4 MK 8 MOD 0 Explosive Bolts for MK 25 MOD 0 and MK 25 MOD 1 Canisters in accordance with NAVSEA Drawing No. 6784421 and the Statement of Work, Attachment 1. The contractor shall warrant the MK 8 MOD 0 Explosive Bolts to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for five years from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0127AA, 0227AA, 0327AA, 0427AA, and 0527AA – MK 41 Vertical Launching System Canister Spares

The contractor shall fabricate, construct, assemble, test and deliver MK 41 VLS Spares in accordance with Attachment 18 hereto and the Statement of Work, Attachment 1. The contractor shall warrant the MK 41 VLS Spares to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for one year from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Items 0127AB, 0227AB, 0327AB, 0427AB, and 0527AB – MK 41 Vertical Launching System Canister Spares for Missile Recertification

The contractor shall fabricate, construct, assemble, test and deliver MK 41 VLS Spares in accordance with Attachment 19 hereto and the Statement of Work, Attachment 1. The contractor shall warrant the MK 41 VLS Spares to conform to these design, manufacturing, and performance requirements, and to be free from defects in material and workmanship for one year from date of acceptance, as described in Warranty Tracking Information, Attachment 10.

Option Item 0128 – Preliminary and Final Production Readiness Reviews

The Government will conduct a single Preliminary Production Readiness Review and a single Final Production Readiness Review, as described and scheduled in Statement of Work, Attachment 1 Section 5.0. The contractor shall provide engineering, technical, administrative, and management support for these reviews.

Option Item 0129 – Aft Closure First Article Test

The contractor shall plan, conduct, and report the results of Aft Closure First Article Tests, as described in Statement of Work, Attachment 1 Section 7.0 and 7.1.

Option Items 0130, 0230, 0330, 0430 and 0530 – MK 13 MOD 0 Physical Configuration Audit

The Government will perform a Physical Configuration Audit (PCA) of the first MK 13 MOD 0 canister assembly with PHS&T built by the contractor, as described in the Statement of Work, Attachment 1 Section 6.0.

The contractor shall provide qualified engineering, technical, manufacturing, administrative, management and other support as necessary for this Government audit. The contractor shall provide a work area, materials, documentation, and reporting as described in the Statement of Work, Attachment 1 Section 6.0.

Option Item 0131 – MK 13 MOD 0 Forward Closure First Artic

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .