Note: In accordance with RFP Section L, Paragraph 1.0 Introduction, the Government may not answer questions submitted after 17 December 2018. Offerors are encouraged to continue to submit questions so the Government may prepare a response during discussions, if discussions are held. Offerors shall not expect the Government to provide answers to questions prior to the proposal submission date for questions submitted after 17 December 2018.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q&A 3
| Q&A # 3 |
| The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation. Answsers will be provided in the order they are received. A Q&A # that has been skipped indicates that a response is still pending. |
| DATE: | Friday, December 21, 2018 | |
| HULLS/TITLE: | LPD 23 USS ANCHORAGE | |
| SOLICITATION NO: | N00024-19-R-4411 | |
| NAVSEA POCs: | Steve Galer |
Colin Gallagher NAVSEA POC E-MAIL: steven.galer@navy.mil colin.j.gallagher@navy.mil NAVSEA POC #: Steve Galer: 202-781-2873 Colin Gallagher: 202-781-3450
| QUESTION #/ DETAILS | QUESTION/ ANSWER | |||||
| Q&A # | Question Area | ITEM NO: | PARA # | Contractor Question | Government Response | FBO Q&A # |
| 21 | GFP | 1.8.2 | RFP Amendment 0001 issued 11/27/18, Page 45 Para 1.8.2: GOVERNMENT FURNISHED MATERIAL (GFM): This RFP provision includes the following Contractor requirements. The contractor is to coordinate and pickup TYCOM Government Furnished Material from the Naval Base with the Project Manager. This GFM will be available at A-30 from one building on the Naval Base. Contractor shall develop pickup schedule accordingly. Transportation costs shall be included in the contract. |
The requirement to coordinate and pickup TYCOM GFM is ambiguous and introduces financial risk and estimating challenges with respect to preparing the required fixed price proposal.
To facilitate proposal preparation and cost estimating efforts, Contractor request that clarification regarding the volume of GFM, quantities of crates, boxes, pallets, sizes and weights. Contractor also needs to know if the GFM will be available for pickup from San Diego Naval Base 32nd street.
CONTRACTOR QUESTION:
For bidding purpose, will the Government provide quantity of crates, boxes, pallets, sizes and weights and confirm which Naval Base?
| The Government will not provide quantity of crates, boxes, pallets, sizes, and weights. All work items that delineate anything BUT '90' in the 4th and 5th digit of the work item (XXX-31-XXX for example) indicate the GFM is TYCOM. The GFM will be picked up from San Diego Naval Base 32nd Street. | |||
| 23 | |||
| 22 | Work Item | 631-11-001 (E1) | 3.1 |
Basic work specification (631-11-001) Para 3.1: Directed the contractor to remove each lower level deck plate.
CONTRACTOR QUESTION:
Will Government please specify the correct amount of deck plates to be removed?
| The Government has included the drawing in ERRATA 2 which delineates how many deck plates need to be removed. | 24 | |||
| 23 | Work Item | 982-31-001 992-11-002 | 3.2.2 3.2 | Work Item 982-31-001 |
Para 3.2.2 Provide a licensed marine pilot and tugs to assist the ship during move to and from repair facility, to and from the outer limits of the harbor to conduct sea trial. Each tug shall have a minimum of 1,200 shaft horsepower.
Work Item 992-11-002 Para 3.2 Provide a licensed marine pilot and tugboat(s), capable of safely moving the ship to and from pier side position and to and from the outer limits of the harbor to the contractor's repair facility, for acceptance of tow, or to where the ship may operate under its own power and to and from the pier or drydock for sea trials.
Will the Government issue an Amendment removing the duplication of effort for sea trials?
| Work item: 982-31-001 is for sea trials. Work item 992-11-002 is for transit from Goverment pier side to repair facility and back to Government pier side. The Government does not percieve a duplication of effort because each work item serves a different purpose. | 25 | |||
| 24 | Work Item | 314-90-001 (E1) | 3.14 3.14.1 3.14.2 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17- 82249K, Uninterrupted Power Supply (UPS); Reduction, Alteration Installation Team (AIT) Support Service; accomplish and provide |
Para 3.14 Services shall:
Para 3.14.1 Be installed not later than 5 business days to commencement of production start date. (See Note 4.1) Para 3.14.2 Be provided for the duration of the availability. Earlier removal if required prior to end of availability, will be when directed by the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be Monday through Saturday.
4.1.1 Production Start Date: 08/12/19
4.1.2 Production Completion Date: 02/08/20
4.1.3 Testing Start Date: 01/10/20.
4.1.4 Testing Completion Date: 03/09/20.
CONTRACTOR QUESTION:
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 08/07/19 to 03/09/20?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 26 | |||
| 25 | Work Item | 441-90-002 | 3.10 3.10.1 3.10.2 4.1 | Title: Ship Alt LPD17-SA 80897K, Navy Multiband Terminal (NMT) AN/WSC-9(V)XX Q/KA/X/GBS Terminal Installation, Alteration Installation Team (AIT) Support Services; provide |
Para 3.10 Services shall:
Para 3.10.1 Be installed when directed by the SPAWAR OSIC via the SUPERVISOR.
Para 3.10.2 Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SPAWAR OSIC via the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 06:00-16:30 Monday through Saturday.
The contractor is unable to estimate the duration of temporary services needed. How many days and over what durations will temporary services be needed to support AIT requirements of this work item?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 27 | |||
| 26 | Work Item | 664-90-001 (E1) | 3.11 3.11.1 3.11.2 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17-87656K, Damage Control Management Software {DCAMS) and Advanced Damage Control System (ADCS) Hardware Tech Refresh, Alteration Installation Team (AIT) Support; accomplish |
Para 3.11 Services shall:
Para 3.11.1 Be installed not later than 5 business days prior to commencement of production start date. (See Note 4.1.1) Para 3.11.2 Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 0700-1700 Monday through Saturday.
Para 4.1.1 Production Start Date: 01/13/2020 Para 4.1.2 Production Completion Date: 03/19/2020 Para 4.1.3 Testing Start Date (ALO): 3/19/2020 Para 4.1.4 Testing Completion Date: 3/26/2020
CONTRACTOR QUESTION:
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 01/08/20 to 03/26/20?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 28 | |||
| 27 | Work Item | 772-90-002 | 3.5 3.5.1 3.5.2 4.1 | Title: Ship Alt LPD23-82544K, Cargo Weapons Elevator (CWE) Number One and Number 2 Door and Ramp Assembly, Alteration Installation Team (AIT)Support Service; provide |
Para 3.5 Services shall:
Para 3.5.1 Be installed not later than 5 business days after start of the availability.
Para 3.5.2 Be provided for the duration of the availability. Earlier removal, if required prior to end of availability, will be when directed by the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 06:00-16:30 Monday through Saturday.
CONTRACTOR QUESTION:
The contractor is unable to estimate the duration of temporary services needed. How many days and over what durations will temporary services be needed to support AIT requirements of this work item?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 29 | |||
| 28 | Work Item | 980-90-014 (E1) | 3.15 3.15.1 3.15.2 4.2 4.2.1 4.2.2 4.2.3 4.2.4 | Title: Ship Alt LPD17- 834 00K, Circuit ~27TV/Surveillance, LPD17 Class Backfit, Alteration Installation Team (AIT) |
Support Service ; provide Para 3.15 Services must:
Para 3.15.1 Be installed not later than 5 business days prior to commencement of production start date. (See Note 4.2.1) Para 3.15.2 Be provided until completion of inport testing. Earlier removal. if required, will be when directed by the SUPERVISOR.
Para 4.2 Regular day shift working hours for the AIT will be 0700-1 600 Monday through Friday.
Para 4.2.1 Production Start Date: 07/08/2019 Para 4.2.2 Production Completion Date: 03/03/2020 Para 4.2.3 Testing Start Date: 03/04/2020 Para 4.2.4 Testing Completion Date: 03/27/2020
CONTRACTOR QUESTION: The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 07/03/19 to 07/27/20.
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 30 | |||
| 29 | Work Item | 980-90-010 | 3.6 3.6.1 3.6.2 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17-81400K, Battle Force Tactical Trainer (BFTT) Hardware 4.2 Upgrade, Alteration Installation Team (AIT) Support Service; accomplish (OPTION ITEM) |
Para 3.6 Services shall:
Para 3.6.1 Be installed not later than 5 business days prior to commencement of production start date (See 4.1.1).
Para 3.6.2 Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 8 working hours Monday through Friday.
Para 4.1.1 Production Start Date: 12/10/2019 Para 4.1.2 Production Completion Date: 03/04/2020 Para 4.1.3 Testing Start Date: TBD Para 4.1.4 Testing Completion Date: TBD
CONTRACTOR QUESTION:
1) The contractor is unable to estimate the duration of temporary services needed. Para 3.6.2 States services will be required until completion of inport testing, But Para 4.1.4 states the testing completion date is “To Be Determined”. When will testing be completed?
2) The contractor request confirmation, will the AIT require temporary services be provided IAW the specification from 12/05/19 to (answer from above question)?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 31 | |||
| 30 | Work Item | 980-90-008 (E1) | 3.5 3.5.1 3.5.2 4.3 | Title: Ship Alt LPD17-85076K HM&E Network Mesh Implementation; provide |
Para 3.5 Services shall:
Para 3.5.1 Be installed not later than 5 business days after start of the availability.
Para 3.5.2 Be provided for the duration of the availability. Earlier removal, if required prior to end of availability, will be when directed by the SUPERVISOR.
Para 4.3 Production Start Date: 09/8/2019 Production Completion Date: 02/30/2020 Testing Start Date: TBD Testing Completion Date: TBD
CONTRACTOR QUESTION:
1) The contractor is unable to estimate the duration of temporary services needed. Para 356.2 States services will be required until end of availability, But Para 4.3 states the testing completion date is “To Be Determined”. When will testing be completed?
2) The contractor request confirmation, will the AIT require temporary services be provided IAW the specification from 09/03/19 to (answer from above question)?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 32 | |||
| 32 | Work Item | 980-90-006 | 3.7 3.7.1 3.7.2 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17-86669K, CIDS (23TV) Hardware and Software V5.1 Upgrade, Alteration Installation Team (AIT) Support Service; provide |
Para 3.7 Services shall:
Para 3.7.1 Be installed not later than 5 business days prior to commencement of production start date.
Para 3.7.2. Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 7am-4pm Monday through Friday.
Para 4.1.1 Production Start Date: 08/08/2019 Para 4.1.2 Production Completion Date: 10/18/2019 Para 4.1.3 Testing Start Date: TBD Para 4.1.4 Testing Completion Date: TBD
CONTRACTOR QUESTION:
1) The contractor is unable to estimate the duration of temporary services needed. Para 3.7.2 States services will be required until completion of inport testing, But Para 4.1.4 states the testing completion date is “To Be Determined”. When will testing be completed?
2) The contractor request confirmation, will the AIT require temporary services be provided IAW the specification from 08/03/19 to (answer from above question)?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 33 | |||
| 33 | Work Item | 980-90-005 | 3.10 3.10.1 3.10.2 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17-86908K, Cargo Weapons Elevator (CWE) and Dumbwaiter Call Signal Station Modification, Alteration Installation Team (AIT) Support Service; provide |
Para 3.10 Services shall:
Para 3.10.1 Be installed not later than 5 business after the start of the availability.
Para 3.10.2 Be provided for the duration of the availability as directed by the SUPERVISOR.
Para 4.1, Regular day shift working hours for the AIT will be 0600-1630 Monday through Saturday.
Para 4.1.1 Production Start Date: 02/03/2020 Para 4.1.2 Production Completion Date: 04/10/2020 Para 4.1.3 Testing Start Date: 04/13/2020 Para 4.1.4 Testing Completion Date: 04/24/2020
CONTRACTOR QUESTION:
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 01/30/20 to 04/24/20.
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 34 | |||
| 34 | Work Item | 980-90-004 | 3.8 3.8.1 3.8.2 | Title: Ship Alt LPD17-78304K Remove AN/SPS-48E BFTT TSSS, Alteration Installation Team (AIT) Support Service; provide |
Para 3.8 Services shall:
Para 3.8.1 Be installed not later than 5 business days prior to commencement of production start date. (See Note 4.1.1) Para 3.8.2 Be provided until completion of inport testing (see Para 4.1.4). Earlier removal, if required, will be when directed by the SUPERVISOR.
Para 4.1 None, CONTRACTOR QUESTION:
Will the Government issue an Amendment and provide Para 4.1.1 through Para 4.1.4?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 35 | |||
| 35 | Work Item | 980-90-003 | 3.11 3.11.1 3.11.2 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17-70678K, AN/SPS-48G Upgrade, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM) |
Para 3.11 Services shall:
Para 3.11.1 Be installed not later than 5 business days prior to commencement of production start date. (See Note 4.1.1) Para 3.11.2 Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 0600-1800 Monday through Saturday.
4.1.1 Production Start Date: 08 July, 2019
4.1.2 Production Completion Date: 17 July 2020
4.1.3 Testing Start Date: 23 March 2020.
4.1.4 Testing Completion Date: 17July 2020.
CONTRACTOR QUESTION:
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 07/03/19 to 07/17/20.
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 36 | |||
| 36 | Work Item | 980-90-001 | 3.8 3.8.1 3.8.2 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17-82770K, Digital Rudder Angle Display System (DRADIS), Alteration Installation Team (AIT) Support Service; provide |
Para 3.8 Services shall:
Para 3.8.1 Be installed not later than 5 business days prior to commencement of production start date. (See Note 4.1.1) Para 3.8.2 Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 0600-1800 Monday through Saturday.
4.1.1 Production Start Date: 22 July, 2019
4.1.2 Production Completion Date: 27 March 2020
4.1.3 Testing Start Date: 30 March 2020.
4.1.4 Testing Completion Date: 27 April 2020.
CONTRACTOR QUESTION:
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 07/17/19 to 04/27/20?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 37 | |||
| 37 | Work Item | 980-90-019 (E1) | 3.7 3.7.1 3.7.2 4.3 | Ship Alt; LPD17-90783K 1 SSDS MK 2 Install to MOD (El) C Baseline, Alteration; Installation Team (AIT) Support Service; accomplish and provide. |
Para 3.7 Services shall:
Para 3.7.1 Be installed not later than 5 business days prior to commencement of production start date. (See Note 4.3) Para 3.7.2 Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the SUPERVISOR.
Para 4.3 Production Start Date: 07/08/2019 Production Completion Date: 03/22/2020 Testing Start Date: 03/23/2020 Testing Completion Date: 07/07/2020
CONTRACTOR QUESTION:
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 07/03/19 to 07/07/20.
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 38 | |||
| 38 | Work Item | 980-90-018 (E1) | 3.9 3.9.1 3.9.2 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Title: Ship Alt LPD17- 80032K, AN/USG-2 Upgrade to AN/USG2B Installation ; Alteration Installation Team (AIT) Support Service; |
accomplish and provide
Para 3.9 Services must:
Para 3. 9.1 Be installed not later than 5 business days prior to commencement of production start date (See Note 4.1.1).
Para 3. 9.2 Be provided until completion of inport testing. Earlier removal, if required will be when directed by the OSIC via the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 0700-1700, Monday-Saturday Para 4.1.1 Production Start Date: 07/29/19 Para 4.1.2 Production Completion Date: 01/05/20 Para 4.1.3 Testing Start Date: 02/13/20 Para 4.1.4 Testing Completion Date : 07/17/20
CONTRACTOR QUESTION:
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 07/24/19 to 07/17/20.
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 39 | |||
| 39 | Work Item | 980-90-016 (E1) | 3.17.1 3.17.2 4.1 4.1 4.1.1 4.1.2 4.1.3 4.1.4 | Ship Alt LPD17-86679K, SWAN Removal, Alteration Installation Team (AIT) Support Service; provide. |
Para 3.17.1 Be installed not later than 5 business days prior to commencement of production start date (See 4.1.1).
Para 3.17.2 Be provided until completion of inport testing. Earlier removal, if required, will be when directed by the OSIC via the SUPERVISOR.
Para 4.1 Regular day shift working hours for the AIT will be 0700-1600, Para 4.1.1 Production Start Date: 07/08/19 Para 4.1.2 Production Completion Date: 02/17/2020 Para 4.1.3 Testing Start Date: TBD Para 4.1.4 Testing Completion Date: TBD
CONTRACTOR QUESTION:
1) The contractor is unable to estimate the duration of temporary services needed. Para 3.17.2 states that services will be required until completion of inport testing, But Para 4.1.3 states that the testing completion date is “To Be Determined”. When will testing be completed?
2) The contractor request confirmation will the AIT require temporary services be provided IAW the specification from 07/03/19 to (answer from above question)?
| ERRATA 2 clarifies the number of days needed to support AIT requirements | 40 | |||
| 41 | Work Item | 589-11-004 | 3.1.2 5 5.1 | Title: Knuckleboom Crane Wire Rope; replace |
Para 3.1.2 Receive wire rope assembly listed in 5.1 from Ship's Force via the SUPERVISOR.
Para 3.1.2 Receive wire rope assembly listed in 5.1 from Ship's Force via the SUPERVISOR
Para 5. GOVERNMENT FURNISHED MATERIAL (GFM):
Para 5.1 LLTM:
1. None.
1) Will the Government confirm wire rope shall be provided as GFM?
| 2) Will the Government provide a point of contact including contact information? | ERRATA 4 will provide clarity on GFM. The SUPERVISOR POC will be provided upon award of the contract. | 41 | |||
| 40 | Work Item | 584-21-003 | 3.4.7 | Paragraph 3.4.7 of specification sates to accomplish electroplating of each piston rod in accordance with 2.4, MIL-STD-2197, Brush Electroplating on Marine Machinery. Contractor notes local source to accomplish is unknown. |
Contractor shall price Industrial Hard Chrome and precision grinding in lieu of MIL-STD-2197.
CONTRACTOR QUESTION:
Will the Government issue an Amendment and delete the requirements of MIL-STD-2197, Brush Electroplating on Marine Machinery?
| The Government does not intend to delete requirements of MIL-STD-2197 and the offeror shall propose accordingly. Refer to the tech manual for a known source. | 42 | |||
| 44 | Work Item | 980-90-018 (E1) 980-90-019 (E1) | 2.3 2.4 | Work Item 980-90-018 (El) Title: Ship Alt LPD17- 80032K, AN/USG-2 Upgrade to AN/USG2B Installation ; Alteration Installation Team (AIT) Support Service; accomplish and provide |
Work Item 980-90-019 (E1) Title : Ship Alt LPD17 90783K; LPD17-90783K 1 SSDS MK 2 Install to MOD C Baseline, M'B--Alteration Class; Installation Team (AIT) Support Service; accomplish and provide
Work Item 980-90-018 (E1) Para 2.4 512-8675164 and Para 2.5 622-8675251. Missing from CD.
Work item 980-90-019 (E1) Para 2.3 512-8674672 and Para 2.8 640-8674675. Missing from CD.
Will the Government provide the four missing references listed above?
| Reference CD avaiable for pickup. Please contact Kelli Cox (kelli.cox@navy.mil) | 43 | |||
| 45 | Work Item | 980-90-014 (E1) 980-90-017 | 2.17 2.2 3.2.2 4.1 | Work Item 980-90-014 (E l) Title: Ship Alt LPD17- 83400K, Circuit ~27TV/Surveillance, LPD17 Class Backfit 1 Alteration Installation Team (AIT) Support Service ; provide |
Para 4.1 Kitted material in 2.17 and 5.3 will be provided by the AIT.
Para 2.17 4720-LPD23-FY19 Rev 6, Ship Alteration Material Summary (4720/3). Contractor has not received Rev-6.
Work Item 980-90-017 Title: Ship Alt LPD17-OA-93234 MK19 MOD 1 Loader Beam Upgrade; provide
Para 3.2.2 Forklift will be provided to accomplish weight movements as need to accomplish weight test accomplished in 3.2 in accordance with 2.2.
Para 2.2 MRC 7211/R53 36M-1, ORDANCE equipment weight test, RAM Launcher Load Test. Contractor has not received.
CONTRACTOR QUESTION:
Will the Government provide the two missing references listed above for work items 980-90-014 (E1) and 980-90-017?
| Reference CD avaiable for pickup. Please contact Kelli Cox (kelli.cox@navy.mil) | 44 | |||
| 46 | Work Item | 980-90-015 (E1) | 3.1 | Work Item 980-90-015 (E1) Title: Ship Alt LPD17 85076K LPD17-85307K Indoor Simulated Markmanship Trainer (ISMT) Installation; |
3 .1 Accomplish the requirements of 2.2 through 2 .7 Contractor notes References 2.2 through 2.7 were not provided with Errata 1.
CONTRACTOR QUESTION:
Will the Government provide References Para 2.2 through 2.7?
| Reference CD avaiable for pickup. Please contact Kelli Cox (kelli.cox@navy.mil) | 45 | ||
| 42 | Work Item | 584-21-001 | Title: Lower Stern Gate Retainer Angle and Gasket; replace |
References: PPI-004 and Q&A #1.
Q&A #1 received on 12/07/18 States: Work item 584-21-001 (A1) is in the original work specification package. Contractor concurs.
PPI-004 informed the Government that 584-21-001 was not listed on the J-4 provided in the RFP. PPI-004 was also submitted to inform the Government that it is not found on the original index.
In order to include a price for the work item the Government will need to provide a revised J-4.
CONTRACTOR QUESTION:
Will the Government provide a revised J-4 that includes work item 584-21-001?
| WI 584-21-001 has been added to the J-4. | 46 | ||
| 31 | Work Item | 980-90-007 | 3.9 3.9.1 3.9.2 |
Title: Ship Alt LPD17-86222K, Next Generation Fathometer (NGF) Backfit Phase I, Alteration Installation Team (AIT) Support Service; provide (OPTION ITEM)
Para 3.9 Services shall:
Para 3.9.1 Be installed 5 business days after start of availability, as designated by the SUPERVISOR.
Para 3.9.2 Be provided for the duration of the availability. Earlier removal, if required, prior to the end of the availability, will be when directed by the SUPERVISOR.
The contractor requests confirmation, will the AIT require temporary services be provided IAW the specification from 07/13/19 to 07/17/20.
| ERRATA 3 clarifies the specification. | 47 | |||
| 43 | Work Item | 474-11-001 | 1.3.1 1.3.2 1.3.3 1.3.4 | Paragraph 3.1 States: Remove existing and install new each MK 137 Decoy Launcher ablative pad assembly listed in 1.3 and located in 1.2, using 2.2 and 2.3 for guidance and in accordance with Paragraph 8.9 of 2.4. |
Paragraph 1.3.1 States: Quantity (One EA), Ablative Pad Assembly, Items 7, 11, and 12, Sheet 8G of 2.2
Paragraph 1.3.2 States: Quantity (One EA), Ablative Pad Assembly, Items 6, 9, and 10, Sheet 8H of 2.2
Paragraph 1.3.3 States: Quantity (One EA), Ablative Pad Assembly, Items 8, 9, and 10, Sheet 8A of 2.3
Paragraph 1.3.4 States: Quantity (One EA), Ablative Pad Assembly, Items 8, 9, and 10, Sheet 8B of 2.3
Problem, Paragraph 1.3.1 Items 7, 11, and 12, are not shown on Sheet 8G of 2.2
Problem, Paragraph 1.3.2 Items 6, 9, and 10, are not shown on Sheet 8H of 2.2
Problem, Paragraph 1.3.3 Items 8, 9, and 10, are not shown on Sheet 8A of 2.3
Problem, Paragraph 1.3.4 Items 8, 9, and 10, are not shown on Sheet 8B of 2.3
CONTRACTOR QUESTION:
Will the Government provide corrected references for Para 2.2 and 2.3 showing Ablative Pad Assemblies?
| ERRATA 3 reflects correct references. | 48 | |||
| 47 | Work Item | 622-12-003 (E1) | 3.1.1 | Paragraph 3.1.1 States: Remove each existing and install new gasket, o-ring, pin, key, stud, bolt, and nut. Material shall conform to specifications in Part List of 2.2. |
The material identified in paragraph 3.1.1, new gasket, o-ring, pin, key, stud, bolt, and nut. Are not identified by a part number or a location on reference 2.2
CONTRACTOR QUESTION:
Will the Government provide clarification for quantities, sizes, types, descriptions or part numbers for material called out in Para 3.1.1?
| ERRATA 3 provides clarification of paragraph 3.1.1. | 49 | |
| 48 | Work Item | 472-90-001 |
Reference: 2.9 (470-8674002 Rev. A) Item No. 5, UNIT, DISPLAY CONVERTER, additional SPEC is needed i.e. Material Spec and manufacture info/details.
Review of DETAIL 10-D on SH # 2, Item No. 5 is enclosed or boxed-in with Item No.6, CONSOLE, DATA DISPLAY GROUP.
CONTRACTOR QUESTION:
• Is Item No. 5 included or part of Item No.6?
• Is Item No.5 GFM and included in the Kit for SA?
• If not, will the Government provide Manufacturer and Manufacturer’s part number?
| Government has confirmed that Item No.5 (Display Converter, CV-4443/U), is part of Item No. 6 (Console, Data Display Group (CDS), OJ-827(V)1/U) and both are GFM. | 50 | ||
| 49 | Work Item | 980-90-018 (E1) | 3.6 |
Paragraph 3.6 States: Accomplish the requirements of 2.4 through 2.5.
- 2.4 512-8675164, ShipAlt LPD17-80032K HVAC Sys Mod
- 2.5 622-8675251, ShipAlt LPD17-80032K AN/USG-2 to AN/USG-2B Upgrade Mod false Deck
Will the Government provide the references listed?
| Reference CD avaiable for pickup. Please contact Kelli Cox (kelli.cox@navy.mil) | 51 | |||
| 50 | Work Item | 980-90-019 (E1) | 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 | Paragraph 3.19 States: Accomplish the requirements of 2.3 through 2.10. |
- 2.3 512-8674672, ShipAlt LPD17-90783K HVAC Sys Mod
- 2.4 514-8675038, ShipAlt LPD17-90783K Chilled Water Sys Mod
- 2.5 528-8675039, ShipAlt LPD17-90783K Sanitary & Sewage Sys Mod
- 2.6 551-8675040, ShipAlt LPD17-90783K Vital Air Sys Mod
- 2.7 555-8674673, ShipAlt LPD17-90783K Fire Extinguisher Sys Mod
- 2.8 640-8674675, ShipAlt LPD17-90783K SSDS MK 2 Install to Mod C Baseline-LPD Class Mod to Furniture
- 2.9 184-8674664, ShipAlt LPD17-90783K SSDS MK 2 Install to Mod C Baseline-LPD Class Mod to Fdn CIC Unattended 02-39-0-Q
- 2.10 401-8674668, ShipAlt LPD17-90783K Mod to Arr
CONTRACTOR QUESTION:
Will the Government provide the references listed?
| Reference CD avaiable for pickup. Please contact Kelli Cox (kelli.cox@navy.mil) | 52 | |||
| 51 | Work Item | 514-21-001 | 3.6.6.1 | CONTRACTOR QUESTION: |
Item nr 514-21-001 askes to quote, fit and install Kit, shaft seal replacement (377-15911-004) but also askes to replace a GFM seal carbon, low speed shaft (029-21722B000) and another Seal carbon low speed shaft (029-21722B000). The seal carbon seals listed are normally provided in the shaft seal replacement kit. Are you wanting us to replace the shaft seal with a kit, by removing the old shaft seal and installing a whole new seal? Or rebuild the shaft seal? If we order the shaft seal kit, we don’t need the GFM seal carbon low speed shaft parts.
Parts are also called out to rebuild the VGD assembly just please note that if any parts not on the list need replaced, we will have to submit a CFR. Typically, if the VGD is needing rebuilt the nozzle base plate (064-48765-D000) needs to also be replaced as the ball bearings create wear to the casting. The nozzle base plate is not on the list but the ball bearings are (029-21728-000) Is the navy wanting to rebuild the VGD or replace using the VGD rebuild kit?
| ERRATA 2 canceled Work Item 514-21-001 | 14 | |||
| 52 | Work Item | 332-90-001 | 3.1 | Para 3.1 Accomplish the requirements of 2.2 through 2.4. |
Reference: 2.4 (331-8674924)
Item No. 0003, 365 feet of cable type LSE3CI-4 Item No. 0004, 330 feet of cable type LSE7CI-4
Contractor is unable to locate the cable (Items 0003 and 0004) in the required lengths. Contractor’s vendors and the manufacture have informed us of a minimum purchase of 3000 feet for each cable type.
Will the Government provided as GFM?
ERRATA 6 clarifies the Government will provide GFM for Item No. 0003, 365 feet of cable type LSE3CI-4 and Item No. 0004, 330 feet of cable type LSE7CI-4. 15 image1.jpg