J-1 - Contract Data Requirements List, DD Form 1423 Exhibit A.pdf
PDF 4 MB Posted
- Solicitation number
- N00024-19-R-2320
About this file
This document contains a Contract Data Requirements List (CDRL) for the Post Shakedown Availability (PSA) execution on nine Freedom Variant Littoral Combat Ships in Mayport, Florida. The CDRL requires the contractor to submit various technical reports, plans, schedules, and cost reports during the PSA period of performance. Required submissions include a funds and man-hours expenditure report, a weekly manning forecast, an earned value management report, test plans, trial reports, cost proposals, problem identification reports, adverse environmental conditions and plant protection plans, a quality plan, and an integrated master schedule. Submissions are due on a one-time, monthly, biweekly, or weekly basis beginning 30 days after contract award through 90 days after the period of performance. The Naval Sea Systems Command will be the requiring office for all submissions.
Not Listed
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA REQUIREMENTS LIST
GENERAL DD FORM 1423 GLOSSARY AND DATA DELIVERABLES
TABLE
FOR EXHIBIT A
"BLOCK 1" - See DoD FAR Supplement Subpart 4.71 for proper numbering.
"BLOCK 2" -TITLE - As it appears on data acquisition document cited in Block 4.
"BLOCK 3" - SUBTITLE - Further definition of data item (optional entry) .
"BLOCK 4" - DATA ITEM DESCRIPTION (DID) - Number, military specification number, or military standard number listed in DoD 5010.12-L (AMSDL), or one-time DID number, that defines data content and format requirements . DID is identified for guidance.
"BLOCK 5" - CONTRACT REFERENCE - Reference to tasking in contract that generates requ irement for the data item (e.g .. , Statement of Work paragraph number).
"BLOCK 6" -TECHNICAL OFFICE - Responsible for ensuring adequacy of the data item.
"BLOCK 7" - Specify requirement for inspection/acceptance of the data item by the Government.
"BLOCK 8" -APPROVAL CODE-An "A" indicates that advance written approval by a Government Representative is required prior to final acceptance by the Government, or prior to publication and distribution of the final version of the document to addresses listed in Block 14. Approval will be defined as to its content, format, and future actions. If a preliminary draft is required, it will be indicated in Block 14. The Government will approve/disapprove the CDRL based on completeness of the data, technical adequacy, compliance with contractual requirements, proper identification and marking of rights in technical data, and distribution statements.
A "R" indicates the Government will perform a review of the data, but approval is not required by the Government, or prior to publication and distribution of the final version of the document to addresses listed in Block 14.
However, the data item will be reviewed and accepted/rejected, based on its conforming to the requirements of the DID, compliance with contractual requirements, proper identification and marking of rights in technical data, and distribution statements.
CODE
A R
WHEN USED
Approval Review
"BLOCK 9" - DISTRIBUTION STATEMENT REQUIRED
"BLOCK 10" - FREQUENCY - The data preparation and submission frequency may be indicated in this block using the codes in the table below. If data are of a recurring type, it is to be submitted at the end of the reporting period established in this block unless otherwise indicated in the data preparation instructions in Blocks 12, 13, 16.
N00024-19 R-2320 Attachment J-1 CDRL
CODE
AR
R/AR
ONE/R
2TIME
WKLY
KEY
As Required Revisions As Required One Time with Revisions Two Separate Submittals Weekly
"BLOCK 11" -AS OF DATE - Date for stopping data collection.
"BLOCK 12" - DATE FOR FIRST SUBMISSION - Due date for initial data submission. This is normally the postage date. Actual dues dates by year/month/day or keyed to an event shown in the table below.
CODE
NLT
XDAC
X DPT
XDAIC
X DARC
PSA
DEFINITION
Not Later Than Days after Contract Award Days Prior To Days After Identification of Change Days After Received Comment(s) Post Shakedown Availability
(NOTE: "X" is assigned a value indicating the number of days. EXAMPLE 30 DAC).
"BLOCK 13" - DATE SUBSEQUENT SUBMISSION/EVENT IDENTIFICATION -Actual due dates by year/month/day or keyed to an event as shown above.
"BLOCK 14" - DISTRIBUTION AND - Code of addresses and the number of copies (regular or reproducible) each addressee is to receive. Regular copies required will be to the left of the slash mark and reproducible copies will be to the right. The type of the reproducible copies are explained in Block 16. Codes and symbols of the addressees referenced in Block 14 of the DD Form 1423 are explained in Appendix 2. List of Addresses giving full mailing addresses.
"BLOCK 15" -TOTAL- Summation of the requirements listed in Block 14. Number of regular copies required will be to the left of the slash mark and number of reproducibles to the right.
"BLOCK 16" - REMARKS - Contains all pertinent data information not specified elsewhere on this DD Form 1423 and any amplification of other blocks on this form.
ADDITIONAL INFORMATION
To ensure a common baseline of terminology, the following terms with definitions/examples are provided and shall be used by the Contractor.
Work Item
Work Spec Availability
Descriptive Title BOA Order#
PL
A specific alpha-numeric label for every work item in the form AWl-0234. Trial Cards shall be numbered DK2013,0l. ECPs shall be formatted as LCSX-0123 or PCW-0123.
An eight digit number in the form 123-45-678 representing a "4EWork Specification".
The type and number of the specific availability period covered by the CORL. PSA or IPDAor Emergent. If multiple events in a category are anticipated, then the several events shall be clearly segregated, for example, PSAl and the second PSA2.
A short three to ten word description of the work.
A numeric or alpha-numeric designation of contractual vehicle such as DO 0001 or DO EROl.
Planning Letter numbered with hull number and sequential numbering such as PLS-01 for Planning Letter number 1 for LCSX.
EL
ST
OT
MAT'L
NTE
PO
CFM
GFM
NSN
IMS
FSST
LLTM
NOTES:
Execution Letter numbered with hull number and sequential numbering such as ELG-02 for Execution Letter number 2 for LCSX Straight Time Overtime Material Not To Exceed Purchase Order Contractor Furnished Material Government Furnished Material National Stock Number Integrated Master Schedule Full Ship Shock Trial Long Lead Time Material - any material that will not be available onsite at the availability execution location and available for use 30 days prior to start of the availability
(1) Approval items require disposition within 30 calendar days. Review and comment items require disposition within 45 calendar days.
(2) In order to streamline reporting procedures, this data may be maintained and delivered in a common digital repository within the Contractor's Integrated Data and Product Model Environment (IDPME}. Contract Letter notification via Email. Email notification shall be made available when data is posted or modified within the IDE. Where indicated herein, paper copies shall be provided to PMS 501 in addition to posting on the IPDME. Classified items shall not be posted on in the IDPME, but should be handled in accordance with Contract requirements.
(3) All Management Plans identified on subsequent option years should be delivered only if they are different than previous submittak
(4) The Contractor is encouraged to provide streamline recommendations for cost efficiency.
(5) Rescheduled submittal requirements are subject to adjustment based on mutual agreement between the Contractor and the Data Manager.
PSA EXECUTION LCS FREEDOM VARIANT
CONTRACT DATA REQUIREMENTS LIST INDEX
SEQ DAT A DESCRIPTION SUBTITLE CONTRACT REFERENCE DID NO.
NO.
A 001 FUNDS AND MAN-HOUR ACTUAL WORK ITEM SECTIONC Dl-FNCL-80331A(BLK 16)
EXPENDITURE REPORT MANHOURS/MATERIAL
EXPENDITURE REPORT
(PRODUCTION)
A 002 PRODUCTION WEEKLY MANNING SECTIONC Dl-MGMT-80507 (BLK 16)
PERSONNEL FORECAST (PRODUCTION)
MANNING AND
SCHEDULE REPORT
A 003 CONTRACTOR'S EARNED VALUE SECTIONC DI-MGMT-80227 (BLK 16)
PROGRESS, STATUS, METRJCS REPORT
AND MANAGEMENT (PRODUCTION)
REPORT
A 004 TECHNICAL REPORT - TEST PLAN SECTIONC DI-MISC-80508B (BLK 16)
STUDY/SERVICES
A 005 TECHNICAL REPORT- POST REPAIR TRIAL(S) SECTION C Dl-MISC-80508B (BLK 16)
STUDY/SERVICES AGENDA-
PRE LIM TN ARY /FIN AL
A 006 CRAFT TRIAL REPORT POST REPAIR SEA TRIAL(S) SECTION C DI-MISC-816 15 (BLK 16)
REPORT
A 007 MANHOUR ESTIMATE, PROJECTED COSTS SECTION C Dl-FNCL-8 1116 (BLK 16)
TECHNICAL COST (PRODUCTION)
PROPOSAL
A 008 REPORT, CONTRACT PROBLEM SECTION C DI-MGMT-8 11 78 (BLK 16)
PRODUCTION, OR IDENTIFICATION
DELIVERY REPORT (CPIR)
PROBLEM(S) (PRODUCTION)
A 009 TECHNICAL REPORT- ADVERSE ENVIRONMENTAL SECTIONC Dl-MISC-80508B (BLK 16)
STUDY/SERVICES CONDITIONS PLAN
(PRODUCTION)
A 010 TECHNICAL REPORT - PLANT PROTECTION PLAN SECTION C Dl-MISC-80508B (BLK 16)
STUDY/SERVICES
A Oil QUALITY SYSTEM PLAN QUALITY PLAN SECTION C D!-QCIC-81 379 (BLK 16)
(PRODUCTION)
A 012 INTEGRATED MASTER INTEGRATED MASTER SECTION C DI-MGMT-8 186 1 (BLK 16)
SCHEDULE (IMS) SCHEDULE (IMS) REPORT
CONTRACT DATA REQUIREMENTS LIST I Form Approved (1 Data Item) OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response. Including the time/or reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection qf information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department qf Defense, Washington Headquarters Services. Directorate/or Information Operations and Reports. 1215 Jefferson Davis Highway. Suite 120-1. Arlington, VA 22202--1302. And to the Office of Management and Budget. Paperwork Reduction Project (070-1-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send comoleted form to the Government L.suin!{ Contractin!{ Officerfor the ContracCPR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
8000 A TDP TM OTHER x -- -- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE J'?.PRJCE
GROUP
A001 FUNDS AND MAN-HOURS EXPENDITURE REPORT ACTUAL WORK ITEM MAN-
HOUR/MATERIAL EXPENDITURE
REPORT (PRODUCTION)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.ES'TLHATED
TOTAL PRICE
DI-FNCL-80331A (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED 2TIME (BLK (BLK 16) b. COPIES
16)
8. APP CODE DISTRIBUTION D 11.ASOFDATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Final R (BLK 16) Draft
Reg Repro
16.REMARKS PMS 501
(BLK 4) PARAS 2, 4.1, AND 4.1.4 APPLY. IN PARA 4.1, REPLACE SUP SHIP
"(SEE FIGURE 1) " WITH "(SEE ATTACHMENT 1) ". IN PARA 4.1.4,
REPLACE "FUNDS AND OUTSTANDING COMMITMENTS" WITH "DOLLARS,
OVERHEAD, AND FEE". AFTER "REPORTING PERIOD FOR", DELETE
THROUGH "COSTS" AND REPLACE WITH "ALL WORK ITEMS''. THE
FORMAT SHALL BE IN EXCEL PER ATTACHMENT 1.
COST ELEMENTS ARE TO BE ADDRESSED FOR EACH WORK ITEM
TASKED. THE REPORT WILL REFLECT CUMULATIVE TASKING TO DATE
FOR ALL AWARDED CLINS, IDENTIFYING AWARDED CLINS PER
ATTACHMENT 1. LABOR HOURS REPORTED SHALL BE TRUE LABOR
HOURS FOR PRIME AND SUBCONTRACTORS. LABOR DOLLARS/HOURS
SHALL NOT BE REPORTED AS MATERIAL. ACTUAL BURDENED
COMPOSITE RATE SHALL BE DERIVED BY DIVIDING LABOR DOLLARS
BY LABOR HOURS.
(BLK 10) SUBMITTALS SHALL BE INFORMALLY PROVIDED TO THE
HULL MANAGER FOR COORDINATION AND FINAL APPROVAL VIA WEEKLY
MEETINGS VICE THE CDRL PROCESS. FORMAL SUBMISSIONS
PERIODICITY REMAINS AS STIPULATED IN BLKS 10/12/13
(BLK 12) PRELIMINARY SUBMISSION DUE 30 DAYS AFTER
AVAILABILITY.
(BLK 13) FINAL SUBMISSION IS REQUIRED 90 DAYS AFTER PERIOD
OF PERFORMANCE.
15. TOTAL-+ 2
G. PREPARED BY I H.DATE I I. APPROVED B~ J2.._ ... ,\c....v ~~'l~#C, (v\.(MJ.ut PM-:.'501 15'-An"· 2.01Ci\ DD Form f423-l, JUN 90 Previous editions are obsolete. u Page..!.. of..!.. Pages
Total Exhibit "A" Pages: 014
Work Item
CLIN
Work Spec
MOD
Avail-ability
Descriptive Title
Status Execution Letter #
Prime
ST
Hours
Prime Labor ST Cost ($) (Fully
Burdened)
Prime Mat'l Cost
Sub1
ST
Hours
Sub1 Labor ST Cost ($)
(Fully Burdened)
Sub1 Mat'l Cost
Sub2
ST
Hours
Sub2 Labor ST Cost ($)
(Fully Burdened)
Sub2 Mat'l Cost
Sub3
ST
Hours
Sub3 Labor ST Cost ($)
(Fully Burdened)
Sub3 Mat'l Cost
Total Cost
Base Fee
Award Fee ($)
Total Sell
Price
Comments
AWI xxxx xxx-yy-zzz COMPLETE
UWI yyyy
IN
PROGRESS
LCSa zzzz CANCELED
DC0001,01
Key:
Planning
Execution
CDRL A001 Attachment 1 Actual Work Item Man-Hour/Material Expenditure Report For Production (by Work Item)
USS _______ (LCS__)
Availability/ies __________________
HOURS
Total Travel
Total Remaining
Grand Total
Grand Total Remaining
Labor hours reported shall be true labor hours for Prime and Subs.
Total Labor
Total Remaining
Total Material
Total RemainingLabor dollars shall NOT be reported as material. It must be possible to derive actual burdened composite rates by dividing labor dollars by labor hours.
Mat'l = Material
OT = Overtime
ST = Straight Time
Sub = Subcontractor
Prime = Prime Contractor
% Remaining
(I Data Item) OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of if?formation, including suggestions/or reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate for Information Operations and Reports. 1215 Jefferson Davis Highway. Suite 120J. Arlington, VA 22202-1302. And lo the Office of Management and Budget. Paperwork Reduction Project (070./-0188). Washington, D.C. 20503. Please DO NOT RETURN your.form to either of these addresses. Send comoleted form to the Government L5Suin!( Contractin!( Ofjicerfor the Contract PR No. listed in Block E.
A CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
8000 A TDP TM OTHER x -- --- --
D. SYSTEMJITEM E. CONTRACTOR!PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 1~_ PRICE
GROVP
A002 PROJECT PLANNING CHART WEEKLY MANNING FORECAST
(PRODUCTION)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTL\fr.TED TOTrlLPRil:E
DI-MGMT-80507C (BLK 16) SECTION C PMS 501
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED MTHLY (BLK 30 DAC b. COPIES
16)
8. APP CODE DISTRIBUTION C 11.ASOFDATE 13. DATE OF SUBSEQUENT
SUBMISSION
a. ADDRESSEE
Final
R (BLK 16) Draft
Reg Repro
16. REMARKS PMS 501
(BLK 4) IN PARA 2 FORMAT, REPLACE WITH THE FOLLOWING: "THE SUP SHIP
FORMAT SHALL BE IN EXCEL PER ATTACHMENT 1. INCLUDE
WORKSHEET FOR EACH SUBCONTRACTOR WITH 15% OR MORE OF
LABOR. " IN PARA 3. 1 PROJECT PLANNING CHART, REP LACE WITH
THE FOLLOWING: "WEEKLY FORECAST VS. WEEKLY ACTUAL MANNING
CURVES SHALL BE DISPLAYED." PARA 3.2 PROGRESS OF WORK,
REPLACE WITH THE FOLLOWING: "FORECAST TO BE BASED ON THE
SIZE OF KNOWN WORK PACKAGE, PROGRESS MADE TO DATE, AND
REMAINING TIME FOR THE ADVANCED PLANNING EFFORT. " IN PARA
3. 1 7 MANHOURS EXPENDED, REPLACE WITH THE FOLLOWING: "THE
PSA ADVANCED PLANNING EFFORT CONDUCTED BY
TRADES/ENGINEERS/PLANNERS/MANAGERS SHALL BE REPORTED. THE
DIRECT LABOR STAFFING, FORECASTED WEEKLY BY ITEM, TO
SUPPORT THE PRODUCTION SCHEDULE. THE DIRECT LABOR STAFFING
SHOULD REFLECT ACTUAL STAFFING PERSONNEL AND NOT A LEVEL OF
EFFORT REQUIRED. " IN PARA 3.19 DELETE "AND CONTRACT FUNDS
EXPENDED FIGURES". DELETE PARAS 3.3, 3.4, 3.12, 3.13, 3.14,
3.15, 3.16, AND 3.18.
(BLK 10) SUBMITTALS SHALL BE INFORMALLY PROVIDED TO THE
HULL MANAGER FOR COORDINATION AND FINAL APPROVAL VIA WEEKLY
MEETINGS VICE THE CDRL PROCESS. FORMAL SUBMISSIONS
PERIODICITY REMAINS AS STIPULATED IN BLKS 10/12/13
(BLK 13) MONTHLY STARTING 30 DAYS AFTER AWARDED CLIN IS
ISSUED UNTIL THE END OF PSA.
15. TOTAL~ 2
G. PREPARED BY I H. DATE I I.APPROVED~~~ J.D~\~'/:U1~ M f ,.,~\(JI 'PM<\. ~01 I t'l Av..r t.n I 0..
DD Form 14'23-1, JUN 90 I Previous editions are obsolete. ~ Page ...1.. of ...1.. Pages
Total Exhibit "A" Pages: 014
Manning Forecast II for Production CDRL A002 Attachment 1
Availability/ies:__________
USS ___ (LCS __)
CU
M
U
LA
TI
VE
M
AN
HO
U
RS
Report Weekly
Projected MHRS (Cumulative)
ActualMHRS (Cumulative)
% Progress
Start of
PSA
PR
O
G
RE
SS
End of
PSAA-30
Sample Data
[Day-Month] 0 25 [Day-Month] 0 75 [Day-Month] 0 50 [Day-Month] 75 25 [Day-Month] 125 175 [Day-Month] 575 250 [Day-Month] 425 675 [Day-Month] 475 775
Availability/ies:__________
USS ___ (LCS __)
Weekly Production Manpower Forecast vs Actual CDRL A002 Attachment 1A
M an
Ho ur s
Date Week Ending
Projected ManHours Actual ManHours
Sample Data
Spikes must be explained.
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Revised Projected ManHours (Based on Multiple Contract Modifications)
Actual ManHours
EAC
ManHours
Total
Explain all adjustment to Projected Manhours with Comment.
CDRL A002 Attachment 1B Manhours Summary Total for Production
USS ___ (LCS __)
Availability/ies:__________
Date (Week Ending) Trade Personnel Engineers Cumulative Totals
Comment Planners PMO Weekly Totals
Notes/Variance Explanations:
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Revised Projected ManHours (Based on Multiple Contract Modifications)
Actual ManHours
EAC
ManHours
Total
Cumulative Totals Comment
Explain all adjustment to Projected Manhours with Comment.
CDRL A002 Attachment 1C Manhours Summary Prime for Production
USS ___ (LCS __)
Availability/ies:__________
Date (Week Ending) Trade Personnel Engineers Planners PMO Weekly Totals
Notes/Variance Explanations:
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Actual ManHours
Projected ManHours
Revised Projected ManHours (Based on Multiple Contract Modifications)
Actual ManHours
EAC
ManHours
Total
Cumulative Totals Comment
Explain all adjustment to Projected Manhours with Comment.
CDRL A002 Attachment 1D Manhours Summary Sub#1 for Production
USS ___ (LCS __)
Availability/ies:__________
Date (Week Ending) Trade Personnel Engineers Planners PMO Weekly Totals
Notes/Variance Explanations:
Public reporting burden/or this collection C!f information is estimated to average 110 hours per reJponse. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection ~f information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions.for reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate.for lnformat1on Operations and Reports. 1215 Jefferson Davis Highway. Suite 1201. Arlington, VA 22202--1302. And to the Office of Management and Budget. Paperwork Reduction Project (070-1-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send comvleted form to the Government Lssuimz Contractinl! Officer for the Contract PR No. listed in Block E.
A CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
8000 A TDP TM OTHER x -- --- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE / 7 _pRJCE
GROUP
A003 CONTRACTOR'S PROGRESS, STATUS, AND EARNED VALUE METRICS REPORT
MANAGEMENT REPORT (PRODUCTION)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. EST!,\JATED
TOTALPRIL'E
DI-MGMT-80227 (BLK 16) SECTION C PMS 501
7. DD 250 REQ 9. DIST STATEMENT 10. FREQUENCY I2. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED MTHLY (BLK (BLK 16) b. COPIES
16)
8. APP CODE DISTRIBUTION D II. AS OF DATE I3. DATE OF SUBSEQUENT
a. ADDRESSEE SUBMISSION Final
R (BLK 16) Draft Reg Repro
16. REMARKS PMS 501
(BLK 4) SUBSTITUTE PARA 10.2 WITH "THIS REPORT SHALL BE SUP SHIP
DEVELOPED IN MICROSOFT EXCEL. ,, IN PARA 10.3, CONTENTS
SHALL BE IN ACCORDANCE WITH SOW. SUBMIT IN ACCORDANCE WITH
ATTACHMENT 1.
(BLK 10) SUBMITTALS SHALL BE INFORMALLY PROVIDED TO THE
HULL MANAGER FOR COORDINATION AND FINAL APPROVAL VIA WEEKLY
MEETINGS VICE THE CDRL PROCESS. FORMAL SUBMISSIONS
PERIODICITY REMAINS AS STIPULATED IN BLKS 10/12/13
(BLK 12/13) MONTHLY STARTING 30 DAYS PRIOR TO START OF PSA
UNTIL THE END OF PSA.
I5. TOTAL-+ 2
MREPAREDBY
.(,t\rlu \)fv\$'50 I I H.IA?;,E~(U.1")10\. I LAPPROVEDB'Y~..,:_;~l.e..>v J DATE f>o~--f~lq DD Form 1413-1, JUN 90 ' Previous editions are obsolete. 0 Page ..l. of ..l. Pages
Total Exhibit "A" Pages: 014
Week XX of YY
CDRL A003 Attachment 1 Weekly PSA Earned Value Metrics Report for Production
USS ___ (LCS __)
Availability/ies:__________
MILESTONE ORIGINAL START REVISED START ACTUAL START ORIGINAL COMP REVISED COMP ACTUAL COMP
Ship Arrival
Start Pre-PSA-1
Ammo Offload
Defuel (Situational)
Start PSA
Migrate LAN Ashore
Crew Move Ashore
Mast Staging Complete
Drydock Ship
Mast Staging Removed
50% Conference
Undock Ship
Load Fuel
Habitability Spaces
Migrate LAN Aboard
Crew Move Aboard
Start C/S Support & Services Available
Combat Systems PCD
Start C/S Light-off/Testing
Fuel Onload (Situational)
Machinery PCD
GELO
MELO
Aviation Certification (Situational)
Aviation Tech Assist Visit (Situational)
ISIC DCMA
ISIC LOA
ISIC LTT1
ISIC LTT2
LOA
Perform Inclining
Dock Trials/Fast Cruise
Post Repair Trials (PRT)
Complete PSA
Departure Conference
Key Event - highlight green
KTR Controlled - highlight yellow
Milestone - highlight orange
Availability/ies:__________
USS ___ (LCS __)
Production Milestones and Key Events
CDRL A003 Attachment 1A
PROVIDE RUNNING EXPLANATION FOR ALL REVISIONS:
WEEK
ENDING
AVAILABILITY
Gov't Obligated
Negotiated
Not Negotiated
% Spent
CUMULATIVE PLANNED VALUE
(BCWS)
CUMULATIVE EARNED VALUE
(BCWP)
CUMULATIVE ACTUAL COST
(ACWP)
CPI SPI BAC EAC
0 START
CDRL A003 Attachment 1B
Production Earned Value Data (Dollars)
USS ___ (LCS __)
Availability/ies:__________
BCWS and BCWP figures include growth and subcontractor costs
BCWP = Budgeted Cost of Work Performed
BCWS = Budgeted Cost of Work Scheduled
EAC = Estimate at Completion = ACWP + ((BAC-BCWP)/CPI)
BAC = Budgeted at Completion
SPI = Schedule Performance Index = BCWP/BCWS
CPI = Cost Performance Index = BCWP/ACWP
ACWP = Actual Cost of Work Performed
ENDING
AVAILABILITY
Gov't Obligated (M/H)
Negotiated (M/H)
Not Negotiated (M/H)
Total M/H % Spent (M/H)
CUMULATIVE PLANNED VALUE
(BCWS)
CUMULATIVE EARNED VALUE
(BCWP)
CUMULATIVE ACTUAL COST
(ACWP)
CPI SPI BAC EAC
0 START
BCWP = Budgeted Cost of Work Performed
BCWS = Budgeted Cost of Work Scheduled
CDRL A003 Attachment 1C
Production Earned Value Data (Man Hours)
USS ___ (LCS __)
Availability/ies:__________
BCWS and BCWP figures include growth and subcontractor costs
EAC = Estimate at Completion = ACWP + ((BAC-BCWP)/CPI)
BAC = Budgeted at Completion
SPI = Schedule Performance Index = BCWP/BCWS
CPI = Cost Performance Index = BCWP/ACWP
ACWP = Actual Cost of Work Performed
1 -50 2 -50 3 -50 4 -50 5 -50 6 -50 7 -50 8 -50 9 -50
10 -50 11 -50 12 -50 13 -50 14 -50 15 -50 16 -50
CDRL A003 Attachment 1D
Availability/ies:__________
USS ___ (LCS __)
Production CSCS Chart (Man Hours)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
M
AN
HO
U
RS
(t ho us an ds
WEEK
BCWS
BCWP
ACWP
EAC MANHOURS
1 -50 2 -50 3 -50 4 -50 5 -50 6 -50 7 -50 8 -50 9 -50
10 -50 11 -50 12 -50 13 -50 14 -50 15 -50 16 -50
Availability/ies:__________
USS ___ (LCS __)
Production CPI($) and SPI(MHrs) Chart
CDRL A003 Attachment 1E
0.75
0.8
0.85
0.9
0.95
1.05
1.1
1.15
1.2
1.25
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
VA
LU
E
WEEK
CPI SPI TCPI
Public reporting burden for this collection of information is estimated to average 110 hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate/or Information Operations and Reports. 1215 J~fferson Davis Highway. Suite 120./. Arlington, VA 22202-4302. And to the Office of Management and Budget. Paperwork Reduction Project (070./-0188). Washington, D. C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completedform to the Government Jssuin~ Contractin~ Officer/or the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C.CATEGORY
8000 A TDP TM OTHER x --- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
1. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE r'.PRJCE
GROUP
A004 TECHNICAL REPORT - STUDY/SERVICES TEST PLAN
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.ESTL\IATED
TOTALPRJL'E
DI-MISC-80508B (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED AR (BLK AR b. COPIES
16)
8. APP CODE DISTRIBUTION C 11. AS OF DATE 13. DATE OF SUBSEQUENT
a. ADDRESSEE SUBMISSION Final
A AR Draft Reg Repro
16.REMARKS PMS 501
(BLK 4) THE FORMAT SHALL BE IN EXCEL AND PRESENTED PER SUP SHIP 1
ATTACHMENT 1. AS WORK SPECIFICATIONS ARE REVIEWED,
INCORPORATE TESTS INTO TEST PLAN AND ALSO INCLUDE THE LC SR ON 1
FOLLOWING IN THE PLAN:
SHIP 1
TEST INDEX, TEST PROCEDURES AND TEST SCHEDULE THAT
ADDRESSES ALL EQUIPMENT AND SYSTEMS IMPACTED BY WORK
PERFORMED DURING THE AVAILABILITY. TEST DOCUMENTATION NOT
FURNISHED BY THE GOVERNMENT SHALL BE DEVELOPED BY THE
CONTRACTOR.
(BLK 10) SUBMITTALS SHALL BE INFORMALLY PROVIDED TO THE
HULL MANAGER FOR COORDINATION AND FINAL APPROVAL VIA WEEKLY
MEETINGS VICE THE CDRL PROCESS. FORMAL SUBMISSIONS
PERIODICITY REMAINS AS STIPULATED IN BLKS 10/12/13
I5. TOTAL~ 4
f!APREPARED B?MS • C.IA...&lA \ t50\ I J~AT~( - -W\t\ I I. APPROVED~~~\o...t.-- ~~'ibl'I DD Form 14~3-l, JUN 90 ' Previous editions are obsolete. a Page J_ of J_ Pages
Total Exhibit "A" Pages: 014
Work Item Work Spec Descriptive Title Unit/Location Test Title Test Number Test Description Accept/Reject
Criteria Test Plan
Paragraph Procedure
AWI xxxx 123-45-678 SEACHEST; PREAIR SEACHEST #1 W-4 UHF SATCOM Radio System Functional Test (4C4415015) M11123TPRO-9876-5432-100, Rev Z
Accomplish an at sea demonstration of the RHIB handling system in accordance with Reference 2.20 PT Final 3.4.5.6 Mil-Std-2035A
CDRL A004 Attachment 1 Format for Tabulated Data in the Test Plan
USS _______ (LCS__)
Availability/ies: __________________
NOTE: Examples are from multiple tests but provide sample of information for each column
CONTRACT DATA REQUIREMENTS LIST
I
Form Approved (I Data Item) OMB No. 0704-0188
Public reporting burden/or this collection of information is estimated to average 1 IO hours per response. Including the time/or reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions/or reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate for Information Operations and Reports. 1215 J~fferson Davis Highway. Suite 120-1. Arlington, VA 22202--1302. And lo the Office of Management and Budget. Paperwork Reduction Project (0704-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send comoleted form to the Government Issuinf! Contractinf! Officer for the Contract/PR No. listed in Block E.
A CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
8000 A TDP TM OTHER x -- --- --
D. SYSTEM/ITEM E. CONTRACTORJPR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I.DATA ITEM NO. 2. TITLE OF DAT A ITEM 3. SUBTITLE /7.PRICE
GROUP
A005 TECHNICAL REPORT - STUDY/SERVICES POST REPAIR TRIAL (SJ AGENDA-
PRELIMINARY/FINAL
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE /8.ESTL\IATED Ta£ALPR1<..'E
DI-MISC-80508B (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED 2TIME (BLK 16) b. COPIES
8. APP CODE DISTRIBUTION C 11. AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Final
A (BLK 16) Draft Reg Repro
16.REMARKS PMS 501
(BLK 4) SUP SHIP
REPLACE PARAGRAPH 3B THROUGH 3D WITH "POST REPAIR TRIALS
AGENDA" AND SUBMIT IN MICROSOFT EXCEL IN ACCORDANCE WITH LCSRON 1
ATTACHMENT 1.
SHIP 1
(BLK 12)
PRELIMINARY: NLT 5 DAYS PRIOR TO TRIAL.
(BLK 13)
FINAL: NLT 5 DAYS AFTER COMPLETION OF TRIAL.
15. TOTAL+ 4
G.PREP~~BY M. La. I \>1\.1\S so '1
I H.DATE I 6-·A:YJ<- },.o 10\ I I.APPROVED'~~-~4 iDA 0 ~~lq DD Form 1413-1, JUN 90
Previous editions are obsolete. a Page_!_ of _l_ Pages
Total Exhibit "A" Pages: 014
Start Time End Time Event # Day Event Description COG DEMONSTRATOR DURATION PROCEDURE NOTES GOV'T WITNESS KTR SUPPORT TEST RQMT #
CONTRACTOR VERIFICATION REQUIREMENT
(List ALL Items requiring verification during Dock Trial/Sea Trials)
CDRL A005 Attachment 1A Post Repair Trials Agenda
USS _______ (LCS__)
Availability/ies: __________________
Dockside and Sea Trials (LCS-XY) Post Repair Trials Schedule of Events (SOE) (SWRMC JFFM Compliant)
DOCK TRIALS
PRELIMINARY EVENTS
[Day Month, Year] (Minimum 30 Days Prior to Dock Trials/Sea Trials Period)
[Day Month, Year]
FAST CRUISE
[Day Month, Year]
Day 3
SEA TRIALS
[Day Month, Year]
Day 1
[Day Month, Year] Day 2
[Day Month, Year]
Mon 26th Overnight Tues 27th Overnight Wed 28th Overnight
Title/Reason for Riding
CDRL A005 Attachment 1B Sea Trial Riders List
USS _______ (LCS__)
Availability/ies: __________________
First Name
LCS-XY Post Repair Trials Riders List (Monday 15 & Tuesday 16 August, 2000)
Day 1 Disembark PAX Rider Total vw/Overnight Total xy (z Female) Day 2 Disembark PAX Rider Total tu/Embark vx PAX Riders/Overnight Total xy (z Female
DD-2807
RCVD BY
Beep & Eat Info RCVD
Rider NOK
RCVD
Rider Rqst Completed
Contractor Pier Pick-Up
Departure Time/ Location RCVD
Company Underway Underway Underway
Event Contract Number
Count M/F Last
Name
USS _______ (LCS__)
Availability/ies: __________________
REQUIREMENT LCSRON Comments/ Amplifying Information
CDRL A005 Attachment 1C
Dock Trials Requirements
REQUIREMENT LCSRON Comments/ Amplifying Information
CDRL A005 Attachment 1D
Sea Trials Requirements
USS _______ (LCS__)
Availability/ies: __________________
Activity Procedure Procedure Owed By POC Procedure Rec'd Comment
CDRL A005 Attachment 1E Post Repair Trials Procedures
USS _______ (LCS__)
Availability/ies: __________________
CONTRACT DATA REQUIREMENTS LIST I Farm Approved (I Data Item) OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average 110 hours per reJponse. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection of infi.Jrmation: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions.for reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate for Information Operations and Reports. 1215 Jefferson Davis Highway. Suite 120-1. Arlington, VA 22202--1302. And lo the Office of Management and Budget. Paperwork Reduction Project (070-1-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Issuim! Cvntractinrz Officerfor the Contract·PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C CATEGORY
8000 A TDP TM OTHER x --- --- ---
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I.DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE l~.PRJCE
GROUP
A006 CRAFT TRIAL REPORT POST REPAIR SEA TRIAL(S)
REPORT
4. AUTHORITY (Data Acquisition Document No) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. EST!.\IATED
TOTALPRJL"E
DI-MISC-81615 (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION I4. DISTRIBUTION REQUIRED AR (BLK 16) b. COPIES
8. APP CODE DISTRIBUTION c 11.ASOFDATE 13. DATE OF SUBSEQUENT SUBMISSION a. ADDRESSEE Final
R 30 DARC Draft Reg Repro
16. REMARKS PMS 501
(BLK 4) IN PARAS 1 AND 2, CHANGE, "CRAFT TRIAL REPORT" TO SUP SHIP
"SHIP TRIAL REPORT".
LCSRON 1
(BLK 12) NLT 7 DAYS AFTER POST REPAIR SEA TRIAL(S).
SHIP 1
15. TOTAL-+ 4 -
G. PREPARED BY I H. DATE I r. APPRovEu ~iv.:_· tSa-s k...A ~g~ '-J,;2.c >q M. ('A ,.r; A Oi'\I\<; ~01 16 -Av-! r - '7...t> I &1.
DD Form 142'.3-1, JUN 90 I Previous editions are obsolete. lJ Page J_ of J_Pages
Total Exhibit "A" Pages: 014
Form Approved
(1 Data Item) OMB No. 0704-0188 Public reporting burden for this collection of information is estimated to average /IO hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate/or Information Operations and Reports. 1215 J~fferson Davis Highway. Suite 120./. Arlington, VA 22202-./302. And to the Office of Management and Budget. Paperwork Reduction Project (0704-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send como/eted form to the Government lssuinf{ Contractinf{ Of{icerfor the Contract'PR No. listed in Block E.
A CONTRACT LINE ITEM NO. B. EXHIBIT C.CATEGORY
8000 A TDP TM OTHER x -- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
1. DATA !TEI\'! NO. 2. TITLE OF DATA ITEM 3. SUBTITLE 1'".PRJCE
GROUP
A007 MANHOUR ESTIMATE, TECHNICAL COST PROJECTED COSTS (PRODUCTION)
PROPOSAL
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTL\tA.TED
TOT AL PR11...'E
DI-FNCL-81116 (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED MTHLY (BLK (BLK 16) b. COPIES
16)
8. APP CODE DISTRIBUTION D 11.ASOFDATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Final
R (BLK 16) Draft Reg Repro
16.REMARKS PMS 501
(BLK 4) PARA 10.1 FORMAT, REPLACE WITH THE FOLLOWING: "THE SUP SHIP
1 FORMAT SHALL BE IN EXCEL AND PRESENTED PER ATTACHMENT 1. ,,
REPORT SHALL IDENTIFY PROJECTED COSTS, TO INCLUDE
SUBCONTRACTORS, FOR ACCOMPLISHMENT OF EACH WORK ITEM TASKED
FOR THE PSA.
THE REPORT SHALL REFLECT CUMULATIVE TASKINGS TO DATE FOR
ALL CONTRACT AWARDS IMPACTING THE ASSIGNED AVAILABILITY.
IDENTIFICATION OF APPLICABLE CONTRACT AWARDS SHALL BE
ANNOTATED PER ATTACHMENT 1.
(BLK 10) SUBMITTALS SHALL BE INFORMALLY PROVIDED TO THE
HULL MANAGER FOR COORDINATION AND FINAL APPROVAL VIA WEEKLY
MEETINGS VICE THE CDRL PROCESS. FORMAL SUBMISSIONS
PERIODICITY REMAINS AS STIPULATED IN BLKS 10/12/13
(BLK 12/13) MONTHLY STARTING 60 DAYS AFTER RECEIPT OF
INITIAL TASKING THR.OUGH PERIOD OF PERFORMANCE.
15. TOTAL-+ 2
MREPARED BY I H. DATE
·Gc..rl<A i>(IA~~O\ 16-An-r- 7Iile>t
I I.APPROVEDB~~-~~ ~DATE '-/ c1'1J.\ ~ICf DD Form 1425-1, JUN 90 I Previous editions are obsolete. ~ Page ..1.. of ..1.. Pages
Total Exhibit "A" Pages: 014
Work Item
CLIN
Work Spec
MOD
Avail-ability
Descriptive Title
Status Execution Letter #
Prime
ST
Hours
Prime Labor ST Cost ($) (Fully
Burdened)
Prime Mat'l Cost
Sub1
ST
Hours
Sub1 Labor ST Cost ($)
(Fully Burdened)
Sub1 Mat'l Cost
Sub2
ST
Hours
Sub2 Labor ST Cost ($)
(Fully Burdened)
Sub2 Mat'l Cost
Sub3
ST
Hours
Sub3 Labor ST Cost ($)
(Fully Burdened)
Sub3 Mat'l Cost
Total Cost
Base Fee
Award Fee ($)
Total Sell
Price
Comments
AWI xxxx xxx-yy-zzz COMPLETE
UWI yyyy
IN
PROGRESS
LCSa zzzz CANCELED
Labor dollars shall NOT be reported as material. It must be possible to derive actual burdened composite rates by dividing l
% Remaining
Total Material
Total Remaining
Total Labor
CDRL A007 Attachment 1 Projected Work Item Man-Hour/Material Report (by Work Item) for Production
USS _______ (LCS__)
Availability/ies: __________________
Labor hours reported shall be true labor hours for Prime and Subs.
HOURS
Mat'l = Material
OT = Overtime
ST = Straight Time
Sub = Subcontractor
Prime = Prime Contractor %
%Grand Total Remaining
Grand Total
Total Remaining
Total Travel
Total Remaining
Form Approved (I Data Item) OMB No. 0704-0188
Public reporting burden for this collection of information is estimated lo average I JO hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions/or reducing this burden, to Department qf Defense, Washington Headquarters Services. Directorate/or lf!formation Operations and Reports. 1215 J~fferson Davis Highway. Suite 120./. Arlington, VA 22202-./302. And to the Office of Management and Budget. Paperwork Reduction Project (0704-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government Lvsuinl! Contractinl! Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
8000 A TDP TM OTHER x -- --- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE F.PRJCE
GROUP
A008 REPORT, PRODUCTION, OR DELIVERY CONTRACT PROBLEM
PROBLEM(S) IDENTIFICATION REPORT (CPIR)
(PRODUCTION)
4. AUTHORITY (Data Acquisition Document No.) S. CONTRACT REFERENCE 6. REQUIRING OFFICE l S. ESTL\!ATED
Tm'..lLf'RJC'E
DI-MGMT-81178 (BLK 16) SECTION C PMS 501
7. DD2SOREQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED AR (BLK 16) b. COPIES
8. APP CODE DISTRIBUTION D 11.ASOFDATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Final
R (BLK 16) Draft Reg Repro
16. REMARKS PMS 501 1
(BLK 4) THE REPORT SHALL PROVIDE ANALYSIS OF THE SUP SHIP 1
ANTICIPATED PROBLEMS.
(BLK 12)
NLT 10 CALENDAR DAYS AFTER IDENTIFICATION OF A CONTRACT
PROBLEM.
(BLK 13)
SUBMIT FOLLOW-UP STATUS REPORT IAW PARAGRAPH (D) OF
CONTRACT CLAUSE CONTRACTOR PROBLEM IDENTIFICATION REPORTS
(NAVSEA) (MAY 1993).
15. TOTAL~ 2
~REPA.RED BYj)I I H.DATE I I. APPRovEDB~~ ~s~ ~~~"}~1'( . Co-d.LA . MS €>0\ I ~--f'AN->.r • 10iC\.
DD Form 1423-1, JUN 90 \ Previous editions are obsolete. () Page .1... of ..L Pages
Total Exhibit "A" Pages: 014
I Form Approved
(1 Data Item) OMB No. 0704-0188 Public reporting burden for this collection of information is estimated to average I JO hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department ~f Defense, Washington Headquarters Services. Directorate for ]~formation Operations and Reports. 1215 Jefferson Davis Highway. Suite 120./. Arlington, VA 22202-4302. And lo the q[fice of Management and Budget. Paperwork Reduction Project (0704-0188). Washington, D.C. 20503. Please DO NOT RETURN your form lo either of these addresses. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO. B. EXHIBIT C.CATEGORY
8000 A TDP TM OTHER x -- -- ---
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE J7.PRJCE
GROUP
A009 TECHNICAL REPORT-STUDY/SERVICES ADVERSE ENVIRONMENTAL
CONDITIONS PLAN (PRODUCTION)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.ESTL\IATED TOTALPRJi:E
DI-MISC-80508B (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED ONE/R (BLK 16) b. COPIES
8. APP CODE DISTRIBUTION C 11.ASOFDATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Final
A AR (BLK 16) Draft Reg Repro
16.REMARKS PMS 501 1
(BLK 4) SUP SHIP 1
THE PLAN SHALL PRESCRIBE THE PROCEDURES WHICH WILL BE
IMPLEMENTED TO PROTECT THE SHIP DURING PERIODS OF HEAVY LCSRON 1
WEATHER OR OTHER ADVERSE ENVIRONMENTAL CONDITIONS TO
INCLUDE HURRICANES. SHIP 1
(BLK 12)
60 DPT START OF PSA.
(BLK 13)
NLT 30 DAIC, 10 DARC.
15. TOTAL~ 4
UREP~DBY
. (,,A _.t,t Vfv\ <:., $C) \
I H.DATE
,e... --IJw...f - ? .Fi I 0\ I I.APPROVED~~~k.A -i;_~A~l/ ~l'J DD Form 1423-1, JUN 90 ' Previous editions are obsolete. tJ Page ..L of ..L Pages
Total Exhibit "A" Pages: 014
Form Approved (I Data Item) OMB No. 0704-0188
Public reporting burden for this collection of information is estimated to average I JO hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect <?f this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate/or lf!formation Operations and Reports. 1215 Jefferson Davis Highway. Suite 120./. Arlington, VA 22202-4302. And to the Qffice of Management and Budget. Paperwork Reduction Project (070./-0188). Washington, D.C. 20503. Please DO NOT RETURN yourform to either of these addresses. Send completed form to the Government 1.<suin11: Contractin11: Officer for the Contract1PR No. listed in Block E.
A CON1RACT LINE ITEM NO. B. EXHIBIT C.CATEGORY
8000 A TDP TM OTHER x --- -- --
D. SYSTEM/ITEM E. CONTRACTORJPR NO. F. CON1RACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
I. DATA ITEM NO. 2. TilLEOFDATAITEM 3. SUBTITLE P.PRICE
GROUP
A010 TECHNICAL REPORT - STUDY/SERVICES PLANT PROTECTION PLAN
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.ESTJ.uATED TOTALPRlL'E
DI-MISC-80503B (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DIS1RIBUTION REQUIRED ONE/R (BLK 16) b. COPIES
8. APP CODE DISTRIBUTION D II.AS OF DATE 13. DATE OF SUBSEQUENT
SUBMISSION a. ADDRESSEE Final
A AR (BLK 16) Draft Reg Repro
16. REMARKS PMS 501 1
(BLK 4) THIS PLAN SHALL DEFINE THE ACTIONS AND PROCEDURES SUP SHIP 1
FOR PROTECTION OF THE SYSTEM. SYSTEM SHALL BE DEFINED AS
THE SHIP (SJ , MATERIAL, AND EQUIPMENT. LCSRON 1
(BLK 12) 60 DPT START OF PSA. SHIP 1
(BLK 13) NLT 30 DAIC, 10 DARC.
15. TOTAL~ 4
~.l1.p~lD 8 P1 .(\ I H. DATE I L APPROVED B'¥,,L ·_.~ k r;g~~" ~ l 'J • ..ll A (V\. f>O \ I <5 -Llnti-v -Z-010/ DD Form 1423-1, JUN 90 ' Previous editions are obsolete. {/ Page ...!.. of...!.. Pages
Total Exhibit "A" Pages: 014
Form Approved
(1 Data Item) OMB No. 0704-0188 Public reporting burden for this collection of information is estimated to average 110 hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the co/lee/ion of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate/or lf!formation Operations and Reports. 1215 J~fferson Davis Highway. Suite 120-1. Arlington, VA 22202--1302. And to the Office of Management and Budget. Paperwork Reduction Project (070./-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send completed form to the Government L.suin!! Contractin}! Officer for the Contract/PR No. listed in Block E.
A CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
8000 A TDP TM OTHER x -- --- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 TBD
l.DATAITEMNO. 2. TITLE OF DATA ITEM 3. SUBTITLE l"'.PRJCE
OIWUP
A011 QUALITY SYSTEM PLAN QUALITY PLAN (PRODUCTION)
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE J8.ESTL\IATED
TOTALPRI<-'E
DI-QCIC-81379 (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED ONE/R 30 DAC b. COPIES
8. APP CODE DISTRIBUTION C II. AS OF DATE 13. DATE OF SUBSEQUENT
a. ADDRESSEE
SUBMISSION Final
A (BLK 16)
Draft
Reg Repro
16. REMARKS PMS 501 1
(BLK 4) PARAGRAPH 10, ADD PARAGRAPH 10. 5: "PLAN SHALL SUP SHIP 1
ADDRESS ALL ASPECTS OF THE SOW INCLUDING PLANNING AND WORK
SPECIFICATION DEVELOPMENT; MATERIAL PROCUREMENT; VENDOR AND LC SR ON 1
SUBCONTRACTOR SUPPORT; EXECUTION OF WORK DURING THE POST
DELIVERY PERIOD TO INCLUDE CHECKPOINTS, INSPECTIONS AND SHIP 1
TESTING. ,,
(BLK 13) NLT 30 DAIC R/AR 30 DARC
15. TOTAL+ 4
.(U'REP~k° BY ..r. _,\ ,PMS~oi I H.DATE I 6 -t\:-vJ f" - ?...iJI q I I. APPROVEDB~~~ ~~-/~1'1
DD Form 142~-l, JUN 90 ' Previous editions are obsolete. u Page ...1. of ..1.. Pages
Total Exhibit "A" Pages: 014
Public reporting burden for this collection of information is estimated to average J JO hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions/or reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate/or Information Operations and Reports. 1215 J~fferson Davis Highway. Suite 120./. Arlington, VA 22202-./302. And to the Office of Management and Budget. Paperwork Reduction Project (070./-0188). Washington, D.C. 20503. Please DO NOT RETURN your form to either of these addresses. Send comvletedform to the Government IssuinK Contractinf! Officer for the Contract/PR No. listed in Block E.
A CONTRACT LINE ITEM NO. B. EXHIBIT C. CATEGORY
8000 A '!'DP TM OTHER x -- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND FOLLOW N00024-19-R-2320 'I'BD
I. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE l".PRJCE
GROUP
A012 INTEGRATED PROGRAM MANAGEMENT REPORT INTEGRATED MASTER SCHEDULE
(IMPR) (IMS) REPORT
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE 6. REQUIRING OFFICE 18. ESTL\IATED TOTALPRJc.:E
DI-MGM'I'-81861 (BLK 16) SECTION C PMS 501
7. DD250REQ 9. DIST STATEMENT IO. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED (BLK 16) (BLK 16) b. COPIES
8. APP CODE DISTRIBUTION C II. AS OF DATE 13. DATE OF SUBSEQUENT a. ADDRESSEE SUBMISSION Draft Final
A (BLK 16) Reg Repro
16.REMARKS PMS 501
THE PRIME CONTRACTOR ( S) ARE RESPONSIBLE FOR FLOWING DOWN SUP SHIP
IMS REQUIREMENTS TO ALL SUBCONTRACTORS.
THE SCHEDULE SHALL PRESENT THE OVERALL PLAN INCLUDING
PREDECESSOR AND SUCCESSOR RELATIONSHIPS WITHIN AND BETWEEN
ALL WORK ITEMS. THE INFORMATION SHALL BE INTEGRATED TO
FACILITATE A CRITICAL PATH ANALYSIS AND BE USED TO VERIFY
ATTAINABILITY OF PROJECT OBJECTIVES AND TO EVALUATE
PROGRESS. THE SCHEDULE SHALL DEPICT ALL ACTIVITIES .REQUIRED
FOR THE PERFORMANCE OF ITEMS AND ALL ACTIVITIES DEFINED IN
THE CONTRACT. IMS KEY EVENTS SHALL BE INCLUDED IN THE IMS.
THE LIST OF IMS KEY EVENTS DOES NOT INDICATE ANY REQUIRED
SCHEDULE SEQUENCE OR DEPENDENCIES. THE CONTRACTUAL
MILESTONES SHALL BE INCLUDED IN THE IMS AND WILL BE TIED TO
ALL .REQUIRED PREDECESSORS.
(BLK 4)REPLACE PARAGRAPH 3. 7.1.2 WITH "IMS STATUS. THE IMS
SHALL BE S'I'A'I'USED ACCORDING TO THE CONTRACTOR'S MANAGEMENT
CONTROL SYSTEM AND SHALL BE SUBMITTED WEEKLY DURING THE
AVAILABILITY. THE IMS SHALL REFLECT EVM DATA CONSISTENT
AND TRACEABLE 7'0 OTHER COST AND SCHEDULE REPORTS
SUBMITTED. "
IN PARAGRAPH 3.7.1.3. REPLACE: "THE IMS SHALL HAVE
TRACEABILITY TO THE IN'I'EGRATED MASTER PLAN (IMP) (IF
APPLICABLE), ORGANIZATIONAL BREAKDOWN STRUCTURE (OBS),
CONTROL ACCOUNTS, WBS AND STATEMENT OF WORK" WITH "THE
SCHEDULE SHALL HAVE A NUMBERING SYS'I'EM DE.RIVED DIRECTLY
FR.OM THE WORK SPECIFICATION, TASK AND SUBTASK NUMBERING
SYS'I'EM OF THE 4E SPECIFICATIONS AND INCLUDES AT A MINIMUM
ALL OF THE TASKS AND SUBTASKS AND PROVIDES TRACEABILITY TO
THE SOW". 15. TOTAL.+ 2
MREPAREDBY .(.,. ~L, -PM\ c....ri \
I H. DATE
i &,- t\V'\.r - 71) I q I I.APPROVEDB~~~4 fi ~A~.J _2'i} q DD Form 1423-1 JUN 90 \ Previous editions are obsolete. (J Pa e ..1. of 3 g Pa es g
Total Exhibit "A" Pages: 014
Form Approved (I Data Item) OMB No. 0704-0188
Public reporting burden/or this collection of information is estimated to average 110 hours per response. Including the time for reviewing instructions. Searching existing data sources. Gathering and maintaining the data needed. And completing and reviewing the collection of information: Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services. Directorate for lf!formation Operations and Reports. 1215 Jefferson Davis Highway. Suite 120./. Arlington, VA 22202-4302. And to the Office of Management and Budget. Paperwork Reduction Project (0704-0188). Washington, D. C. 20503. Please DO NOT RETURN yourform to either of these addresses. Send completed form to the Government Lisuinf! Contracting Officer for the Contract'PR No. listed in Block E.
A CONTRACT LINE ITEM NO. B. EXHIBIT C.CATEGORY
8000 A TDP TM OTHER x -- -- --
D. SYSTEM/ITEM E. CONTRACTOR/PR NO. F. CONTRACTOR
FREEDOM VARIANT HULLS 17 AND N00024-19-R-2320 TBD
FOLLOW
I. DATA ITEM NO. 2. TITLE OF DATA ITEM 3. SUBTITLE !".PRICE
GROUP
A012 INTEGRATED MASTER SCHEDULE (IMS) INTEGRATED MASTER SCHEDULE
(IMS) REPORT
4. AUTHORITY (Data Acquisition Document No.) 15. CONTRACT REFERENCE 6. REQUIRING OFFICE 18.ESTL\IATED TOTAi... PRICE
DI-MGMT-81861 (BLK 16) SECTION C PMS 501
7.DD250REQ 9. DIST STATEMENT 10. FREQUENCY 12. DATE OF FIRST SUBMISSION 14. DISTRIBUTION REQUIRED (BLK 16) (BLK 16) b. COPIES
8. APP CODE DISTRIBUTION C II. AS OF DATE 13. DATE OF SUBSEQUENT
a. ADDRESSEE
SUBMISSION Draft Final
A (BLK 16) Reg Repro
16.REMARKS
REPLACE PARAGRAPH 3. 7. 1. 4 WITH "ANALYSIS. DURING THE
AVAILABILITY THE CONTRACTOR WILL PROVIDE AN ANALYSIS IN
CONJUNCTION WITH WEEKLY IMS SUBMITTAL THAT INCLUDES:
CHANGES TO SCHEDULE ASSUMPTIONS, VARIANCES TO THE BASELINE
SCHEDULE, CAUSES FOR VARIANCES POTENTIAL IMPACTS AND
RECOMMENDED CORRECTIVE ACTIONS TO RECOVER AND MINIMIZE
SCHEDULE DELAYS. THE ANALYSIS SHALL ALSO IDENTIFY POTENTIAL
PROBLEMS AND PROVIDE AN ASSESSMENT OF THE CRITICAL AND
NEAR-CRITICAL PATHS. "
REMOVE PARAGRAPHS 1.1.1 THROUGH 1.1.5, 1.1.7, 2.1.1.1,
2.1.1.3, 2.2.1, 2.2.3,…