This document contains a Contract Data Requirements List (CDRL) for a federal contract opportunity with the Department of the Navy. The CDRL outlines three required data items: a Project Program Planning Document, a Project Plan, and optional Project Plan Deliverables such as technology transition plans and project briefings. Delivery of the Project Program Planning Document and Project Plan will be required once at the start of each new project, with optional additional deliverables submitted on a semi-annual basis. The distribution statement allows sharing of the data items with the Department of Defense and U.S. DoD contractors. The related federal contract opportunity pre-solicitation provides context that the Navy's Manufacturing Technology Program aims to reduce costs for key acquisition platforms like aircraft carriers and submarines through seven Centers of Excellence, and that the RFP for contract N00014-19-R-0003 for Electro-Optics manufacturing technology support will be issued on or around May 29, 2019.

RFP Exhibit B Project CDRLS

View the file

Other files

File Type Posted
RFP_Sec_J_Attachment_10_Q_A.pdf PDF
Sol_N00014-19-R-0003_Amd_0001.pdf PDF
RFP_Sec_J_Attachment_6_PPQ.docx DOCX document
RFP_Sec_J_Attachment_1_SOW_EOCOE.docx DOCX document
RFP_Exhibit_A_CoE_Level_CDRLS.docx DOCX document
RFP_Sec_J_Attachment_2_Key_Personnel.doc DOC document
RFP_Sec_J_Attachment_4_COR.docx DOCX document
RFP_Sec_J_Attachment_8_CE_Summary.xlsx XLSX spreadsheet
ENCLOSURE_NUMBER_1.docx DOCX document
RFP_Sec_J_Attachment_9_ONRRepsCerts.pdf PDF
Sol_N00014-19-R-0003.pdf PDF
RFP_Sec_J_Attachment_5_PPIF.docx DOCX document
RFP_Sec_J_Attachment_3_Report_Format.doc DOC document
RFP_Sec_J_Attachment_7_Price_Information.docx DOCX document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DATA REQUIREMENTS LIST

(2 Data Items) Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
0001
B
TDP

TM

OTHER
R&D
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
TBD
TBD
TBD

17. PRICE GROUP

6. REQUIRING OFFICE

18. ESTIMATED

TOTAL PRICE

14. DISTRIBUTION

a. ADDRESSEE
b. COPIES
Draft
Final
Reg
Repro

See Enclosure #1

15. TOTAL

1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B001
Project Program Planning Document (PPD)
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED

TOTAL PRICE

Statement of Work
Statement of Work
Office of Naval Research,

ManTech Program Office

7. DD 250 REQ
9. DIST STATEMENT
10 FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
LT*
REQUIRED
ONCE/R
***

D**

a. ADDRESSEE
b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT
Draft
Final

N/A

***
SUBMISSION
Reg
Repro
16. REMARKS
See Enclosure #1

* Block 7: The contractor shall submit a Project Program Planning Document in accordance with annual Navy ManTech Guidance.

** Block 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (TBD at time of award). Other requests shall be referred to the Office of Naval Research COR noted in the contract *** Block 11, 12, and 13: A PPD is required for each planned project. The due date will be established by the ONR Program Officer/COR.

15. TOTAL

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
Mary Helen Dent
22 Mar 2019
Mary Helen Dent

DD FORM 1423-2, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page 1

CONTRACT DATA REQUIREMENTS LIST

(2 Data Items) Form Approved OMB No. 0704-0188

The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0701-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. Listed in Block E.

A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY
0001
B
TDP

TM

OTHER
R&D
D. SYSTEM/ITEM
E. CONTRACT/PR NO.
F. CONTRACTOR
TBD
TBD
TBD
1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B002
Project Plan
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED

TOTAL PRICE

Statement of Work
Statement of Work
Office of Naval Research,
7. DD 250 REQ
9. DIST STATEMENT
10 FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
*
REQUIRED
ONCE/R
***

D **

a. ADDRESSEE
b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT
Draft
Final

N/A

***
SUBMISSION
Reg
Repro
16. REMARKS
See Enclosure #1

* Block 7: The contractor shall submit a project plan in accordance with annual Navy ManTech Guidance and the Statement of Work.

** Block 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (TBD at time of award). Other requests shall be referred to the Office of Naval Research COR noted in the contract *** Block 11, 12, and 13: The due date for individual project plans will be established by the ONR Program Officer/COR.

15. TOTAL

1. DATA ITEM NO.
2. TITLE OF DATA ITEM
3. SUBTITLE

17. PRICE GROUP

B003
Optional Project Plan Deliverables*
4. AUTHORITY (Data Acquisition Document No.)
5. CONTRACT REFERENCE
6. REQUIRING OFFICE

18. ESTIMATED

TOTAL PRICE

Statement of Work
Statement of Work
Office of Naval Research,
7. DD 250 REQ
9. DIST STATEMENT
10 FREQUENCY
12. DATE OF FIRST SUBMISSION
14. DISTRIBUTION
LT
REQUIRED
Semi Annual
***

D**

a. ADDRESSEE
b. COPIES

8. APP CODE

11. AS OF DATE
13. DATE OF SUBSEQUENT
Draft
Final

N/A

***
SUBMISSION
Reg
Repro
16. REMARKS
See Enclosure #1

*Depending on the type of project, other deliverables may also be required. Optional Project Plan Deliverables include: Technology Transitions Plans, Project Database Information, Project Book Information, Project Quad Charts, Project Briefings, and Success Stories.

** Block 9: DISTRIBUTION STATEMENT D. Distribution authorized to the Department of Defense and U.S. DoD contractors only (Critical Technology) (TBD at time of award). Other requests shall be referred to the Office of Naval Research COR noted in the contract *** Block 11, 12, and 13: The due date for documents listed above will be provided as needed by the ONR Program Officer/COR.

15. TOTAL

G. PREPARED BY
H. DATE
I. APPROVED BY
J. DATE
Mary Helen Dent
22 Mar 2019
Mary Helen Dent

DD FORM 1423-2, AUG 96 (EG) PREVIOUS EDITION MAY BE USED Page 2