MXG Mini-Split 07 Mar 25_.pptx
PPTX presentation 4 MB Posted
- Attached to
- A/C Split Units Installation, Aviano AFB, Italy
- Solicitation number
- FA568225Q8015
About this file
The file is a PowerPoint presentation (MXG Mini-Split 07 Mar 25_.pptx) related to a Request for Quotes (RFQ) for A/C Split Units Installation at Aviano Air Force Base in Italy. The solicitation, numbered FA568225Q8015, is issued by the Department of the Air Force United States Air Forces in Europe - Air Forces Africa and seeks commercial products/services for installing mini-split air conditioning units. The acquisition is a Firm Fixed Price (FFP) contract with no specific set-aside, classified under NAICS Code 238220 for A/C Equipment installation.
Key procurement details include quotes due by 2:00 PM Central European Time on 4 June 2025, submitted via email to Contract Specialist Resi Santin and Contracting Officer TSgt Joshua Largent. The anticipated contract performance is at Aviano AB, Italy, with a requested delivery date of 30 August 2025. Vendors must submit questions by 28 May 2025. The solicitation uses Simplified Acquisition Procedures and does not guarantee contract award, with the government reserving the right to cancel the RFQ. An attached Statement of Work dated 25 March 2025 provides additional project-specific details.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work 90 Total Requested new installations Slide 2, 1 of those replacement, removal and disposal of existing units. (1 replacement units in bldg. 1131) Slide 12, 7 of those replacement, removal, and disposal of existing units. (7 replacement units in bldg. 1270). Arrows highlighted in yellow need wifi removed.
The red arrows are where the new units are to be placed.
Slide 6 building 11225 requires 5 splits installed on the 1st floor.
Slide 9 building 933 requires 3 splits installed on the 1st floor.
All other splits will be installed on the ground floor. At the normal height of ±2.5m
Building 9109 requires 2 new mini-split installations in the office areas image1.png image2.png image3.png image4.png image5.png image6.png image7.png image8.png image9.png image10.png image11.png image12.png image17.png image18.png image19.png image20.png image21.png image13.png image14.png image15.png image16.png image22.png image23.png image24.png