Mulino Hangar and Waterline Project - Pre-Bid Meeting Agenda - Q and A - Attendees_.pdf

PDF 296 KB Posted

Attached to
Mulino State Airport Hangar and Waterline Project
Solicitation number
S-10900-00016730
Issued by
Oregon

About this file

This document is a Pre-Bid Conference Agenda and Attendee List for the Mulino State Airport Hangar and Waterline Improvements Project, organized by the Oregon Department of Aviation (ODAV) in coordination with the engineering firm Century West Engineering. The project involves the expansion of an existing hangar building with eight new hangars, including slab foundation and new structure; extension of Taxilane D with new pavement; extension of asphalt pavement from the hangar face to Taxilane C and D; installation of new storm drainage conveyance and detention systems; relocation of existing electrical power infrastructure; and installation of taxilane markings. The voluntary pre-bid meeting was held electronically via Microsoft Teams on May 6, 2026, at 10:00 AM, with twenty bid attendees representing construction and trade firms listed on the sign-in sheet. Bids were due on May 19, 2026, at 2:00 PM with electronic opening via Teams. The project is structured in three phases: Phase 0 (Architectural & Building Permitting) with interim completion within 90 calendar days after Notice to Proceed; Phase 1 with substantial completion within 180 calendar days after NTP; and Final Completion within 30 calendar days after substantial completion. Award will be made to the lowest responsible and responsive bidder for items selected for award based on the Base Bid form.

The project is federally funded through the Federal Aviation Administration Airport Improvement Program (AIP NO. 3-41-0072-019-2025). Davis Bacon or Oregon Bureau of Labor and Industries (BOLI) prevailing wage rates, whichever is higher, apply to the project. Previous Disadvantaged Business Enterprise (DBE) requirements applicable to federally funded projects were suspended as of October 3, 2025, though ODAV maintains a nondiscrimination policy based on race, color, sex, or national origin. Liquidated damages are set at $1,500 per day for schedule delays. The contractor is responsible for obtaining all permits not obtained by the owner through Clackamas County, which will include reviews by Mollala Fire District and Water Environment Services. The project requires construction staking by the contractor, erosion control measures including sediment fencing and inlet protection, and strict adherence to airport safety and security protocols with no work permitted without an engineer or airport representative present. All excavated materials are planned to be hauled off-site, with any pavement damage resulting from contractor use of taxilanes to be repaired at the contractor's expense.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5500 Meadows Road, Suite 250 | Lake Oswego, OR 9703

AGENDA – Mulino State Airport – Hangar and Waterline

Improvements Project

Pre-Bid Conference (Voluntary)

Project: Mulino State Airport – Hangar and Waterline Improvements Project (AIP NO. 3-41-0072-019- 2025)

Date & Time: May 6, 2026, 10:00 AM

Location: Electronic (MS Teams)

Attendees: See attached sign in sheet

Meeting Overview: This is the voluntary pre-bid meeting for all interested bidders.

I. Introductions

Engineer: Century West Engineering

• James Kirby, Century West Engineering – Sr Project Manager

• Ryan Halvorson, Century West Engineering – Project Manager

Sponsor/Owner: Oregon Department of Aviation (ODAV)

• Anthony Beach, ODAV – State Airports Manager

• Alex Thomas, ODAV – Policy, Planning & Programs Manager

• Ermie Buncal – Program & Contracts Coordinator

II. Scope of Work

The work generally involves the following activities:

• Expansion of existing hangar building (8 new hangars) including slab foundation and new hangar.

• Extend Taxilane D east of hangar extension with new pavement section.

• Extend asphalt pavement from face of hangar to Taxilane C (west) and Taxilane D

(east) of hangar extension.

• Install new storm drainage conveyance system for hangar extension.

• Install new storm drainage facility to infiltrate the 2-year, 24-hour, storm event and detain stormwater events 5-year through 100-year to pre-existing conditions.

• Relocate existing electrical power to existing hangar for hangar extension and reconnect power to existing hangar.

• Install Taxilane markings.

III. Bids Due

Date: May 19th, 2026

Time: As described in the Invitation to Bid/Oregon Buys (2:00 p.m., Local Time), Bids open at 2:00 p.m.

Location: Electronic opening per Invitation to Bid (Teams) at 2:00 p.m following bid closure

IV. Project Funding

Federal funding through the Federal FAA Airport Improvement Program (A.I.P.)

V. Award

Basis of Award: Lowest responsible and responsive bidder for items selected for award, Attachment A, Form A-2, Base Bid. The Sponsor reserves the right to withdraw any item from award consideration

VI. Prevailing Wage Rates

Wage rates are included as part of the bid documents. The project shall pay the higher of Davis Bacon Wages or BOLI Prevailing Wages.

VII. Disadvantaged Business Enterprise (DBE) Goal

• DBE requirements that were applicable to federally funded projects prior to

10/03/2025 effective date of the Interim Final Rule by the US Department of

Transportation are no longer in effect, and DBE requirements have been suspended pending implementation of the DBE.

• ODAV has policy to practice nondiscrimination based on race, color, sex, or national origin in the award or performance of this Contract.

• Design team encourages participation by all firms qualifying under this solicitation regardless of size or ownership.

VIII. Contract Time

Refer to “Notice to Proceed” in the Proposal.

1. Phase 0 (Architectural & Building Permitting) Interim Completion to be achieved

90 calendar days after NTP

2. Phase 1 Substantial Completion to be achieved 180 calendar days after NTP

3. Final Completion to be achieved 30 calendar days after Substantial Completion

IX. Liquidated Damages

• $1,500 per day per the Invitation to Bid

X. Addenda

No anticipated addenda at this time. An addendum is anticipated after Question Due date of May 12th if necessary.

XI. Permits:

Contractor shall pay for and obtain all permits not obtained by the owner required to complete the work. Refer to Section 01160 of the technical specs.

XII. Airport Safety, Security, Work Areas

• Safety and security is a primary concern for airport projects.

• Access to airport comes from S Mulino Road and S Landing Way to S Airport

Road north of proposed hangar location.

• No work can occur without the Engineer’s project representative or an Airport representative present. If subcontractors are working, a representative of the prime contractor shall be on site.

• Section 01160 of the specifications contains additional safety provisions and requirements. This includes the use and placement of low-level barricades, tubular markers, airport radios, checkered flags, rotating beacons on vehicles, etc.

• Section 01406 describes staking requirements for work areas.

• Drawing G-04 show work area limits and describe their requirements.

• Airport security is to be maintained throughout construction at main gate on S

Airport Road and temporary secondary construction access directly onto S

Mulino Road.

• Staging areas, haul routes and project access points are shown on G-04.

• Refer to Drawings G-04 and G-05 for work area requirements and restrictions.

Work Area Phasing:

• Each Phase shall be completed as a single complete stage.

• Phase 0 shall be completed within 90 continuous calendar days.

• Phase 1 shall be completed within 180 continuous calendar days.

Runway or Taxiway Closure Schedule:

• None anticipated for this project.

As required in Section 01160 of the General Requirements, the Contractor shall submit a proposed schedule for completion of the work 5-days prior to the pre-construction conference in order to allow the ODAV to coordinate notification with airport users.

XIII. Construction Staking

Construction staking shall be performed by the Contractor. Control monuments have been established. Refer to Section 01406. Contractor shall do all staking. Staking is anticipated to include, but is not limited to:

• Hangar layout

• Grading and asphalt grading

• Storm layout and stormwater facility

XIV. Quantities

• Quantities will be reviewed in the field with RPR/Inspector daily.

• Quantities developed may be slightly different from current existing conditions.

As a result, quantities may need to be revised during construction.

XV. Erosion Control

• Sediment fence around boundary and catch basin inlet protection per EC-01.

• Erosion control plans are provided per EC-01, EC-02, EC-03, and EC-04.

XVI. Questions?

Q1: Is there or will there be a PGE plan to supplement the project?

A1: The project team has coordinated with PGE on the project scope. A PGE plan is in process and will be supplied prior to or during construction.

Q2: Is there an anticipation for the existing power service from the PGE pole to the existing transformer to be increased? Will this require additional conduits from the existing pole to the existing transformer?

A2: It is not anticipated for the existing power service to be increased from the PGE pole to the existing transformer. The existing conduits should be of sufficient size for a minor increase in capacity if needed. PGE will review the building submittal with the final electrical loading to determine if any additional capacity increase is required.

Q3: Does the new hangar require separate communications lines for the hangar?

A3: After discussions with ODAV, the State would like a communication line to be supplied to the new hangar building for future security camera usage. There is an existing communication pedestal adjacent to the PGE power pole to install a service from.

Q4: Does the new hangar need security cameras similar to the existing hangars?

A4: ODAV does not require security cameras installed with the new hangar building. However, the State would like electrical power and data to be supplied for cameras to be installed in the future. This would include exterior electrical outlets for cameras at the building corners and conduit to route the data line.

Q5: Does the new hangar fire panel need to be connected to the existing hangar?

A5: No, the new hangar fire panel does not need to be connected to the existing hangar.

Q6: Does the State want the color of the exterior to match the existing hangars?

A6: Yes, the State does want the exterior to match the existing hangars.

Q7: What does the contractor need to provide with building permit submittal? Is the hangar to be a prefabricated building? Structural design of the slab?

A7: Per Specification 13 34 10, the hangar building submittal includes the foundation, slab, and prefabricated metal building design. In discussions with several prefabricated metal building hangar suppliers, they do not supply a structural design for the slab and foundation. Structural calculations and design for the foundation and slab is to be designed by the Contractor. ITB

Attachment G is the Geotechnical Report for the project with recommendations and information for the slab, foundation, and base rock.

Q8: Who will the permitting be through for this project?

A8: The permitting for the Hangar will be through Clackamas County. This will include reviews by the Mollala Fire District and Water Environment Services (WES).

Q9: Has the site gone through the permitting process?

A9: No, the hangar site has not gone through the Development Permit permitting process and will be included with the Building Permit process.

Q10: Will Century West be involved in the permitting process if questions come up during the permit review?

A10: Yes, Century West will support the permitting process by the Contractor with Clackamas

County.

Q11: If an issue arises during the permitting process that will require longer than 90 days to obtain the permit, will there be a time allowance?

A11: Yes, if an unanticipated issue arises during the permitting process which will require longer than 90 days for obtaining the permit the timeline for the permitting will be extended.

Q12: Are there contaminated soils on the site?

A12: The Geotechnical Investigation did not find any contaminated soils on the site and the

State is not aware of any contaminated soils on the airport.

Q13: Will the hangar impact the landscape berm?

A13: Yes, the landscape berm will be impacted by the hangar project. A portion of the berm will need to be removed and regraded to provide clearance and drainage away from the hangar per

Sheet C-08.

Q13: Will trucks be allowed to traverse the taxilanes during the project?

A13: The airport will remain active during the construction of the hangar. To minimize interaction and potential safety issues with the airport operations area (AOA), the security entrance off S Mulino Road north of the hangar should be utilized for truck traffic to the greatest extent possible. Trucks can traverse the taxilanes during the project with flagging or escorting in the AOA. Please note the taxilane pavement sections are not designed for heavy traffic loadings (approximately 3” of asphalt over 6-7 inches of aggregate base), and any damage resulting from use of those pavements by the contractor will need to be repaired at the

Contractor’s expense.

Q14: Can steel interior walls be substituted for drywall?

A14: Substitution of steel interior walls may be requested post-bid. Contractor will need to provide details on the proposed steel interior walls at such time.

Q15: Is on-site disposal of excavated materials allowed? If so, has a dump site been identified?

A15: The airport has a large amount of wetlands on the site and east of the hangar is the skydiver landing zone requiring a flat open area for safe landings. As a result, all excavated material is planned to be hauled off the site.

Mulino State Airport – Hangar and Waterline Improvements Project Pre-Bid Conference (Voluntary)

Date & Time: May 6, 2026, 10:00 AM Location: Electronic (MS Teams)

Attendees

1. Robert West

2. Cody Line

3. Chet Line

4. Trevor Thibert

5. Kris Brown

6. Che Green

7. Garrett Kitchen

8. Travis Boling

9. Lisa Jackson

10. Karl Knoppala

11. Zach

12. Chris Camache

13. Bailey Duhrkoop

14. Kevin Beede

15. Doug Berger

16. Javier Iboy

Salem Fire Alarm C4 C4 Cornice

CRW

Green Mountain Ex.

Route 66 Elect.

K&E Excavating 2KG Contractors Westmore Const.

Colton Construction Peak Electric ASA Construction Boss Excavating LLC PHI Construction Walen Contruction