Mt_Talbert_Paving_Project_Bid Analysis_Comparison.xlsx

XLSX spreadsheet 35 KB Posted

Attached to
BID# 2025-52 Mount Talbert Paving Project
Solicitation number
S-C01010-00013918
Issued by
Clackamas County, Oregon

About this file

The file is a bid tabulation and price comparison spreadsheet for the Mount Talbert Paving Project (Bid #2025-52) issued by Clackamas County, Oregon. The project involves roadway resurfacing across approximately 1.2 miles of twelve urban local roads, including SE 124th Ave, SE 125th Ave, and SE 126th Ave. Key deliverables include placing 4,700 tons of asphalt, completing 23,325 square yards of cold plane pavement removal, performing pavement repairs of varying depths, constructing one concrete curb ramp, and implementing temporary work zone traffic control measures. Electronic proposal submissions are due by June 11, 2025, at 2:00 PM Pacific Time, with an anticipated substantial completion date of September 12, 2025, and a final completion date of December 31, 2025.

The engineer's estimated project cost is $973,000.00, with prevailing wage rates applicable due to the project's compensation exceeding $50,000. The bid tabulation shows multiple contractors submitted bids, including Eagle-Elsner, Inc., KNL Industries, Inc., Knife River Corp., and Northwest North Santiam Paving, with total bid amounts ranging from $780,942.90 to $1,102,322.00. The county encourages participation from minority, women, and emerging small businesses and requires bidders to possess a valid Oregon Construction Contractors Board registration. Bidders must submit performance and payment bonds and comply with disadvantaged enterprise participation guidelines. The project will be funded through local county infrastructure budgets, with an emphasis on transparent, competitive bidding and inclusive contracting practices.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Compare to Estimate Mt Talbert Paving Project Estimate vs. Low Bid

Engineer's EstimateKNL Industries, Inc.Comparison (total price)Average of the Bids
Bid ItemUnitQuantityUnit PriceTotal PriceUnit PriceTotal PriceMaximumMinimumAverage Unit PriceAverage Total
101EXTRA WORK DONE ON FORCE ACCOUNT BASISLS1$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00
102MOBILIZATIONLS1$ 67,000.00$ 67,000.00$ 10,000.00$ 10,000.00$ 67,000.00$ 10,000.00$ 71,041.90$ 71,041.90
103TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 124TH AVELS1$ 5,000.00$ 5,000.00$ 3,000.00$ 3,000.00$ 5,000.00$ 3,000.00$ 5,232.50$ 5,232.50
104TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 125TH AVELS1$ 5,000.00$ 5,000.00$ 3,000.00$ 3,000.00$ 5,000.00$ 3,000.00$ 5,482.50$ 5,482.50
105TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE OPAL WAYLS1$ 2,000.00$ 2,000.00$ 3,000.00$ 3,000.00$ 3,000.00$ 2,000.00$ 3,107.50$ 3,107.50
106TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE MATHER RDLS1$ 5,000.00$ 5,000.00$ 3,000.00$ 3,000.00$ 5,000.00$ 3,000.00$ 3,107.50$ 3,107.50
107TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 126TH AVELS1$ 5,000.00$ 5,000.00$ 3,000.00$ 3,000.00$ 5,000.00$ 3,000.00$ 5,107.50$ 5,107.50
108TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE HURON STLS1$ 5,000.00$ 5,000.00$ 3,000.00$ 3,000.00$ 5,000.00$ 3,000.00$ 5,107.50$ 5,107.50
109TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 124TH PLLS1$ 1,000.00$ 1,000.00$ 3,000.00$ 3,000.00$ 3,000.00$ 1,000.00$ 3,032.50$ 3,032.50
110TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 128TH AVELS1$ 5,000.00$ 5,000.00$ 3,000.00$ 3,000.00$ 5,000.00$ 3,000.00$ 5,107.50$ 5,107.50
111TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE SONOMA STLS1$ 1,000.00$ 1,000.00$ 2,500.00$ 2,500.00$ 2,500.00$ 1,000.00$ 2,907.50$ 2,907.50
112TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE DERRY LNLS1$ 2,000.00$ 2,000.00$ 2,500.00$ 2,500.00$ 2,500.00$ 2,000.00$ 3,857.50$ 3,857.50
113TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE MARK KELLY CTLS1$ 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$ 3,500.00$ 2,000.00$ 3,357.50$ 3,357.50
114TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE HAROLD CTLS1$ 1,000.00$ 1,000.00$ 3,000.00$ 3,000.00$ 3,000.00$ 1,000.00$ 3,182.50$ 3,182.50
115TEMPORARY PROJECT INFORMATION SIGNSSQFT150$ 50.00$ 7,500.00$ 35.00$ 5,250.00$ 7,500.00$ 5,250.00$ 30.78$ 4,616.25
116EROSION CONTROL PLANLS1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,265.00$ 5,265.00
117POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 500.00$ 500.00$ 1,000.00$ 500.00$ 652.75$ 652.75
118CONSTRUCTION SURVEY WORKLS1$ 8,000.00$ 8,000.00$ 1,000.00$ 1,000.00$ 8,000.00$ 1,000.00$ 5,895.00$ 5,895.00
119REMOVAL OF SURFACINGS FOR CURB RAMP CONSTRUCTIONSQTD100$ 17.00$ 1,700.00$ 25.00$ 2,500.00$ 2,500.00$ 1,700.00$ 28.20$ 2,820.00
12012 INCH SUBGRADE STABILIZATIONSQYD250$ 44.00$ 11,000.00$ 50.00$ 12,500.00$ 12,500.00$ 11,000.00$ 61.00$ 15,250.00
121DRAINAGE CURBSFOOT35$ 25.00$ 875.00$ 50.00$ 1,750.00$ 1,750.00$ 875.00$ 36.50$ 1,277.50
122MIONOR ADJUSTMENT OF MANHOLE - METHOD CEACH1$ 500.00$ 500.00$ 2,500.00$ 2,500.00$ 2,500.00$ 500.00$ 3,320.00$ 3,320.00
123INSTALL MONUMENT BOXESEACH1$ 1,000.00$ 1,000.00$ 750.00$ 750.00$ 1,000.00$ 750.00$ 1,280.00$ 1,280.00
124RECONDITION EXISTING ROADWAYSQYD22,600$ 4.00$ 90,400.00$ 1.25$ 28,250.00$ 90,400.00$ 28,250.00$ 1.24$ 27,967.50
125COLD PLANE PAVEMENT REMOVAL, 1 1/2-2 INCHES DEEPSQYD64$ 5.00$ 320.00$ 2.70$ 172.80$ 320.00$ 172.80$ 20.35$ 1,302.24
126COLD PLANE PAVEMENT REMOVAL, 1 1/2 INCHES DEEPSQYD1,022$ 5.00$ 5,110.00$ 2.70$ 2,759.40$ 5,110.00$ 2,759.40$ 5.58$ 5,697.65
127COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEPSQYD8,383$ 5.00$ 41,915.00$ 2.70$ 22,634.10$ 41,915.00$ 22,634.10$ 4.21$ 35,313.39
128COLD PLANE PAVEMENT REMOVAL, 3 INCHES DEEPSQYD10,119$ 5.00$ 50,595.00$ 2.70$ 27,321.30$ 50,595.00$ 27,321.30$ 5.73$ 57,931.27
129COLD PLANE PAVEMENT REMOVAL, 4 INCHES DEEPSQYD3,739$ 5.00$ 18,695.00$ 2.70$ 10,095.30$ 18,695.00$ 10,095.30$ 6.49$ 24,256.76
130AGGREGATE BASE, 3/4"-0TON20$ 98.00$ 1,960.00$ 100.00$ 2,000.00$ 2,000.00$ 1,960.00$ 95.00$ 1,900.00
131LEVEL 2, 1/2 INCH ACP MIXTURETON4,700$ 119.00$ 559,300.00$ 113.00$ 531,100.00$ 559,300.00$ 531,100.00$ 106.50$ 500,550.00
1323 INCH ASPHALT CONCRETE PAVEMENT REPAIRSQYD40$ 75.00$ 3,000.00$ 50.00$ 2,000.00$ 3,000.00$ 2,000.00$ 64.50$ 2,580.00
1338 INCH ASPHALT CONCRETE PAVEMENT REPAIRSQYD580$ 25.00$ 14,500.00$ 40.00$ 23,200.00$ 23,200.00$ 14,500.00$ 55.63$ 32,262.50
134EXTRA FOR SPOT GRIND AND INLAYSSQYD500$ 13.00$ 6,500.00$ 15.00$ 7,500.00$ 7,500.00$ 6,500.00$ 17.75$ 8,875.00
135EXTRA FOR CURB RAMP ASPHALT PLUGSQFT124$ 20.00$ 2,480.00$ 5.00$ 620.00$ 2,480.00$ 620.00$ 11.13$ 1,379.50
136CONCRETE CURB, CURB AND GUTTERFOOT58$ 90.00$ 5,220.00$ 50.00$ 2,900.00$ 5,220.00$ 2,900.00$ 70.50$ 4,089.00
137CONCRETE WALKSSQFT258$ 21.00$ 5,418.00$ 30.00$ 7,740.00$ 7,740.00$ 5,418.00$ 19.28$ 4,972.95
138EXTRA FOR NEW CURB RAMPSEACH1$ 2,000.00$ 2,000.00$ 2,500.00$ 2,500.00$ 2,500.00$ 2,000.00$ 1,940.00$ 1,940.00
139TRUNCATED DOMES ON NEW SURFACESSQFT28$ 42.00$ 1,176.00$ 50.00$ 1,400.00$ 1,400.00$ 1,176.00$ 36.75$ 1,029.00
140PAVEMENT BAR, TYPE B-HSSQFT90$ 25.00$ 2,250.00$ 50.00$ 4,500.00$ 4,500.00$ 2,250.00$ 30.75$ 2,767.50
141REMOVE AND INSTALL EXISTING SIGNS ON EXISTING SIGN SUPPORTSLS1$ 1,000.00$ 1,000.00$ 3,500.00$ 3,500.00$ 3,500.00$ 1,000.00$ 1,500.00$ 1,500.00
142REMOVE AND INSTALL EXISTING SIGNS ON NEW SIGN SUPPORTSLS1$ 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$ 3,500.00$ 2,000.00$ 1,862.50$ 1,862.50
143ROADSIDE RESTORATIONLS1$ 1,000.00$ 1,000.00$ 3,000.00$ 3,000.00$ 3,000.00$ 1,000.00$ 2,500.00$ 2,500.00
144REMOVING AND REBUILDING FENCEFOOT35$ 150.00$ 5,250.00$ 200.00$ 7,000.00$ 7,000.00$ 5,250.00$ 143.75$ 5,031.25
Total$ 972,664.00Total$ 780,942.90Average Total$ 895,716.42

Bid Tabs

Mt Talbert Paving Project Bid Tabulations
Eagle-Elsner, Inc.KNL Industries, Inc.Knife River Corp. NorthwestNorth Santiam PavingLow/High AnalysisAverage of the Bids
Bid ItemUnitQuantityUnit PriceTotalUnit PriceTotalUnit PriceTotalUnit PriceTotalLow UPHigh UPAverage Unit PriceAverage Total
101EXTRA WORK DONE ON FORCE ACCOUNT BASISLS1$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00
102MOBILIZATIONLS1$ 46,917.60$ 46,917.60$ 10,000.00$ 10,000.00$ 65,000.00$ 65,000.00$ 162,250.00$ 162,250.00$ 10,000.00$ 162,250.00$ 71,041.90$ 71,041.90
103TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 124TH AVELS1$ 5,000.00$ 5,000.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 10,000.00$ 10,000.00$ 2,930.00$ 10,000.00$ 5,232.50$ 5,232.50
104TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 125TH AVELS1$ 6,000.00$ 6,000.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 10,000.00$ 10,000.00$ 2,930.00$ 10,000.00$ 5,482.50$ 5,482.50
105TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE OPAL WAYLS1$ 1,500.00$ 1,500.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 5,000.00$ 5,000.00$ 1,500.00$ 5,000.00$ 3,107.50$ 3,107.50
106TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE MATHER RDLS1$ 1,500.00$ 1,500.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 5,000.00$ 5,000.00$ 1,500.00$ 5,000.00$ 3,107.50$ 3,107.50
107TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 126TH AVELS1$ 4,500.00$ 4,500.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 10,000.00$ 10,000.00$ 2,930.00$ 10,000.00$ 5,107.50$ 5,107.50
108TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE HURON STLS1$ 4,500.00$ 4,500.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 10,000.00$ 10,000.00$ 2,930.00$ 10,000.00$ 5,107.50$ 5,107.50
109TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 124TH PLLS1$ 1,200.00$ 1,200.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 5,000.00$ 5,000.00$ 1,200.00$ 5,000.00$ 3,032.50$ 3,032.50
110TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE 128TH AVELS1$ 4,500.00$ 4,500.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 10,000.00$ 10,000.00$ 2,930.00$ 10,000.00$ 5,107.50$ 5,107.50
111TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE SONOMA STLS1$ 1,200.00$ 1,200.00$ 2,500.00$ 2,500.00$ 2,930.00$ 2,930.00$ 5,000.00$ 5,000.00$ 1,200.00$ 5,000.00$ 2,907.50$ 2,907.50
112TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE DERRY LNLS1$ 5,000.00$ 5,000.00$ 2,500.00$ 2,500.00$ 2,930.00$ 2,930.00$ 5,000.00$ 5,000.00$ 2,500.00$ 5,000.00$ 3,857.50$ 3,857.50
113TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE MARK KELLY CTLS1$ 2,000.00$ 2,000.00$ 3,500.00$ 3,500.00$ 2,930.00$ 2,930.00$ 5,000.00$ 5,000.00$ 2,000.00$ 5,000.00$ 3,357.50$ 3,357.50
114TEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETE: SE HAROLD CTLS1$ 1,800.00$ 1,800.00$ 3,000.00$ 3,000.00$ 2,930.00$ 2,930.00$ 5,000.00$ 5,000.00$ 1,800.00$ 5,000.00$ 3,182.50$ 3,182.50
115TEMPORARY PROJECT INFORMATION SIGNSSQFT150$ 28.00$ 4,200.00$ 35.00$ 5,250.00$ 18.10$ 2,715.00$ 42.00$ 6,300.00$ 18.10$ 42.00$ 30.78$ 4,616.25
116EROSION CONTROL PLANLS1$ 9,500.00$ 9,500.00$ 5,000.00$ 5,000.00$ 2,560.00$ 2,560.00$ 4,000.00$ 4,000.00$ 2,560.00$ 9,500.00$ 5,265.00$ 5,265.00
117POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 500.00$ 500.00$ 811.00$ 811.00$ 300.00$ 300.00$ 300.00$ 1,000.00$ 652.75$ 652.75
118CONSTRUCTION SURVEY WORKLS1$ 9,000.00$ 9,000.00$ 1,000.00$ 1,000.00$ 6,330.00$ 6,330.00$ 7,250.00$ 7,250.00$ 1,000.00$ 9,000.00$ 5,895.00$ 5,895.00
119REMOVAL OF SURFACINGS FOR CURB RAMP CONSTRUCTIONSQTD100$ 25.00$ 2,500.00$ 25.00$ 2,500.00$ 31.80$ 3,180.00$ 31.00$ 3,100.00$ 25.00$ 31.80$ 28.20$ 2,820.00
12012 INCH SUBGRADE STABILIZATIONSQYD250$ 45.00$ 11,250.00$ 50.00$ 12,500.00$ 84.00$ 21,000.00$ 65.00$ 16,250.00$ 45.00$ 84.00$ 61.00$ 15,250.00
121DRAINAGE CURBSFOOT35$ 50.00$ 1,750.00$ 50.00$ 1,750.00$ 16.00$ 560.00$ 30.00$ 1,050.00$ 16.00$ 50.00$ 36.50$ 1,277.50
122MIONOR ADJUSTMENT OF MANHOLE - METHOD CEACH1$ 4,000.00$ 4,000.00$ 2,500.00$ 2,500.00$ 3,780.00$ 3,780.00$ 3,000.00$ 3,000.00$ 2,500.00$ 4,000.00$ 3,320.00$ 3,320.00
123INSTALL MONUMENT BOXESEACH1$ 1,000.00$ 1,000.00$ 750.00$ 750.00$ 2,620.00$ 2,620.00$ 750.00$ 750.00$ 750.00$ 2,620.00$ 1,280.00$ 1,280.00
124RECONDITION EXISTING ROADWAYSQYD22,600$ 1.50$ 33,900.00$ 1.25$ 28,250.00$ 1.20$ 27,120.00$ 1.00$ 22,600.00$ 1.00$ 1.50$ 1.24$ 27,967.50
125COLD PLANE PAVEMENT REMOVAL, 1 1/2-2 INCHES DEEPSQYD64$ 9.50$ 608.00$ 2.70$ 172.80$ 52.19$ 3,340.16$ 17.00$ 1,088.00$ 2.70$ 52.19$ 20.35$ 1,302.24
126COLD PLANE PAVEMENT REMOVAL, 1 1/2 INCHES DEEPSQYD1,022$ 4.50$ 4,599.00$ 2.70$ 2,759.40$ 10.10$ 10,322.20$ 5.00$ 5,110.00$ 2.70$ 10.10$ 5.58$ 5,697.65
127COLD PLANE PAVEMENT REMOVAL, 2 INCHES DEEPSQYD8,383$ 4.40$ 36,885.20$ 2.70$ 22,634.10$ 3.75$ 31,436.25$ 6.00$ 50,298.00$ 2.70$ 6.00$ 4.21$ 35,313.39
128COLD PLANE PAVEMENT REMOVAL, 3 INCHES DEEPSQYD10,119$ 6.20$ 62,737.80$ 2.70$ 27,321.30$ 7.00$ 70,833.00$ 7.00$ 70,833.00$ 2.70$ 7.00$ 5.73$ 57,931.28
129COLD PLANE PAVEMENT REMOVAL, 4 INCHES DEEPSQYD3,739$ 8.60$ 32,155.40$ 2.70$ 10,095.30$ 7.65$ 28,603.35$ 7.00$ 26,173.00$ 2.70$ 8.60$ 6.49$ 24,256.76
130AGGREGATE BASE, 3/4"-0TON20$ 85.00$ 1,700.00$ 100.00$ 2,000.00$ 100.00$ 2,000.00$ 95.00$ 1,900.00$ 85.00$ 100.00$ 95.00$ 1,900.00
131LEVEL 2, 1/2 INCH ACP MIXTURETON4,700$ 96.00$ 451,200.00$ 113.00$ 531,100.00$ 105.00$ 493,500.00$ 112.00$ 526,400.00$ 96.00$ 113.00$ 106.50$ 500,550.00
1323 INCH ASPHALT CONCRETE PAVEMENT REPAIRSQYD40$ 100.00$ 4,000.00$ 50.00$ 2,000.00$ 48.00$ 1,920.00$ 60.00$ 2,400.00$ 48.00$ 100.00$ 64.50$ 2,580.00
1338 INCH ASPHALT CONCRETE PAVEMENT REPAIRSQYD580$ 27.00$ 15,660.00$ 40.00$ 23,200.00$ 62.50$ 36,250.00$ 93.00$ 53,940.00$ 27.00$ 93.00$ 55.63$ 32,262.50
134EXTRA FOR SPOT GRIND AND INLAYSSQYD500$ 9.00$ 4,500.00$ 15.00$ 7,500.00$ 17.00$ 8,500.00$ 30.00$ 15,000.00$ 9.00$ 30.00$ 17.75$ 8,875.00
135EXTRA FOR CURB RAMP ASPHALT PLUGSQFT124$ 6.00$ 744.00$ 5.00$ 620.00$ 13.50$ 1,674.00$ 20.00$ 2,480.00$ 5.00$ 20.00$ 11.13$ 1,379.50
136CONCRETE CURB, CURB AND GUTTERFOOT58$ 80.00$ 4,640.00$ 50.00$ 2,900.00$ 52.00$ 3,016.00$ 100.00$ 5,800.00$ 50.00$ 100.00$ 70.50$ 4,089.00
137CONCRETE WALKSSQFT258$ 15.00$ 3,870.00$ 30.00$ 7,740.00$ 17.10$ 4,411.80$ 15.00$ 3,870.00$ 15.00$ 30.00$ 19.28$ 4,972.95
138EXTRA FOR NEW CURB RAMPSEACH1$ 1,700.00$ 1,700.00$ 2,500.00$ 2,500.00$ 1,560.00$ 1,560.00$ 2,000.00$ 2,000.00$ 1,560.00$ 2,500.00$ 1,940.00$ 1,940.00
139TRUNCATED DOMES ON NEW SURFACESSQFT28$ 32.00$ 896.00$ 50.00$ 1,400.00$ 30.00$ 840.00$ 35.00$ 980.00$ 30.00$ 50.00$ 36.75$ 1,029.00
140PAVEMENT BAR, TYPE B-HSSQFT90$ 28.00$ 2,520.00$ 50.00$ 4,500.00$ 15.00$ 1,350.00$ 30.00$ 2,700.00$ 15.00$ 50.00$ 30.75$ 2,767.50
141REMOVE AND INSTALL EXISTING SIGNS ON EXISTING SIGN SUPPORTSLS1$ 250.00$ 250.00$ 3,500.00$ 3,500.00$ 1,500.00$ 1,500.00$ 750.00$ 750.00$ 250.00$ 3,500.00$ 1,500.00$ 1,500.00
142REMOVE AND INSTALL EXISTING SIGNS ON NEW SIGN SUPPORTSLS1$ 250.00$ 250.00$ 3,500.00$ 3,500.00$ 2,500.00$ 2,500.00$ 1,200.00$ 1,200.00$ 250.00$ 3,500.00$ 1,862.50$ 1,862.50
143ROADSIDE RESTORATIONLS1$ 1,800.00$ 1,800.00$ 3,000.00$ 3,000.00$ 2,200.00$ 2,200.00$ 3,000.00$ 3,000.00$ 1,800.00$ 3,000.00$ 2,500.00$ 2,500.00
144REMOVING AND REBUILDING FENCEFOOT35$ 125.00$ 4,375.00$ 200.00$ 7,000.00$ 120.00$ 4,200.00$ 130.00$ 4,550.00$ 120.00$ 200.00$ 143.75$ 5,031.25
Total$ 808,808.00Total$ 780,942.90Total$ 890,792.76Total$ 1,102,322.00Average$ 895,716.42