Manufacturing Qualification Requirements Summary
This is a Manufacturing Qualification Requirements document for an Accelerometer Assembly (P/N 16C0715-3, NSN 6680010397817WF) used in F-16 aircraft applications. The document establishes mandatory qualification standards that potential offerors must satisfy before becoming eligible for contract award. Offerors must complete ten primary qualification requirements: notify the appropriate government Small Business Office or contracting officer of intent to qualify; certify possession of required manufacturing, inspection, testing, and storage facilities; verify possession of a complete data package including Lockheed Martin drawing 16C0715 and all associated procedures and specifications; demonstrate manufacturing and process compliance with ESA-approved engineering data and Unique Identification (UID) requirements per DFARS 211.274; prepare and submit a qualification test plan for government approval detailing verification of all performance, environmental, mechanical, and quality assurance requirements; provide a pre-contract award qualification article at the offeror's expense for form, fit, and function evaluation; notify the government at least 30 days in advance of testing; and submit complete test reports to 416 SCMS/GUEAA for review and approval prior to contract award. The government retains the right to inspect testing processes and witness documented testing on-site.
The estimated cost for qualification testing and evaluation is $4,000.00, with an estimated completion timeline of 365 days based on the complexity of the Accelerometer Assembly. Offerors will receive notification of qualification article pass/fail results within 90 days of submission, though successful completion does not guarantee contract award. The document establishes that contract awards will not be delayed to allow vendors additional time to meet qualification standards. Additionally, six Source Qualification Waiver Criteria (QWC) are available for potential sources to apply for partial or complete waiver of qualification requirements: prior government or OEM supply certification; qualified on mirror-image articles; qualified on parent assemblies; qualified on earlier dash numbers of the same part number; qualified on similar or like items; or previously qualified sources that have undergone corporate transitions while maintaining equivalent facilities and personnel. Even if a waiver is granted, the government may require a post-contract award first article exhibit to verify production capability.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CPP.pdf | ||
| EDR.pdf | ||
| EDL.pdf | ||
| FATR.pdf | ||
| SPRHA426Q0470.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MANUFACTURING QUALIFICATION REQUIREMENTS
NSN: 6680010397817WF
P/N: 16C0715-3 Noun: Accelerometer Assembly Application: F-16
1-Oct-20 Section C 1/3
SECTION C:
1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE
a. Prequalification Notice/Sources Sought: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Accelerometer Assembly.
b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to manufacture, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.
c. Data Verification: The offeror must verify that he has a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum Lockheed Martin (81755) drawing 16C0715. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.
d. Manufacture/Process Verification: The offeror must manufacture this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 416 SCMS/GUEAA. The offeror shall also identify its sources for materials and its standards for internally used processes.
e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 416 SCMS/GUEAA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing 16C0715. After completion of the approved qualification testing, the offeror shall be required to submit a complete test report of the results to 416 SCMS/GUEAA for their review and approval prior to the contract award. The government retains the right to exercise the option to inspect the testing processes, including on-site witnessing of any or all documented testing. To allow accomplishing this, the offeror shall notify the government at least 30 days in advance of the occurrence of any testing that will be used as a basis for qualification. The offeror’s facilities shall be made available for government inspection during these tests.
f. Qualification Article Verification: The offeror must provide, at their own expense, a pre-contract award qualification article for evaluation by the government. This article must comply with all of the requirements of Drawing 16C0715. This article shall be subjected to a form, fit, and function evaluation to demonstrate compatibility with the weapon system and to evaluate the
P/N: 16C0715-3
1-Oct-20 Section C 2/3 manufacturing capability of the offeror. Offerors will be notified whether or not their qualification article passed or failed the required qualification testing within 90 days of submitting a product for qualification testing. Note that successful completion of the qualification testing does not guarantee any contract award. If the offeror is deemed qualified and awarded the contract, a post-contract award first article exhibit may be required to verify production capability.
g. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified: $4,000.00.
h. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 365 days. This is based on complexity of the Accelerometer Assembly and other factors.
i. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.
j. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved source for this item. Approval, however, does not guarantee subsequent contract award.
P/N: 16C0715-3
1-Oct-20 Section C 3/3
2. SOURCE QUALIFICATION WAIVER REQUIREMENTS
Sources who meet any of the following source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:
a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).
b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.
c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.
d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.
e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.
f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the manufacturing process.