Mott PCC - New Start 11.10.25.pdf
PDF 817 KB Posted
- Attached to
- Prahl College Center Testing & Inspection
- Solicitation number
- RFP-KD-1025-Prahl-Testing&Inspection
- Issued by
- Genesee County, Michigan
About this file
This is a detailed construction project schedule for the Mott Prahl College Center, developed by Clark construction, with a comprehensive timeline spanning from January 31, 2025, to August 23, 2027. The project involves a multi-level renovation and construction effort that includes pre-construction, design, bidding, procurement, and construction phases across various building levels including lower, entry, and upper levels, as well as a penthouse/roof section. Key milestones include bid preparation and submission between July and November 2025, construction start on November 10, 2025, and systematic progression through demolition, exterior facade work, site improvements, and interior build-out of different building sections. The project involves multiple complex stages such as MEP (Mechanical, Electrical, Plumbing) installations, framing, ceiling work, painting, flooring, and final closeout.
The schedule meticulously breaks down construction activities by building level and trade, with specific durations for tasks like abatement, demolition, mechanical/electrical rough-ins, equipment setting, and final inspections. Each level (lower, entry, upper) follows a similar phased approach with consistent workflow: metals work, priority wall framing, MEP rough-ins, overhead and ceiling installations, wall framing, drywall, painting, flooring, and final connections. The project concludes with a 10-day final inspection and turnover period, with substantial completion set for August 23, 2027. The timeline demonstrates a highly structured, sequenced approach to construction that allows for coordination across different trades and building sections while maintaining a clear critical path.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 21104 MCC Prahl BIDS-Drawings.pdf | ||
| 21104-1000 MCC Prahl Project Manual BIDS.pdf | ||
| Mott Logistics.pdf | ||
| RFP-KD-1025-Prahl-Testing_Inspection.pdf.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Description Original
Duration Start Finish
Mott Prahl College Center 658 02/03/25 08/23/27
Pre-Construction 536 02/03/25 03/04/27
Design 121 02/03/25 07/21/25
Plan Submission / Permitting 1 07/22/25 07/22/25
Bid and Award 79 07/22/25 11/07/25
100 Prepare Bid Documents 14 07/22/25 08/08/25
110 Out to Bid 15 08/11/25 08/29/25
120 Pre-Bid Meeting 1 08/19/25 08/19/25
130 RFI Cut-off 1 08/22/25 08/22/25
140 Bids Due 1 08/29/25 08/29/25
150 Post-Bid Interviews 10 09/02/25 09/15/25
160 LORs 4 09/16/25 09/19/25
170 Mott Board Approval 1 09/22/25 09/22/25
180 Contract Issuance 10 09/23/25 10/06/25
190 Owner Moveout 34 09/23/25 11/07/25
Procurement and Deliveries 350 10/21/25 03/04/27
200 Procure/Submit Electrical Equipment Submittals 350 10/21/25 03/04/27
210 Procure/Submit HVAC Equipment Submittals 110 10/21/25 03/30/26
Construction 458 11/10/25 08/23/27
Construction 458 11/10/25 08/23/27
220 Construction Start 0 11/10/25
229 Building Scan 10 02/23/26 03/06/26
230 BIM Coordination 100 03/09/26 07/24/26
Abatement & Demolition 100 11/10/25 04/03/26
240 Abatement 60 11/10/25 02/06/26
250 Demolition (Elevation Top-Down-Interior Bottom-up) 60 01/12/26 04/03/26
Exterior Facade 351 01/12/26 05/20/27
260 Install Temp Enclosure Panels 80 01/12/26 05/01/26
270 Cold-Form Framing & Sheathing 50 02/23/26 05/01/26
280 Foundations / Insulation / Waterproofing 20 04/06/26 05/01/26
290 AVB / Masonry / CW / Metal Panels 90 04/06/26 08/07/26
300 Roofing (Demo & Install New) 25 04/27/26 05/29/26
301 Final Roof Membrane 10 05/07/27 05/20/27
Site 407 11/10/25 06/11/27
310 Temp Fencing / Tree Protection 5 11/10/25 11/14/25
320 Laydown & Hoist Areas - Site Logistics 10 11/17/25 12/02/25
330 Site Utilities 20 12/03/25 01/02/26
340 Exterior Improvements (Spring Start/Frost Laws) 30 05/03/27 06/11/27
2025 2026 2027
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
P ro je ct
S ta rt
P ro je ct
F in is h
Prepare Bid Documents
Out to Bid
Pre-Bid Meeting
RFI Cut-off
Bids Due
Post-Bid Interviews
LORs
Mott Board Approval
Contract Issuance
Owner Moveout
Procure/Submit Electrical Equipment Submittals
Procure/Submit HVAC Equipment Submittals
Construction Start
Building Scan
BIM Coordination
Abatement
Demolition (Elevation Top-Down-Interior Bottom-up)
Install Temp Enclosure Panels
Cold-Form Framing & Sheathing
Foundations / Insulation / Waterproofing
AVB / Masonry / CW / Metal Panels
Roofing (Demo & Install New)
Final Roof Membrane
Temp Fencing / Tree Protection
Laydown & Hoist Areas - Site Logistics
Site Utilities
Exterior Improvements (Spring Start/F
Start Date: 01/31/25
Finish Date: 08/23/27
Data Date: 12/30/24
Run Date: 09/19/25
Mott PCC - New Start 11.10.25.ppx
Page 1A
Duration Start Finish
Lower Level West Side 298 02/09/26 04/05/27
350 Underground Plumbing 30 02/09/26 03/20/26
360 Backfill / Pour SOG / Cure time 10 03/23/26 04/03/26
370 Misc. Metals (as required) 170 04/06/26 12/01/26
380 Priority walls frame, top-out and paint (All Corridors) 25 04/06/26 05/08/26
390 MEP stub "in / out" for topping out 25 04/06/26 05/08/26
400 MEP shafts and risers (coordinate with priority walls) 80 04/06/26 07/24/26
410 MEP Overhead & Above Ceilings 35 05/11/26 06/26/26
420 All Trades Overhead & Above Ceilings Installations 35 05/11/26 06/26/26
430 Overhead & Above ceiling inspections 1 06/29/26 06/29/26
440 Stud / Frame Remaining Walls & Hard Lids 35 06/30/26 08/17/26
450 MEP in walls / to framing 35 07/07/26 08/24/26
460 All Trades in walls / to framing 35 07/07/26 08/24/26
470 In wall and lid inspections 1 08/25/26 08/25/26
480 Hang, tape, finish drywall 35 08/26/26 10/13/26
490 Prime paint / First Coat / Wallcoverings (coordinate) 25 10/14/26 11/17/26
500 Hard Tile 35 09/30/26 11/17/26
510 Install acoustical grid, cuts and only pads for MEP to grid 20 10/28/26 11/24/26
520 MEP to grid 15 11/04/26 11/24/26
530 Permanent Lighting 10 11/18/26 12/03/26
540 All flooring required beneath Div. 6,8,10,11,12,13 work 20 11/25/26 12/24/26
550 Division 6,8,10,11,12,13 Work 25 12/28/26 01/29/27
560 MEP Final Connections 25 01/04/27 02/05/27
570 MEP final overhead & above ceiling inspections 1 02/08/27 02/08/27
580 Ceiling Pads (Contingent on Balancing) 15 02/09/27 03/01/27
590 Doors/Hardware 15 02/16/27 03/08/27
600 Finish Paint 15 02/23/27 03/15/27
610 Carpet and remaining flooring 15 03/02/27 03/22/27
620 MEP Finishes 15 03/09/27 03/29/27
630 Work List / Punchlist 15 03/16/27 04/05/27
Lower Level East Side 373 02/09/26 07/19/27
635 Service Elevator 2 Demolition and Construction (No interior finishes) 25 03/30/26 05/01/26
636 Passenger Elevator 1 Demolition and Construction (Includes Finishes) 30 05/04/26 06/12/26
637 Service Elevator 2 Interior Finishes 5 07/13/27 07/19/27
640 Underground Plumbing 30 02/09/26 03/20/26
650 Backfill / Pour SOG / Cure time 10 03/23/26 04/03/26
660 Misc. Metals (as required) 170 05/04/26 12/30/26
670 Priority walls frame, top-out and paint (All Corridors) 25 05/04/26 06/05/26
680 MEP stub "in / out" for topping out 25 05/04/26 06/05/26
690 MEP shafts and risers (coordinate with priority walls) 80 05/04/26 08/21/26
700 MEP Overhead & Above Ceilings 35 06/08/26 07/24/26
710 All Trades Overhead & Above Ceilings Installations 35 06/08/26 07/24/26
2025 2026 2027
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
P ro je ct
S ta rt
P ro je ct
F in is h
Underground Plumbing
Backfill / Pour SOG / Cure time
Misc. Metals (as required)
Priority walls frame, top-out and paint (All Corridors)
MEP stub "in / out" for topping out
MEP shafts and risers (coordinate with priority walls)
MEP Overhead & Above Ceilings
All Trades Overhead & Above Ceilings Installations
Overhead & Above ceiling inspections
Stud / Frame Remaining Walls & Hard Lids
MEP in walls / to framing
All Trades in walls / to framing
In wall and lid inspections
Hang, tape, finish drywall
Prime paint / First Coat / Wallcoverings (coordinate)
Hard Tile
Install acoustical grid, cuts and only pads for MEP to grid
MEP to grid
Permanent Lighting
All flooring required beneath Div. 6,8,10,11,12,13 work
Division 6,8,10,11,12,13 Work
MEP Final Connections
MEP final overhead & above ceiling inspections
Ceiling Pads (Contingent on Balancing)
Doors/Hardware
Finish Paint
Carpet and remaining flooring
MEP Finishes
Work List / Punchlist
Service Elevator 2 Demolition and Construction (No interior finishes)
Passenger Elevator 1 Demolition and Construction (Includes Finishes)
Service Elevator 2 Interior Fini
Underground Plumbing
Backfill / Pour SOG / Cure time
Misc. Metals (as required)
Priority walls frame, top-out and paint (All Corridors)
MEP stub "in / out" for topping out
MEP shafts and risers (coordinate with priority walls)
MEP Overhead & Above Ceilings
All Trades Overhead & Above Ceilings Installations
Start Date: 01/31/25
Finish Date: 08/23/27
Data Date: 12/30/24
Run Date: 09/19/25
Page 2A
Duration Start Finish
720 Overhead & Above ceiling inspections 1 07/27/26 07/27/26
730 Stud / Frame Remaining Walls & Hard Lids 35 07/28/26 09/14/26
740 MEP in walls / to framing 35 08/04/26 09/21/26
750 All Trades in walls / to framing 35 08/04/26 09/21/26
760 In wall and lid inspections 1 09/22/26 09/22/26
770 Hang, tape, finish drywall 35 09/23/26 11/10/26
780 Prime paint / First Coat / Wallcoverings (coordinate) 25 11/11/26 12/17/26
790 Hard Tile 35 10/28/26 12/17/26
800 Install acoustical grid, cuts and only pads for MEP to grid 20 11/25/26 12/24/26
810 MEP to grid 15 12/04/26 12/24/26
820 Permanent Lighting 10 12/18/26 01/01/27
830 All flooring required beneath Div. 6,8,10,11,12,13 work 20 12/28/26 01/22/27
840 Division 6,8,10,11,12,13 Work 25 01/25/27 02/26/27
850 MEP Final Connections 25 02/01/27 03/05/27
860 MEP final overhead & above ceiling inspections 1 03/08/27 03/08/27
870 Ceiling Pads (Contingent on Balancing) 15 03/09/27 03/29/27
880 Doors/Hardware 15 03/16/27 04/05/27
890 Finish Paint 15 03/23/27 04/12/27
900 Carpet and remaining flooring 15 03/30/27 04/19/27
910 MEP Finishes 15 04/06/27 04/26/27
920 Work List / Punchlist 15 04/13/27 05/03/27
Entry Level West Side 258 06/01/26 05/31/27
930 Misc. Metals (as required) 170 06/01/26 01/27/27
940 Priority walls frame, top-out and paint (All Corridors) 25 06/01/26 07/03/26
950 MEP stub "in / out" for topping out 25 06/01/26 07/03/26
960 MEP shafts and risers (coordinate with priority walls) 80 06/01/26 09/18/26
970 MEP Overhead & Above Ceilings 35 07/06/26 08/21/26
980 All Trades Overhead & Above Ceilings Installations 35 07/06/26 08/21/26
990 Overhead & Above ceiling inspections 1 08/24/26 08/24/26
1000 Stud / Frame Remaining Walls & Hard Lids 35 08/25/26 10/12/26
1010 MEP in walls / to framing 35 09/01/26 10/19/26
1020 All Trades in walls / to framing 35 09/01/26 10/19/26
1030 In wall and lid inspections 1 10/20/26 10/20/26
1040 Hang, tape, finish drywall 35 10/21/26 12/10/26
1050 Prime paint / First Coat / Wallcoverings (coordinate) 25 12/11/26 01/15/27
1060 Hard Tile 35 11/25/26 01/15/27
1070 Install acoustical grid, cuts and only pads for MEP to grid 20 12/28/26 01/22/27
1080 MEP to grid 15 01/04/27 01/22/27
1090 Permanent Lighting 10 01/18/27 01/29/27
1100 All flooring required beneath Div. 6,8,10,11,12,13 work 20 01/25/27 02/19/27
1110 Division 6,8,10,11,12,13 Work 25 02/22/27 03/26/27
1120 MEP Final Connections 25 03/01/27 04/02/27
2025 2026 2027
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
P ro je ct
S ta rt
P ro je ct
F in is h
Overhead & Above ceiling inspections
Stud / Frame Remaining Walls & Hard Lids
MEP in walls / to framing
All Trades in walls / to framing
In wall and lid inspections
Hang, tape, finish drywall
Prime paint / First Coat / Wallcoverings (coordinate)
Hard Tile
Install acoustical grid, cuts and only pads for MEP to grid
MEP to grid
Permanent Lighting
All flooring required beneath Div. 6,8,10,11,12,13 work
Division 6,8,10,11,12,13 Work
MEP Final Connections
MEP final overhead & above ceiling inspections
Ceiling Pads (Contingent on Balancing)
Doors/Hardware
Finish Paint
Carpet and remaining flooring
MEP Finishes
Work List / Punchlist
Misc. Metals (as required)
Priority walls frame, top-out and paint (All Corridors)
MEP stub "in / out" for topping out
MEP shafts and risers (coordinate with priority walls)
MEP Overhead & Above Ceilings
All Trades Overhead & Above Ceilings Installations
Overhead & Above ceiling inspections
Stud / Frame Remaining Walls & Hard Lids
MEP in walls / to framing
All Trades in walls / to framing
In wall and lid inspections
Hang, tape, finish drywall
Prime paint / First Coat / Wallcoverings (coordinate)
Hard Tile
Install acoustical grid, cuts and only pads for MEP to grid
MEP to grid
Permanent Lighting
All flooring required beneath Div. 6,8,10,11,12,13 work
Division 6,8,10,11,12,13 Work
MEP Final Connections
Start Date: 01/31/25
Finish Date: 08/23/27
Data Date: 12/30/24
Run Date: 09/19/25
Page 3A
Duration Start Finish
1130 MEP final overhead & above ceiling inspections 1 04/05/27 04/05/27
1140 Ceiling Pads (Contingent on Balancing) 15 04/06/27 04/26/27
1150 Doors/Hardware 15 04/13/27 05/03/27
1160 Finish Paint 15 04/20/27 05/10/27
1170 Carpet and remaining flooring 15 04/27/27 05/17/27
1180 MEP Finishes 15 05/04/27 05/24/27
1190 Work List / Punchlist 15 05/11/27 05/31/27
Entry Level East Side 258 06/29/26 06/28/27
1200 Misc. Metals (as required) 170 06/29/26 02/24/27
1210 Priority walls frame, top-out and paint (All Corridors) 25 06/29/26 07/31/26
1220 MEP stub "in / out" for topping out 25 06/29/26 07/31/26
1230 MEP shafts and risers (coordinate with priority walls) 80 06/29/26 10/16/26
1240 MEP Overhead & Above Ceilings 35 08/03/26 09/18/26
1250 All Trades Overhead & Above Ceilings Installations 35 08/03/26 09/18/26
1260 Overhead & Above ceiling inspections 1 09/21/26 09/21/26
1270 Stud / Frame Remaining Walls & Hard Lids 35 09/22/26 11/09/26
1280 MEP in walls / to framing 35 09/29/26 11/16/26
1290 All Trades in walls / to framing 35 09/29/26 11/16/26
1300 In wall and lid inspections 1 11/17/26 11/17/26
1310 Hang, tape, finish drywall 35 11/18/26 01/08/27
1320 Prime paint / First Coat / Wallcoverings (coordinate) 25 01/11/27 02/12/27
1330 Hard Tile 35 12/28/26 02/12/27
1340 Install acoustical grid, cuts and only pads for MEP to grid 20 01/25/27 02/19/27
1350 MEP to grid 15 02/01/27 02/19/27
1360 Permanent Lighting 10 02/15/27 02/26/27
1370 All flooring required beneath Div. 6,8,10,11,12,13 work 20 02/22/27 03/19/27
1380 Division 6,8,10,11,12,13 Work 25 03/22/27 04/23/27
1390 MEP Final Connections 25 03/29/27 04/30/27
1400 MEP final overhead & above ceiling inspections 1 05/03/27 05/03/27
1410 Ceiling Pads (Contingent on Balancing) 15 05/04/27 05/24/27
1420 Doors/Hardware 15 05/11/27 05/31/27
1430 Finish Paint 15 05/18/27 06/07/27
1440 Carpet and remaining flooring 15 05/25/27 06/14/27
1450 MEP Finishes 15 06/01/27 06/21/27
1460 Work List / Punchlist 15 06/08/27 06/28/27
Upper Level West Side 258 07/27/26 07/26/27
1470 Misc. Metals (as required) 170 07/27/26 03/24/27
1480 Priority walls frame, top-out and paint (All Corridors) 25 07/27/26 08/28/26
1490 MEP stub "in / out" for topping out 25 07/27/26 08/28/26
1500 MEP shafts and risers (coordinate with priority walls) 80 07/27/26 11/13/26
1510 MEP Overhead & Above Ceilings 35 08/31/26 10/16/26
1520 All Trades Overhead & Above Ceilings Installations 35 08/31/26 10/16/26
2025 2026 2027
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
P ro je ct
S ta rt
P ro je ct
F in is h
MEP final overhead & above ceiling inspections
Ceiling Pads (Contingent on Balancing)
Doors/Hardware
Finish Paint
Carpet and remaining flooring
MEP Finishes
Work List / Punchlist
Misc. Metals (as required)
Priority walls frame, top-out and paint (All Corridors)
MEP stub "in / out" for topping out
MEP shafts and risers (coordinate with priority walls)
MEP Overhead & Above Ceilings
All Trades Overhead & Above Ceilings Installations
Overhead & Above ceiling inspections
Stud / Frame Remaining Walls & Hard Lids
MEP in walls / to framing
All Trades in walls / to framing
In wall and lid inspections
Hang, tape, finish drywall
Prime paint / First Coat / Wallcoverings (coordinate)
Hard Tile
Install acoustical grid, cuts and only pads for MEP to grid
MEP to grid
Permanent Lighting
All flooring required beneath Div. 6,8,10,11,12,13 work
Division 6,8,10,11,12,13 Work
MEP Final Connections
MEP final overhead & above ceiling inspectio
Ceiling Pads (Contingent on Balancing)
Doors/Hardware
Finish Paint
Carpet and remaining flooring
MEP Finishes
Work List / Punchlist
Misc. Metals (as required)
Priority walls frame, top-out and paint (All Corridors)
MEP stub "in / out" for topping out
MEP shafts and risers (coordinate with priority walls)
MEP Overhead & Above Ceilings
All Trades Overhead & Above Ceilings Installations
Start Date: 01/31/25
Finish Date: 08/23/27
Data Date: 12/30/24
Run Date: 09/19/25
Page 4A
Duration Start Finish
1530 Overhead & Above ceiling inspections 1 10/19/26 10/19/26
1540 Stud / Frame Remaining Walls & Hard Lids 35 10/20/26 12/09/26
1550 MEP in walls / to framing 35 10/27/26 12/16/26
1560 All Trades in walls / to framing 35 10/27/26 12/16/26
1570 In wall and lid inspections 1 12/17/26 12/17/26
1580 Hang, tape, finish drywall 35 12/18/26 02/05/27
1590 Prime paint / First Coat / Wallcoverings (coordinate) 25 02/08/27 03/12/27
1600 Hard Tile 35 01/25/27 03/12/27
1610 Install acoustical grid, cuts and only pads for MEP to grid 20 02/22/27 03/19/27
1620 MEP to grid 15 03/01/27 03/19/27
1630 Permanent Lighting 10 03/15/27 03/26/27
1640 All flooring required beneath Div. 6,8,10,11,12,13 work 20 03/22/27 04/16/27
1650 Division 6,8,10,11,12,13 Work 25 04/19/27 05/21/27
1660 MEP Final Connections 25 04/26/27 05/28/27
1670 MEP final overhead & above ceiling inspections 1 05/31/27 05/31/27
1680 Ceiling Pads (Contingent on Balancing) 15 06/01/27 06/21/27
1690 Doors/Hardware 15 06/08/27 06/28/27
1700 Finish Paint 15 06/15/27 07/05/27
1710 Carpet and remaining flooring 15 06/22/27 07/12/27
1720 MEP Finishes 15 06/29/27 07/19/27
1730 Work List / Punchlist 15 07/06/27 07/26/27
Upper Level East Side 258 08/24/26 08/23/27
1740 Misc. Metals (as required) 170 08/24/26 04/21/27
1750 Priority walls frame, top-out and paint (All Corridors) 25 08/24/26 09/25/26
1760 MEP stub "in / out" for topping out 25 08/24/26 09/25/26
1770 MEP shafts and risers (coordinate with priority walls) 80 08/24/26 12/15/26
1780 MEP Overhead & Above Ceilings 35 09/28/26 11/13/26
1790 All Trades Overhead & Above Ceilings Installations 35 09/28/26 11/13/26
1800 Overhead & Above ceiling inspections 1 11/16/26 11/16/26
1810 Stud / Frame Remaining Walls & Hard Lids 35 11/17/26 01/07/27
1820 MEP in walls / to framing 35 11/24/26 01/14/27
1830 All Trades in walls / to framing 35 11/24/26 01/14/27
1840 In wall and lid inspections 1 01/15/27 01/15/27
1850 Hang, tape, finish drywall 35 01/18/27 03/05/27
1860 Prime paint / First Coat / Wallcoverings (coordinate) 25 03/08/27 04/09/27
1870 Hard Tile 35 02/22/27 04/09/27
1880 Install acoustical grid, cuts and only pads for MEP to grid 20 03/22/27 04/16/27
1890 MEP to grid 15 03/29/27 04/16/27
1900 Permanent Lighting 10 04/12/27 04/23/27
1910 All flooring required beneath Div. 6,8,10,11,12,13 work 20 04/19/27 05/14/27
1920 Division 6,8,10,11,12,13 Work 25 05/17/27 06/18/27
1930 MEP Final Connections 25 05/24/27 06/25/27
2025 2026 2027
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
P ro je ct
S ta rt
P ro je ct
F in is h
Overhead & Above ceiling inspections
Stud / Frame Remaining Walls & Hard Lids
MEP in walls / to framing
All Trades in walls / to framing
In wall and lid inspections
Hang, tape, finish drywall
Prime paint / First Coat / Wallcoverings (coordinate)
Hard Tile
Install acoustical grid, cuts and only pads for MEP to g
MEP to grid
Permanent Lighting
All flooring required beneath Div. 6,8,10,11,12,13
Division 6,8,10,11,12,13 Work
MEP Final Connections
MEP final overhead & above ceiling insp
Ceiling Pads (Contingent on Balanci
Doors/Hardware
Finish Paint
Carpet and remaining flooring
MEP Finishes
Work List / Punchlist
Misc. Metals (as required)
Priority walls frame, top-out and paint (All Corridors)
MEP stub "in / out" for topping out
MEP shafts and risers (coordinate with priority walls)
MEP Overhead & Above Ceilings
All Trades Overhead & Above Ceilings Installations
Overhead & Above ceiling inspections
Stud / Frame Remaining Walls & Hard Lids
MEP in walls / to framing
All Trades in walls / to framing
In wall and lid inspections
Hang, tape, finish drywall
Prime paint / First Coat / Wallcoverings (coordinat
Hard Tile
Install acoustical grid, cuts and only pads for MEP
MEP to grid
Permanent Lighting
All flooring required beneath Div. 6,8,10,11
Division 6,8,10,11,12,13 Work
MEP Final Connections
Start Date: 01/31/25
Finish Date: 08/23/27
Data Date: 12/30/24
Run Date: 09/19/25
Page 5A
Duration Start Finish
1940 MEP final overhead & above ceiling inspections 1 06/28/27 06/28/27
1950 Ceiling Pads (Contingent on Balancing) 15 06/29/27 07/19/27
1960 Doors/Hardware 15 07/06/27 07/26/27
1970 Finish Paint 15 07/13/27 08/02/27
1980 Carpet and remaining flooring 15 07/20/27 08/09/27
1990 MEP Finishes 15 07/27/27 08/16/27
2000 Work List / Punchlist 15 08/03/27 08/23/27
Penthouse/Roof 161 09/21/26 05/06/27
2010 Misc. Metals 50 09/21/26 12/01/26
2020 Concrete Housekeeping Pads 5 10/12/26 10/16/26
2030 Mechanical / Electrical Rough-in 60 10/19/26 01/13/27
2040 Set Equipment 20 03/05/27 04/01/27
2050 MEP Connections 20 04/02/27 04/29/27
2060 Louvers & Exterior Wall Panels 25 04/02/27 05/06/27
Closeout 10 08/10/27 08/23/27
2070 Final Inspections / Turnover 10 08/10/27 08/23/27
2080 Substantial Completion 0 08/23/27
2025 2026 2027
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
P ro je ct
S ta rt
P ro je ct
F in is h
MEP final overhead & above ceilin
Ceiling Pads (Contingent on B
Doors/Hardware
Finish Paint
Carpet and remaining floo
MEP Finishes
Misc. Metals
Concrete Housekeeping Pads
Mechanical / Electrical Rough-in
Set Equipment
MEP Connections
Louvers & Exterior Wall Panels
Start Date: 01/31/25
Finish Date: 08/23/27
Data Date: 12/30/24
Run Date: 09/19/25
Page 6A
File details come from the government source that posted it. Updated .