This is a Statement of Work (SOW) for independent environmental monitoring and sampling services during the remediation of an indoor firearms training range at the United States Merchant Marine Academy (USMMA) in Kings Point, New York. The contractor shall provide third-party oversight of lead contamination cleanup activities, including air monitoring, surface wipe sampling, HEPA filter replacement verification, lead-based paint encapsulation oversight, brass casing recovery verification, and post-cleaning clearance sampling. All work must comply with OSHA lead standards, EPA lead and hazardous waste requirements, HUD/EPA lead-safe work practices, New York State Department of Labor regulations, and New York State Department of Environmental Conservation requirements. The contractor must also ensure compliance with the Secretary of the Interior's Standards for the Treatment of Historic Properties, as USMMA is listed on the National Register of Historic Places.
Key deliverables include a Site-Specific Monitoring and Sampling Plan, daily logs, sampling results, non-compliance notices, and a final report. The contractor must provide all labor, equipment, certifications, and sampling media and must operate a microbiology, toxicology, and chemistry laboratory currently accredited by New York State under the Environmental Laboratory Approval Program (ELAP) prior to award. The period of performance is concurrent with cleaning contractor activities, not to exceed 30 calendar days from Notice to Proceed, with anticipated on-site work of 3-5 working days during normal business hours (7:00 a.m. to 4:00 p.m., Monday through Friday). Work is subject to Davis-Bacon Act prevailing wage requirements using Nassau County, New York wage determinations. The contractor is responsible for any subcontractors and must conduct recleaning, re-application of encapsulant, and resampling at no additional cost if regulatory clearance levels are not initially met.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ Amendment 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
1. Background The United States Merchant Marine Academy (USMMA), Kings Point, NY, is conducting environmental cleaning of its indoor firearms training range. An independent monitoring and sampling contractor is required to oversee activities involving lead contamination and verify regulatory compliance.
USMMA is listed on the National Register of Historic Places on August 29, 2014. Therefore, all work shall be consistent with the Secretary of the Interior's Standards for the Treatment of Historic Properties (36 CFR part 68). http://www.nps.gov/tps/standards/four-treatments/treatment-guidelines.pdf.
Additionally, all work shall meet or exceed the standards provided in the Secretary of the Interior’s Standards for Rehabilitation and guidelines for applying the standards published by the National Park Service, U.S. Department of the Interior 36 CFR 67.7 - Standards for rehabilitation.”
2. Purpose The purpose of this contract is to provide independent third-party environmental monitoring, sampling, and oversight services during the Bowditch Hall indoor gun range environmental deep cleaning project. Services shall comply with all applicable federal and New York State regulations, including OSHA lead standards, EPA lead and hazardous waste requirements, HUD/EPA lead-safe work practices, New York State Department of Labor regulations, and New York State Department of Environmental Conservation requirements.
3. Scope of Work The Contractor shall furnish all labor, equipment, certifications, sampling media, and reporting required to independently monitor and verify the indoor range cleaning operations.
3.1 Pre-Work Activities
Review contractor plans, attend coordination meetings, and submit a Site-Specific Monitoring and Sampling Plan.
3.2 On-Site Monitoring
Provide air monitoring, surface wipe sampling, and observe work practices to ensure compliance with approved procedures.
3.3 HEPA Filter Replacement Oversight
Observe removal, disposal, and installation of HEPA filters and verify safe handling and installation practices.
3.4 Lead-Based Paint Encapsulation Oversight
Verify encapsulation work is conducted properly and without prohibited abrasive methods.
3.5 Brass Recycling Verification
Observe casing recovery and review recycling documentation.
3.6 Post-Cleaning Clearance
Conduct clearance sampling and provide written clearance recommendations.
4. Deliverables Monitoring Plan, Daily Logs, Sampling Results, Non-Compliance Notices, and Final Report.
5. Labor Standards This project is subject to the Davis-Bacon Act using Nassau County, NY wage determinations.
6. Period of Performance
• Concurrent with cleaning contractor activities, not to exceed 30 calendar days from
Notice to Proceed (NTP).
• On-site work is anticipated to last approximately 3-5 working days.
7. Acceptance Criteria Services accepted upon completion of approved monitoring, sampling, and reporting.
8. Notes and Assumptions
• All work must be completed between normal business hours of operation (7am –
4:00pm), Monday – Friday, unless additional approval is granted by the CO and COR.
• Contractor site visit walkthrough prior to project bid.
• Awarded contractor shall work with the academy’s awarded remediation contractor.
• Awarded contractor shall provide microbiology, toxicology and chemistry laboratory services. Contractor must submit documentation showing that the laboratory is currently accredited by NYS, under the Environmental Laboratory Approval Program (ELAP), prior to the award date.
• Recleaning shall be conducted if current regulatory clearance levels are not met.
• Re-application and/or additional application of encapsulant shall be performed if current regulatory clearance levels are not met.
• Recleaning and/or additional application of encapsulant shall be performed repeatedly until clearance levels are met at no additional cost incurred to USMMA and the government.
• Resampling shall be conducted if current regulatory clearance levels are not met at no additional cost incurred to USMMA and the government.
• Awarded contractor is responsible for any subcontractors that may be used throughout this project. Subcontractors are required to adhere to all the requirements set forth within this SOW.
| Statement of Work (SOW) |
| 1. Background |
| 2. Purpose |
| 3. Scope of Work |
| 3.1 Pre-Work Activities |
| 3.2 On-Site Monitoring |
| 3.3 HEPA Filter Replacement Oversight |
| 3.4 Lead-Based Paint Encapsulation Oversight |
| 3.5 Brass Recycling Verification |
| 3.6 Post-Cleaning Clearance |
| 4. Deliverables |
| 5. Labor Standards |
| 6. Period of Performance |
| 7. Acceptance Criteria |
| 8. Notes and Assumptions |
File details come from the government source that posted it. Updated .