Milestone Payment Matrix - MBTA Coach Repair.pdf
PDF 268 KB Posted
- Solicitation number
- BD-19-1206-40000-42502-33119
- Issued by
- Middlesex County, Massachusetts
About this file
This document is a Milestone Payment Matrix for the repair of Massachusetts Bay Transportation Authority (MBTA) Kawasaki Commuter Rail Control Trailer Coach 1722 under RFP-158C-18. The matrix outlines the key milestones and associated percentage of contract value for the repair project, including delivery of the vehicle, approval of repair plans, completion of disassembly and inspection, pre-shipment inspection, and final delivery and acceptance by the MBTA. The total contract value is to be paid out across these six milestones, with the largest portion (50%) tied to the completion of the Pre-Shipment Inspection.
The Milestone Payment Matrix is associated with the RFP-158C-18 state and local contract opportunity for the repair of the MBTA's Kawasaki Commuter Rail Bi-Level Control Trailer Coach 1722, which experienced body damage. The contract is located in the state of Massachusetts and will be awarded by the MBTA.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Milestone Description Percentage of Contract Value
A Delivery of the Vehicle to the Contractor’s Facility and approval by MBTA of the receiving inspection.
5%
B Submission and approval by MBTA of the initial Repair Plan defined in Section 7.5.
5%
C Disassembly of the vehicle and completion of the hold point inspection defined in Section 3.4.
10%
D Submission and approval of the updated Repair Plan and Contract Deliverables defined in Section 7.9 and Section 10.
10%
E Completion of the Pre-Shipment Inspection defined in Section 5.2.5.
50%
F Delivery and Acceptance of the Vehicle by the MBTA 20%