Middle Mile Construction and Marketing Agreement Contract.docx
DOCX document 212 KB Posted
- Attached to
- Fiber Marketing and Construction Partner for High Speed Nevada Phase II Nevada Middle Mile Network
- Solicitation number
- 01GO-S2478
- Issued by
- Nevada
About this file
This document is a Master Customer Agreement between the State of Nevada, represented by the Governor's Office of Science, Innovation and Technology (OSIT), and a service provider to serve as the Fiber Construction and Marketing Partner for the Nevada Middle Mile Network project.
The agreement covers the design, construction, and delivery of lit fiber services, dark fiber leases, and conduit leases for two separately funded middle mile fiber optic routes in Nevada - the Interstate 80 Route and the Eastern Nevada Middle Mile Route. The provider will be responsible for all aspects of the projects including finalizing design, obtaining environmental approvals, procuring materials, constructing the infrastructure, and marketing the services to third-party broadband providers and end-customers. The projects must be completed by September 30, 2026. The provider will have an exclusive 10-year right to offer services on the middle mile infrastructure, with the state receiving a percentage of the net revenues. Pricing for the lit fiber, dark fiber, and conduit services is specified in the agreement.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MIDDLE MILE FIBER CONSTRUCTION
AND MARKETING AGREEMENT
RECITALS
| ARTICLE I | - | DEFINITIONS |
| ARTICLE II | - | NEW CONSTRUCTION |
| ARTICLE III | - | CONSTRUCTION INVOICES AND PAYMENTS |
| ARTICLE IV | - | DELIVERY OF LIT FIBER SERVICES, DARK FIBER LEASE AND CONDUIT LEASE, COLOCATION FACILITIES, FIBER MAINTENANCE SERVICES TO THIRD PARTY SERVICE PROVIDERS AND OTHER END CUSTOMERS |
| ARTICLE V - | ACCESS TO CUSTOMER MIDDLE MILE FACILITIES | |
| ARTICLE VI | - | ADDITIONAL OBLIGATIONS OF PARTIES |
| ARTICLE VII | - | WARRANTIES |
| ARTICLE VIII | - | FINANCIAL GRANT ASSURANCES |
| ARTICLE IX | - | INSPECTION & AUDIT |
| ARTICLE X | - | PROPERTY & PROPERTY INTERESTS |
| ARTICLE XI | - | DEFAULT, BREACH & TERMINATION |
| ARTICLE XII | - | NOTICES |
| ARTICLE XIII | - | REGULATIONS FOR MANAGING GOVERNMENT FUNDED PROJECTS |
| ARTICLE XIV | - | CONFIDENTIALITY |
| ARTICLE XV | - | INSURANCE SCHEDULE & COVERAGE |
| ARTICLE XVI | - | GENERAL PROVISIONS |
APPENDICES
| EXHIBIT A | - | DEFINED SERVICES | |
| EXHIBIT B | - | SPECIAL INSTRUCTIONS | |
| EXHIBIT C | - | TECHNICAL SPECIFICATIONS | |
| (CONSTRUCTION STANDARDS FOR FIBER) | |||
| EXHIBIT D | FIBER MAINTENANCE STANDARDS | ||
| EXHIBIT E | - | SERVICE ACCEPTANCE CERTIFICATE (EXAMPLE) | |
| EXHIBIT F | - | CONSTRUCTION TIMELINE | |
| EXHIBIT G | - | BUDGET MILESTONE PAYMENTS | |
| EXHIBIT H | - | WEEKLY CONSTRUCTION REPORT | |
| EXHIBIT I | - | FINAL FIBER CONSTRUCTION REPORT | |
| EXHIBIT J | - | LOCATIONS AND PRICING TABLES | |
| EXHIBIT K | - | PROVIDER'S [REDACTED] RESPONSE TO RFP |
MIDDLE MILE FIBER CONSTRUCTION
AND MARKETING AGREEMENT
MIDDLE MILE FIBER CONSTRUCTION AND MARKETING AGREEMENT (Agreement") is made and entered into on this _____ day of November 2023 by and between ________________________ a company licensed to do business in the State of Nevada (“the Provider), and the State of Nevada (“Customer”), as represented by the Governor’s Office of Science, Innovation and Technology (“OSIT”). Provider and Customer are hereinafter collectively referred to as “the Parties.”
RECITALS
WHEREAS the Customer has secured funding from two different federal government agencies and the State of Nevada, Department of Transportation, to construct and own the following middle mile fiber routes,
a) The Interstate 80 Route – United States Department of the Treasury (Treasury)– Capital Project Fund. The approval to use $76.6 million of the State of Nevada’s Coronavirus Capital Projects Fund (CPF) funding to design, build, operate and maintain a buried, multi-duct route that spans the entirety of Interstate 80 in Nevada between mile-marker 0 at the Utah/Nevada border to mile marker 410.67 at the California/Nevada Border. This build is entirely in the Interstate 80 Nevada Department of Transportation (NDOT) Right of Way.
b) The Eastern Nevada Middle Mile (Eastern Route) – National Telecommunications and Information Agency (NTIA) Middle Mile Grant Program. The State of Nevada has applied for and received an NTIA Middle Mile grant to design, build, operate and maintain a buried, multi-innerduct route from a major Internet Exchange in Las Vegas (7135 S. Decatur Blvd, Las Vegas, NV, United States) to an interconnect point at Interstate 80 in Wells, NV (577 Wells Ave, Wells, NV 89835). This route follows Interstate 15 to the US Route 93 interchange in eastern Clark County, and then along US 93 Route from Interstate 15 North to Wells, NV. The route is expected to be placed entirely within the NDOT Right of Way.
WHEREAS Provider has submitted a detailed proposal to Customer to undertake the role of Fiber Construction and Marketing Partner for the Middle Mile Projects, which role encompasses the following tasks:
· Finalize Middle Mile Project construction design and specifications.
· Conduct environmental assessment and obtain all necessary environmental approvals for the Middle Mile Project.
· Obtain all necessary access permits to construct the Middle Mile project.
· Construct the broadband infrastructure necessary for the Middle Mile Project.
· Prior to completion of construction of the network begin to market the infrastructure and pre-sell dark fiber leases prior for each middle mile project prior to project completion.
· Analyze and determine the parameters around the Fiber Marketing Partner offering its own Lit Transport, Lit Bundled Transport and Commodity Internet Access Services, Dark Fiber Leases and Conduit Leases to third party service providers and other customers.
· Comply with all State and federal reporting requirements.
WHEREAS, Customer has selected Provider’s proposal to deliver such construction, marketing, lit fiber, dark fiber lease and conduit lease services over other proposals in a fair and competitive bid evaluation process, WHEREAS, this Agreement for the design, construction, installation and/or provisioning of Fiber Assets, Fiber Equipment, marketing services for lit fiber, dark fiber lease and conduit lease services on the two State of Nevada owned routes will fulfill an important state and public need for the delivery of improved technology, infrastructure, and services to support future statewide communication operations, economic development, social and community interests, WHEREAS, the Customer has agreed with the NITA and the Treasury to treat the construction of each route as a separate project and the Provider has agreed to comply with the separate and distinct reporting obligations for construction of each route in accordance with the requirements of the NTIA and Treasury, WHEREAS, NRS 333.700 authorizes officers, departments, institutions, boards, commissions, and other agencies in the Executive Department of the State Government which derive their support from public money in whole or in part to engage, subject to the approval of the Board of Examiners (BOE), services of entities as independent contractors; and WHEREAS, it is deemed that the service of the Provider herein is both necessary and in the best interests of the State of Nevada.
NOW, THEREFORE, in consideration of the mutual covenants, conditions, agreements, and undertakings contained herein, and other good and valuable consideration, the receipt and sufficiency of which is hereby acknowledged, the Parties agree as follows:
ARTICLE I
DEFINITIONS
1.0 Definitions: The following terms in this Agreement shall have the meanings ascribed to them in this Article, or, if defined elsewhere in the text, as stated where defined.
1.1 “A Location” means the beginning point of a middle mile fiber segment. These are usually designated as the eastern most or northern most point of a middle mile fiber segment.
1.2 "Award Amount" means the total funds allocated to complete the terms and conditions under this Agreement.
1.3 "Contract Documents" means all Exhibits and attachments incorporated into this Agreement describing the scope of work and obligations of the parties.
1.4 “Colocation Hut, Hub Shelter, Regeneration Hut” A facility placed along a middle mile fiber optic cable route that houses provider and third-party customer equipment necessary to interconnect with the middle mile network and to regenerate the signal that defines the broadband capacity and speed of the fiber optic network.
1.5 "Contractor" means the person or entity that performs services and/or provides goods and/or services in furtherance of, or in connection with, this Agreement.
1.6 "CPF" means the Capital Projects Fund.[footnoteRef:1] [1: ]
1.7 “Customer” means the State of Nevada, Nevada Governor’s Office of Science, Innovation and Technology (“OSIT”).
1.8 “Customer Agency” means an agency of the State of Nevada.
1.9 “Customer Fiber System” means the conduit, cable, vaults, handholes, interconnect facilities including regeneration facilities and hub shelters constructed for and owned by the Customer.
1.10 "Conduit (Six-Way Conduit)" means an outside tube or encasement with six innerducts especially constructed for the purpose of placing and enclosing fiber optic cable.
1.11 “Conduit Lease” means a transaction by which an empty innerduct in a six way innerduct is leased to a third-party service provider.
1.12 Community Anchor Institutions (CAIs) means schools, libraries, healthcare provider facilities, institutions of higher education, community support organizations or entities, and in the future, other facilities as defined by the State of Nevada and OSIT.
1.13 “Dark Fiber" means optical fiber provided without electronics or optronics and which is not "lit" or activated, of which a designated number of such fiber optic strands will be leased from an existing or newly constructed fiber system.
1.14 “Dark Fiber Lease” a transaction by which dark fiber optic strands are leased to a third-party service provider.
1.15 “Delinquent Account” means accounts for which payment is more than forty-five 45 days past due.
1.16 “Effective Date” is the date this Agreement becomes effective upon approval by the Nevada State Board of Examiners.
1.17 “End Points” means the “Z” Location and the “A” location for a broadband transport service.
1.18 "Federal Interest Period" or "Limited Federal Interest Period". In the case of property associated with a broadband infrastructure project funded with the SLFRF or CPF, and which project is substantially completed by December 31, 2026, the federal interest in SLFRF or CPF broadband infrastructure will last until December 31, 2034 (Federal Interest Period).[footnoteRef:2] [2: See SLFRF and CPF Supplementary Broadband Guidance, May 17, 2023.]
1.19 “Fiber Assets” means existing or newly constructed fiber optic cable, conduit, rights (contractual or otherwise), or property used in connection with the construction, ownership, operation of a fiber optic system for delivery or transmission of broadband services.
1.20 “Fiber Equipment" means equipment used to pass light and Internet Protocol traffic (and therefore broadband traffic) through a fiber optic cable.
1.21 “Fiber Maintenance and Repair” means the act of inspection, maintaining and repairing fiber optic cable strands to maintain the ability of the fiber optic strands to deliver lit fiber services to end customers within the standards of the service level agreement or for dark fiber lease customers to maintain service over dark fibers leased from the Provider.
1.22 “Fiber Relocation” means the requirement to relocate or reconstruct segments of middle mile fiber.
1.23 "Property Standards" means those definitions and standards for real property, equipment and/or supplies set forth in 2 CFR 200, §§ 200.311, 200.313, and 200.314, or as specifically identified in Federal statutes, regulations, or the terms and conditions of the Federal award.
1.24 “Finding of No Significant Impact (FONSI)” means a certification received by the Provider after State and Federal agency environmental review determines there is no environmental impact related to the construction of new fiber along the proposed route between the “Z location” and the “A location”. This certification is required for the vast majority of new fiber construction projects and must be obtained prior to commencing construction activities.
1.25 “Interference” means any occurrence that impairs or interrupts the ability of the fiber optic cables to transmit Internet Protocol voice, video, or data traffic.
1.26 "IRU" means Indefeasible Right to Use, an exclusive and irrevocable right to use optical fiber(s) for a defined period of time as set forth in the IRU Agreement.
1.27 "Lit Fiber Services" means fiber optic cables which have been equipped with the necessary equipment to enable point-to-point transmission or transport of data by an Internet service provider, and all associated activities necessary to provision such services.
1.28 “MCA” refers to this Master Customer Agreement.
1.29 “Monthly Recurring Charges” or "MRC" means charges for Lit Service(s) or Dark Fiber Service(s) that accrue to the Customer monthly.
1.30 "Maintain" or "Maintenance" or derivatives thereof means the activity of assuring continuing operational status of the system through repair, replacement or otherwise, but excludes relocation or additions of fiber conduit, fiber equipment or assets into the rights-of-way.
1.31 “Middle Mile Project” refers fiber optic based broadband infrastructure, commonly referred to in the industry as "middle mile", that traverses major Interstate and US Highways in a state. It passes by rural population centers and through rural areas terminating in cities like Las Vegas and Reno. The Middle Mile Project for this contract encompasses the construction and marketing of two separately funded, long-haul (over 60 miles in length) middle mile spans, namely, the Eastern Nevada Middle Mile (US 93) and the I-80 project.
1.32 “New Fiber” or “Newly Constructed Fiber” or “New Construction” means new fiber optic cable and supporting components or infrastructure placed aerially or buried. Newly Constructed Fiber for this Contract should strictly follow the fiber construction specifications outlined in the relevant Exhibits.
1.33 "Notice to Proceed" means a written notice given by Customer to Contractor fixing the date on which the Contract times will commence to construct a segment or segments of fiber optic cable between defined end points Commencement of construction and initiation of service, will require a "Notice to Proceed”.
1.34 "NTIA" means the National Telecommunications and Information Agency.
1.35 "OSIT" means the Nevada Governor's Office of Science, Innovation and Technology.
1.36 “Outside Plant Materials” means all materials necessary to construct Newly Constructed Fiber to include but not be limited to fiber, conduit, handholes, vaults, markers, cabinets, construction hardware, electronics, shelters, and pole attachment materials.
1.37 "One Time Construction Charges" means the build-out costs associated with the construction of the Middle Mile project, including the costs of construction of network facilities, design, engineering, and project management leased lit service, leased dark fiber and/or self-provisioning (own) fiber. For the purposes of this agreement, one time construction charges paid by the customer are limited to the amount of grant funds for the I-80 route and the amount of grant funds from the NTIA and matching funds from the State of Nevada Department of Transportation for the Eastern NV Middle Mile.
1.38 “Provider Equipment” means any equipment, owned by a service provider, used for, or which supports, transmission of light and Internet Protocol (IP) traffic (and therefore broadband traffic) through a fiber optic cable.
1.39 "Project Property" means the broadband infrastructure constructed and/or installed pursuant to Provider's contract with Customer OSIT.[footnoteRef:3] In the case of these two projects, all project property is owned by the State of Nevada. [3: See guidance from U.S. Treasury at: https://home.treasury.gov/system/files/136/SLFRF-and-CPF-Supplementary-Broadband-Guidance.pdf#:~:text=Title%20to%20real%20property%20or%20equipment%20acquired%20or,Period%2C%20the%20ISP%20and%20any%20successors%20or%20transferees%3A
1.40 “Planned Services Date” means the date that represents service initiation that Provider offers a Lit Service, Dark Fiber lease or Conduit lease to third party customers Customer.
1.41 "ROW" means the right-of-way granted by NDOT, City, County, landowners, or federal agency to allow occupancy to locate, operate, construct, reconstruct, maintain any fiber assets or fiber equipment.
1.42 “State” means the State of Nevada and any State agency identified herein, its officers, employees and immune contractors as defined in NRS 41.0307
1.43 "State Materials" means any data, state records, state software, research, studies, photographs, documents, drawings, models, materials, or information provided by the State to Provider in the course of this Contract.
1.44 “Service Level Agreement” or SLA – the standards of service for uptime, latency, packet loss, jitter, oversubscription and other technical standards for a Lit Fiber Service. For this agreement, SLA standards for Lit Fiber Service is enumerated in Exhibit A.
1.45 “Subcontractor” means any third person or entity hired by or performing work pursuant to a request of the Provider as part of, or related to, any project or work arising from this Agreement.
1.46 “Z Location” means the origin location for a broadband transport service, usually a customer’s operating office or premise, where a broadband connection originates. All Z locations are connected to specific A locations via fiber optic cable.
ARTICLE II
NEW CONSTRUCTION
| 2.0 | Commencement: For purposes of Newly Constructed Fiber or New Construction, this Agreement will commence on the Effective Date. Construction or pre-Construction work related to new Construction shall commence within 30 days of the Effective Date. For the purposes of this clause, pre-construction work can include but is not limited to design, engineering, permitting, environmental assessment, pre-order of Outside Plant Materials and other activities. |
| 2.1 | Completion: The completion of new fiber construction, installation, and the offering of lit services, dark fiber leases and/or conduit leases to third party service providers or other end customers shall be completed on or before September 30, 2026. Time is of the essence in the delivery of services and completion of this project. This date may be extended only if the deadline for expending CPF or NTIA funds is extended by the federal government. |
| 2.2 | Scope of Services: It is the intent of this Agreement to describe and create a functionally complete project consisting of new Fiber Assets that will deliver certain goods and services in accordance with specifications set forth in the attached Exhibits. The Parties acknowledge the primary objective of this Agreement is the design, construction, installation, and delivery of service that will reliably meet the needs of third-party service providers who deliver broadband services to residential, business and Community Anchor Institution customers along the two routes. This includes all tasks related to: |
2.2.1 Creating and adhering to a detailed project schedule for the engineering, design, construction, and test of the entirety of the Middle Mile Project.
2.2.2 Engineering and design of the Middle Mile Project routes.
2.2.3 Completion of all necessary Environmental Categorical Exclusion and Environmental Assessment documents.
2.2.4 Successfully obtaining an Environmental Finding of No Significant impact (FONSI) for the Middle Mile Project.
2.2.5 Successfully procuring all outside plant materials necessary to construct the Middle Mile project.
2.2.6 Constructing the Middle Mile project in accordance with the construction deliverables and specifications outlined in Exhibit C, and in accordance with the detailed project schedule.
| 2.3 | Construction Deliverables: Provider shall comply with the design, engineering, procurement, permitting, construction and delivery requirements in Exhibit A and Exhibit C that will include Lit Service(s), Dark Fiber Lease Service(s) and Conduit Lease services to third party service providers or other end customers pursuant to the terms of this Agreement. Provider agrees to design, engineer, procure and construct "the entirety of the Middle Mile (encompassing both routes) from Construction End Points as set forth in specifications so identified and as required to connect the Z Locations to the A Locations. Any unintentionally omitted executory provisions or obligations contained in Exhibit K, Response to the State RFP, with respect to the executory provisions, scope of work and construction deliverables, are hereby incorporated by this reference. |
| 2.4 | New Construction or Installation: For New Construction or Newly Constructed Fiber and/or installation activity included to enable the provisioning of services (see Article III), the Provider agrees to deliver to Customer the standards of construction set forth in Exhibit C, and comply with the terms, conditions, and covenants herein. |
| 2.6 | Construction Progress Reports: For the Middle Mile Projects, Provider will provide Customer with regular progress reports to update Customer on the construction progress, impediments, finances and any other matters which may impact the project. Provider Reports shall include: |
| 2.6.1 | Weekly Reports: Weekly construction reports will be provided to OSIT's Director of Fiber Networks. Commencement of the reporting will be contingent on the Parties mutually agreeing on the required components of the weekly reports. |
| 2.6.2 | Quarterly Progress and Fiscal Reports: On a quarterly basis, Provider shall deliver to the Director of OSIT a report in the format specified by OSIT addressing the construction milestone, financial and technical updates, and any other issues impacting construction efforts. |
| 2.6.3 | As Requested: Upon written request by Customer, Provider shall respond within three business days to any request for status or update from Customer and provide information as requested. |
| 2.7 | Permitting and Landlord Approval: Provider shall be responsible for acquiring all permits necessary for the completion of the Middle Mile Routes. The Customer shall be the named recipient of all permits. Provider and Customer shall use best efforts to work with permitting agency(ies) to obtain required permits and/or secure the necessary approval(s) for access. Customer is responsible for providing access into Customer locations from the public ROW at no cost to provider. |
| 2.8 | Construction Testing, Inspection and Acceptance of Project Milestones: At such times during the construction period, and upon meeting specific construction milestones set forth in Exhibit G for each specified milestone, or upon incurring $1,000,000.00 or more in costs, Customer shall review, test, inspect and verify completed of each specified milestone ("Inspection Period"). If deliverables and technical specifications (Exhibit C) have been inspected, tested, meet specifications and are acceptable, Customer will proceed with payment to Provider. |
| 2.9 | Use of Existing Customer Colocation Facilities: Customer agrees to provide or obtain any permission or consent required for Provider to access existing Customer colocation facilities identified in Exhibit A, at no cost to Provider. These existing facilities will be inspected by the Provider and found to be suitable for use in the construction of the Middle Mile Projects. These existing facilities are provided in “as-is” condition with the Provider responsible for any necessary enhancements as part of the Middle Mile Construction project. |
| 2.10 | Finalization of Construction: At such time as Provider considers that portion of the New Fiber or New Construction ready for provisioning of intended services, whether Lit Fiber Service(s) Dark Fiber Service(s) or Conduit Lease for its intended use, Provider will notify Customer Agency and the OSIT Project Manager in writing that the final construction phase is substantially complete (except for items specifically listed by Provider as incomplete), request a Final Fiber Construction Report (see Exhibit I), and request that the OSIT Project Manager issue a Certificate of Substantial Completion. Following review, OSIT's Project Manager will issue a Certificate of Substantial Completion, or, if the OSIT Project Manager does not consider the work complete, said Manager will notify Provider in writing giving the reasons therefor and provide a list of items to be completed or corrected. Provider shall have seven calendar (7) days after receipt thereof during which to make written objections as to any items on the list. Failure to object will be deemed a waiver of any objections. After considering any such objections, the OSIT Project Manager will either deliver a revised list of items to be completed or corrected, setting forth the reasons therefor, or will issue a determination that all work and deliverables are substantially completed. Within thirty (30) days of the Certificate of Substantial Completion, Provider will issue a Final Fiber Construction Report (see Exhibit I), at which time final payment shall be authorized. |
ARTICLE III
CONSTRUCTION INVOICES AND PAYMENTS
| 3.0 | Construction Charges: Customer shall be responsible for all One-Time Construction Charges required for the commencement of the service up to the limits set in the CPF grant for the I-80 route and the total amount of the NTIA grant and the cash match from the Nevada Department of Transportation (DOT) for the Eastern Nevada Middle Mile. The one-time construction funding is sourced from the following sources: 1) Interstate 80 Route will receive funding from the allocation to the Customer from the CPF portion of the 2021 American Rescue Plan Act for the I-80 Middle Route, and 2) The Eastern Nevada Route will receive funding from the NTIA Middle Mile Grant program contained in the 2022 Infrastructure Investment and Jobs Act and the State of Nevada Highway Fund. Regardless of the source of funds, the Customer is responsible for the payment of One-Time Construction Charges and all additional payments based on the terms of the Agreement. |
| 3.0.1 | Award Amount: The Award Amount for the project is agreed upon at $____________________. This amount represents the maximum amount that the Customer shall be obligated to pay under this Agreement, regardless of any additional costs incurred by the Provider during the execution of the project. The Award Amount covers all labor, materials, equipment, management, subcontractor costs, permits, licenses, taxes, insurance, overhead expenses and any other direct or indirect costs necessary to complete the project as specified in the Award Agreement. There is no opportunity for the Provider to request additional funds to complete this project. In the event OSIT seeks additional builds, a separate addendum will be negotiated for that build. |
| 3.0.2 | Costs: The Provider shall be solely responsible for managing and controlling all costs associated with the project within the agreed upon Award Amount. The Provider shall exercise due diligence, employ efficient construction practices, not bill for unallowable costs or non bona fide goods or services, and will make every reasonable effort to complete the project within the budget. The Provider shall immediately notify the Customer of all manufacturer's price declines and Customer shall receive the benefit of such declines. |
| 3.0.3 | Costs in Excess of Award Amount: In the event the Provider incurs costs that exceed the Award Amount due to unforeseen circumstances, errors in estimation, or any other reasons beyond the Customer’s control, the Provider shall bear all additional costs and expenses. The Customer shall not be held responsible for any cost overruns or additional charges incurred by the Provider. |
| 3.1 | Construction Phases: Provider and Customer will mutually divide the construction elements of the bid into distinct components that align with the phases of construction (“Construction Phases”) that are outlined in Exhibit F for purposes of tracking progress and/or securing periodic or milestone payments in accordance with Article 3.2 below. |
| 3.2 | Milestone Payments: All payments for construction of fiber facilities under this RFP will be made on a reimbursement basis in accordance with one of two methods. Provider may either seek reimbursement based on completion of milestones identified in Exhibit F or, alternatively, Provider may seek reimbursement after accruing a minimum of $1,000,000.00 in costs. The engineering and design effort at the beginning of a project can be considered one of the Construction Phases for purposes of Provider compliance and payment. Exhibit G may be divided into tasks that do not necessarily require completion of all pre-construction activities and construction activities but divide these overall milestones into specific tasks. Prior to issuance of Milestone Payments or Payments for Reimbursement of $1,000,000.00, Provider will allow Customer’s Director of Fiber Network or Project Manager to review, inspect and/or test the completed work to ensure compliance with project requirements, stated deliverables, and any technical specifications. Milestone payment will be issued only after approval and acceptance of work and deliverables by the OSIT Project Manager. |
| 3.3 | Billing Submission / Timeliness: The parties agree that time is of the essence with respect to the timeliness of invoicing. All billings for dates of services prior to July 1 must be submitted to the Customer no later than the first Friday in August of the same calendar year. A billing submitted after the first Friday in August, which forces the State to process the billing as a stale claim pursuant to NRS 353.097, will subject the Provider to an administrative fee not to exceed one hundred dollars ($100.00). The parties hereby agree this is a reasonable estimate of the additional costs to the state of processing the billing as a stale claim and that this amount will be deducted from the stale claim payment due to Provider. |
| 3.4 | Pre-Construction Invoicing: Pre-construction charges shall be reimbursed only once invoices are received from the Provider and the required milestone payment forms (see Exhibit G) have been submitted and approved by OSIT. Reimbursements will only be made for costs incurred and paid in full by the Provider that are aligned with the approved construction budget contained in Exhibit G. The Provider invoices must be accompanied by acceptable proof of payment for work performed, including invoices from subcontractors billing for the work (if applicable), suitable evidence that the invoiced work has been completed, that the Provider has made payment for the work, and for final invoice, that the pre-construction work of Outside Plant Materials and other activities. Pre-Order of Outside Plant Materials cannot occur until the project has completed successful environmental review and been issued a proper Finding of No Significant Impact (FONSI). |
| 3.5 | Construction Invoicing: Construction charges shall be reimbursed only once accurate invoices and supporting documentation are received from the Provider totaling a minimum of $1,000,000.00, and/or the required milestone payment forms have been submitted, and the work and deliverables have been inspected, approved, and accepted by the OSIT Director of Fiber Networks or Project Manager as outlined in Article 2.8, and 2.9. Reimbursements will only be made for costs incurred and paid in full by the Provider that are aligned with the approved construction budget contained in Exhibit G. The Provider invoices must be accompanied by acceptable proof of payment, accurate invoices for work performed, including invoices from subcontractors billing (if subcontractors are involved in the work), and suitable evidence that the work has commenced or was completed. |
| 3.6 | Invoice Payments: Payments are due 30 days after the State receives reimbursement from the applicable source of funding (U.S. Treasury or NTIA). After receiving an invoice for special construction charges or monthly recurring charges, Customer may dispute any charge at its sole discretion and ask for additional documentation from the Provider that the Customer believes necessary to clarify the charges. |
ARTICLE IV.
DELIVERY OF LIT FIBER SERVICES, DARK FIBER LEASE, CONDUIT LEASE,
COLOCATION SERVICES AND FIBER MAINTENANCE SERVICES
TO THIRD PARTY SERVICE PROVIDERS AND OTHER END CUSTOMERS
| 4.0 | Term: For 10 years from the completion and final acceptance of each Middle Mile Project, the Provider shall have the exclusive right to offer Lit Fiber Services, Dark Fiber Lease, Conduit Lease, Colocation Space Rental and Fiber Maintenance Services to third party service providers and other customers. |
| 4.1 | Revenue Goals: One year prior to the presumed issuance of an Acceptance Certificate for the Middle Mile Projects and annually thereafter, the Customer and the Provider will set annual revenue goals for the Provider’s revenue from Lit Fiber Services, Dark Fiber Lease, Conduit Lease, Colocation Space Rental and Fiber Maintenance Services. These annual goals shall include revenue from fiber maintenance services and from colocation space rental. The performance of the Provider over the ten-year term shall be evaluated by the Customer based on the Provider’s achievement of the revenue goals and the Provider’s ability to meet or exceed the lit fiber service and dark fiber service level agreements for third party customers outlined in Exhibit A. Evaluation of the Provider’s performance shall be at the sole discretion of the Customer. |
| 4.2 | Compensation and Revenue Share for Customer: The compensation to the Customer shall be the following: |
4.2.1 No Cost Maintenance and Repair: The Provider shall, at no cost to the Customer, maintain, repair, and relocate both the Customer’s six-way conduit and the general use six-way conduit for the entirety of the term of the agreement and any and all renewal terms. Provider will ensure that use, management and maintenance of the conduit, fiber optics and other related assets will not be used in such a way as to interfere with any other party's use of its fiber optic cable and associated components. The standards of maintenance and repair services are outlined in Exhibit D.
4.2.2 Net Revenue Share to Customer: The Provider shall provide the Customer with an_____% share of all revenues from Lit Fiber Service, Dark Fiber Leases, Conduit Leases, Fiber Maintenance Fees, and Colocation Fees that are derived from the Middle Mile projects. The Net Revenue shall be calculated net of any Federal, State or Local revenue, sales, use and property taxes that accrue to the provider.
4.2.3 Payment to Customer: Payments on net revenues shall be made quarterly commencing three (3) months after the Customer issues the Certificate of Acceptance for the Middle Mile Projects. Payments shall lag revenue receipt by the Provider by one quarter.
4.2.4 Audit and Inspection Rights
: Customer will have a limited right to access the documents and records in Provider’s custody and control that are directly related to the calculation of the Customer’s share of revenue payments hereunder. Customer may exercise their audit right not more than once per calendar year. Provider shall be responsible for the costs associated with any such requested audit.
| 4.3 | Liens: Provider shall keep leased conduit and any other legally recognized property, free and clear from any and all liens, claims and demands which may attach as the result of the acts or omissions of Provider, its employees, subcontractors, or agents for work performed, materials furnished, or operations conducted on the leased conduit at the request or direction of Provider. If such a lien is filed, the Provider shall promptly cause such lien to be removed or released and shall indemnify, hold harmless and defend Customer from any and all costs to remove such lien. |
| 4.4 | Marketing: Provider will use its best efforts in the marketing of its services and the fiber assets within its control. The Customer will have no obligation to promote, market or advertise the operations or services of Provider. |
| 4.5 | Renewal: Following the Initial 10-year term, the Customer may renew this agreement for up to four (4) optional five (5) year renewals. Any renewal(s) must be in writing and signed by the Parties on or before the anniversary of the commencement date of this Agreement unless Customer delivers written Notice of Non-Renewal to Provider, or any designated successor, at least sixty (60) days prior to expiration of either the Initial Term or expiration of any renewal term. |
| 4.6 | Obligations of Provider to Provide Customer with a Summary of Third-Party Users: Provider shall provide Customer with a listing of third-party service providers or other customers receiving service from the Middle Mile Projects. This list shall be updated monthly. The listing shall include all one-time lease fees, all monthly recurring fees, all maintenance fees and all colocation rental fees paid by the third-party service provider or other customer. |
| 4.7 | Obligations of Provider to Provide Customer with Access to Service Contracts with Third Party Users: Provider shall provide Customer with real-time access to contracts the Provider has signed with third party service providers or other customers receiving service from the Middle Mile projects. |
ARTICLE V
ACCESS TO CUSTOMER MIDDLE MILE FACILITIES
| 5.1 | Providers Service Equipment: Customer acknowledges that Provider will collocate Provider’s equipment required to serve third party service providers and other customers with the Customer’s equipment in Colocation Facilities along the Middle Mile routes. Customer agrees to immediately notify Provider if Provider's Equipment is lost, damaged, or stolen, or Customer is aware at any time that Service is being stolen or fraudulently used. | |
| 5.2 | Colocation Facility Access Security: Customer shall grant the Provider with 24/7/365 access to all colocation facilities along the Middle Mile Routes for all purposes related to providing Lit Fiber Services, Dark Fiber Lease, Conduit Lease, Colocation Space Rental and Fiber Maintenance Services to third party providers and other end customers. Provider agrees to maintain a list of parties authorized to access Colocation Facilities and to have all authorized users abide by Customer’s security access procedures and protocols. A list of Customer’s security access protocols will be provided by the Customer during the Construction phase of the Middle Mile Project. | |
| 5.3 | Interference: In the event of any interference that occurs after installation and approval of the Service Acceptance Certificate, the Parties agree that Provider shall be responsible for identification and resolution of the interference within 30 days of the identification of the interference. If Provider is the cause of such interference, Provider will be responsible for any costs associated with the resolution of such interference. | |
| 5.4 | Notice of Damage/Irregularities: Customer agrees to immediately notify Provider if Provider's Equipment is lost, damaged, or stolen, or Customer is aware at any time that Service is being stolen or fraudulently used. Customer shall be granted access to the asset defined as Customer Fiber. | |
| 5.5 | Liability for Damage to Customer’s Equipment: Provider shall not be liable for any damage to Customer's, Customer Agency’s equipment, third- party service provider owned equipment, and/or third party owned structures on account of criminal burglary, vandalism, power failure, lack of heat, weather conditions, natural and man-made phenomena such as "skip" interference, power line or ignition noise, and co-channel interference, unless the cause for such occurrence, activity or damage is attributable to Provider's negligence. Provider shall be responsible for maintaining its equipment within the colocation facility in a safe and secure location within the colocation facility as agreed to by the provider and the customer. The Customer shall not be liable to Provider for any damage to Provider's equipment unless said damage is the result of Customer's negligence. |
ARTICLE VI
ADDITIONAL OBLIGATIONS OF PARTIES
6.0 Deadline for Invoicing for New Fiber Construction or Services: Provider hereby acknowledges and understands that any federal funding allocated under this Agreement for the purpose of one-time construction charges must be committed for eligible use(s) no later than December 31, 2024. The final deadline for submission of any invoice for payment of one-time construction charges must be committed for eligible use no later than December 31, 2024. The final deadline for submission of any invoice for payment of one-time construction charges shall be September 30, 2026, and NO INVOICE FOR ONE-TIME CONSTRUCTION CHARGES WILL BE ACCEPTED FOR PAYMENT AFTER SEPTEMBER 30, 2026,[footnoteRef:4] unless an extension is authorized by the federal funding source. [4: See Supplementary Broadband Guidance, supra.]
| 6.1 | Subcontractors: The Provider is responsible for the supervision of each subcontractor’s compliance with the terms and conditions of this Agreement. | |
| 6.1.1 | Safety Program: Provider must submit employee safety program documentation and safety program documentation for any of its subcontractors who will be involved in construction work, materials handling site inspection, engineering or permitting. | |
| 6.1.2 | Payment of Subcontractors: Provider warrants and agrees that all invoices, claims or charges by subcontractors or lien claimants for labor, materials, works of improvements and/or services provided in furtherance of this Agreement will be timely paid, settled or compromised prior to any payment authorization approved by Customer. Provider shall indemnify, defend, and hold harmless Customer from any such claims. Provider’s failure to ensure resolution of all invoices, claims, or charges by its subcontractors or lien claimants prior to receipt of final payment authorization by Customer will be deemed a material breach of this Agreement. | |
| 6.2 | Disclosures Regarding Current or Former State Employees: For the purpose of State compliance with NRS 333.705, Provider represents and warrants that if Provider, or any employee or authorized agent of Provider who will be performing services under this Contract, is a current or former employee of the State employed by the State within the preceding 24 months, Provider must disclose to Customer the identity of such person(s), and the services that each such person will perform, to enable Customer to submit the required disclosure to the State Board of Examiners | |
| 6.3 | Compliance with Local, State, Federal Legal Obligations: Provider shall procure and maintain for the duration of this Contract any state, county, city or federal license, authorization, waiver, permit qualification or certification required by statute, ordinance, law, or regulation to be held by Provider to provide the goods and/or services required by this Contract. Provider shall provide proof of its compliance upon request of the Customer. Provider will be responsible for paying all taxes, assessments, fees, premiums, permits, and licenses required by law. Real property and personal property taxes are the responsibility of Contractor in accordance with NRS 361.157 and NRS 361.159. Contractor agrees to be responsible for payment of any such government obligations not paid by its subcontractors during performance of this Contract. | |
| 6.4 | Notice of Claim: Customer shall promptly serve the Provider with written notice of any third-party claim, suit and/or legal action which may affect the Parties. Provider shall likewise promptly serve Customer with written notice of any third-party claim, suits, or legal action which may affect either Party. Any notices so served shall be in accordance with Article 12 – Notices, of this Agreement. | |
| 6.5 | Mutual Cooperation: Each party shall provide all reasonable and necessary assistance to the other party for performing the obligations under this Agreement. |
ARTICLE VII
WARRANTIES
| 7.0 | Corporation in Good Standing: Provider warrants that it is a corporation in good standing, licensed to do business in the State of Nevada, and that it will maintain such status during the pendency of this Agreement. |
| 7.1 | General Warranty: Provider warrants that all construction, installations and/or work products under this Contract shall be completed in a workmanlike manner, consistent with standards in the trade, profession, or industry; shall conform to or exceed the specifications set forth in the incorporated attachments; and shall be of good quality, fit for ordinary use, with no material defects at the time of delivery. |
| 7.2 | Compliance with Federal, State, Local Statutes: Projects funded through this effort must comply with all applicable Federal laws and regulations, executive orders, and with all requirements for State, local, and Tribal laws and ordinances to the extent that such requirements do not conflict with Federal laws. These requirements are extensive. Provider acknowledges and warrants that Provider and its subcontractors shall comply with all statutes, rules, orders, building codes, ordinances, requirements and regulations of any City, County, State and/or Federal governments, applicable to the premises, including, but not limited to, the Occupational Safety and Health Administration (“OSHA”), The Americans with Disabilities Act (“ADA”) of 1990 (P.L. 101-136) set forth in 42 U.S.C. Section 12101 through 12213, as amended, and regulations adopted thereunder, including 28 C.F.R Section 35, inclusive, any relevant program-specific regulations, and 47 U.S.C. Sections 225.611, at Provider's sole cost and expense. In addition, Provider and its subcontractors shall comply with the requirements of the Civil Rights Act of 1964 (P.L. 88-352), as amended, the Rehabilitation Act of 1973 (P.L. 93-112), as amended, and any relevant program-specific regulations, and shall not discriminate against any employee or offeror for employment because of race, national origin, creed, color, sex, religion, age, disability, or handicap condition (including AIDS and AIDS-related conditions.) |
| 7.3 | Compliance with Labor Standards: Provider acknowledges and warrants with respect to both Middle Mile Projects, it will comply with applicable labor standards, and that it has policies and practices in place to ensure its contractors and subcontractors will incorporate high labor standards, offer strong wages and benefits and include local hire provisions in accordance with the Middle Mile Grant Program Notice of Funding Opportunity[footnoteRef:5], 2 CFR 200, and 29 CFR Part 5[footnoteRef:6]. [5: See Section VI (E)(1) https://broadbandusa.ntia.doc.gov/sites/default/files/2022-05/MIDDLE%20MILE%20NOFO.pdf ] [6: See 29 CFR Part 5 concerning compliance with the labor requirements. |
7.4 Wages: The Middle Mile Project will comply with the provisions of NAC 338, NRS 338 and 338.035 et seq. with respect to the payment of prevailing wages.[footnoteRef:7] [7: See the Nevada Public Works Project Handbook, June 2021 at https://labor.nv.gov/uploadedFiles/labornvgov/content/PrevailingWage/Final%20PWP%20Handbook%202021%20rev.%2008.07.2023.pdf ]
| 7.5 | Provider further certifies that: |
| 7.5.1 | Provider's workforce meets high safety and training standards, including professional certification(s), licensure, and/or robust, in-house training. Examples of such standards may include, but are not limited to, direct employment of the workforce, paying prevailing wages, as defined by the Nevada Department of Labor, and/or employing a project labor agreement, and/or project workforce continuity plan, and/or a labor peace agreement as applicable, hiring locally, employing policies and practices to avoid worker misclassification, and demonstrating there are no recent violations of federal and State labor and employment laws. |
| 7.5.2 | Provider will prioritize hiring of Nevadans, including individuals from historically disadvantaged communities. |
| 7.6 | Compliance with Federal Requirements; Uniform Guidance, 2 CFR 200: Provider acknowledges and warrants it will comply with the applicable programmatic and reporting requirements in accordance with the grant obligations set forth in the Middle Mile Notice of Funding Opportunity, set forth in the Compliance and Reporting Guidance of the U.S. Treasury [footnoteRef:8] and Appendix II to the Uniform Guidance in 2 CFR 200, Contract Provisions for Non-Federal Entity Contracts Under Federal Awards,[footnoteRef:9] including: [8: See https://home.treasury.gov/system/files/136/SLFRF-Compliance-and-Reporting-Guidance.pdf |
] [9: See https://www.ecfr.gov/current/title-2/subtitle-A/chapter-II/part-200/appendix-Appendix%20II%20to%20Part%20200
| 7.6.1 | Termination for Cause and Convenience. See Article X. |
| 7.6.2 | Equal Employment Opportunity Act, including requirements and exemptions;[footnoteRef:10] [10: Except as otherwise provided under 41 CFR Part 60, all contracts that meet the definition of “federally assisted construction contract” in 41 CFR Part 60–1.3 must include the equal opportunity clause provided under 41 CFR 60–1.4(b), in accordance with Executive Order 11246, “Equal Employment Opportunity” (30 FR 12319, 12935, 3 CFR Part, 1964–1965 Comp., p. 339), as amended by Executive Order 11375, “Amending Executive Order 11246 Relating to Equal Employment Opportunity,” and implementing regulations at 41 CFR part 60, “Office of Federal Contract Compliance Programs, Equal Employment Opportunity, Department of Labor.” |
7.6.3 Clean Air Act: Provider acknowledges and warrants it will comply with Clean Air Act and Federal Water Pollution Act[footnoteRef:11] for contracts that exceed the Simplified Acquisition Threshold (currently $250,000). [11: Clean Air Act (42 U.S.C. 7401–7671q.) and the Federal Water Pollution Control Act (33 U.S.C. 1251–1387), as amended. See Clean Air Act (42 U.S.C. 7401–7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251–1387). Violations must be reported to the Federal awarding agency and the Regional Office of the Environmental Protection Agency (EPA).
| 7.6.4 | Access to Records. Customer and authorized State agents shall have access to documents, papers, or timely access to personnel pertinent to the award in accordance with 2 CFR Part 200.337. |
| 7.6.5 | Prohibition of Use of Certain Telecommunications Equipment. Recipients and subrecipients are prohibited from entering into a contract to procure or obtain equipment, services or systems that uses covered telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation.[footnoteRef:12] Pub. Law 115-232. See 2 CFR 200.216 [12: See Pub. Law 115-232. See 2 CFR 200. |
7.7 Work Safety Standards: Provider acknowledges and warrants it will comply with the Contract Work Hours and Safety Standards Act (40 U.S.C. 3701–3708) where applicable.[footnoteRef:13] [13: Where applicable, all contracts awarded by the non-Federal entity in excess of $100,000 that involve the employment of mechanics or laborers must include a provision for compliance with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor regulations (29 CFR Part 5).