This addendum to the invitation to bid for the East Street Housing Site Infrastructure Project is issued by the Town of Morris and Morris Housing Authority in Connecticut. The addendum documents attendees from the mandatory pre-bid site walk held on March 4, 2026, including representatives from ten construction firms: Alibozak Construction, Carabetta/SRC, LaRosa Earth Group, Nosal Builders, Palker Excavating, Pelletier Construction, Towne & Aurell, VUU Industries, and Yield Industries. The addendum extends the original bid submission deadline by one week to 2:00 P.M. on Wednesday, March 25, 2026, and extends the question-and-answer response date from Wednesday, March 11 to Monday, March 16. The Q&A responses will include additional scope details regarding electrical site power and site lighting, as well as expanded landscaping scope requirements.
The addendum serves to clarify project requirements and address questions raised during the site walk while providing bidders additional time to prepare comprehensive proposals. By extending the Q&A timeline and bid submission deadline, the Town of Morris accommodates the incorporation of supplemental electrical and landscaping scope items into the project specifications. These modifications ensure all prospective bidders receive complete and consistent project information prior to bid submission, supporting a fair and competitive bidding process for the eight-unit affordable housing site infrastructure work.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF MORRIS and MORRIS HOUSING AUTHORITY
INVITATION TO BID – SITE CONSTRUCTION
EAST STREET HOUSING – 103 EAST STREET, MORRIS, CT
Addendum 1: Responses to Questions at Site Walk and Other Requests for Information
1. Who attended the site walk?
Alibozak Construction
Carabetta / SRC
LaRosa Earth Group
Nosal Builders
Palker Excavating
Pelletier Construction
Towne & Aurell
VUU Industries
Yield Industries
2. What is the schedule for Q&A answers and for bid submission.
The due date for the bids is being extended by one week to 2:00 PM on
Wednesday, March 25. The Q&A answers will take a little longer to get out to everyone, and this is extended from Wednesday, March 11 to Monday March 16. The Q&A answers will contain some additional electrical scope for site power and site lighting and some additional landscaping scope.
File details come from the government source that posted it. Updated .