Measurement and Payment Specifications - Police Fencing.pdf
PDF 70 KB Posted
- Attached to
- Police Station Security Fencing
- Solicitation number
- 52963
- Issued by
- Fairfax County, Falls Church City, Virginia
About this file
This document contains the Measurement and Payment Specifications for a Police Station Security Fencing project in the jurisdictions of Fairfax County and Falls Church City, Virginia. The project requires the provision of chain link fencing and two electronic speed gates to enhance the security of the City police station. The fencing will be measured and paid per linear foot, and the speed gates will be paid as a lump sum. Additional lump sum items include allowance for gate foundation modifications, erosion and sedimentation controls, and the remainder of work to complete the project. A pre-bid conference is scheduled for January 17, 2024 at 1:00 pm at 3730 Blenheim Blvd, Fairfax VA.
The unit and lump sum prices shall be full compensation for overhead, profit, insurance, bonds, labor, equipment, materials, and all other incidentals necessary to complete the work. Any differing conditions encountered, such as unexpected rock or deeper foundations, will be paid as a negotiated allowance based on actual costs. The project is funded by the local jurisdictions, but the specific funding sources and amounts are not provided in this document.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB 24033 Addendum #1.pdf | ||
| IFB 24033 Bid Submission Form.docx | DOCX document | |
| 2 Security Gates and Fencing Project Specifications.pdf | ||
| Bid Form - Exhibit A.xlsx | XLSX spreadsheet | |
| Bid Tabulation | — | |
| IFB 24033 Addendum #3.pdf | ||
| IFB 24033 Prebid Attendance Sheet.pdf | ||
| IFB 24033 Addendum #2.pdf | ||
| IFB 24033 Police Station Security Fencing Project.pdf | ||
| Supplemental Conditions.pdf | ||
| 1 Security Gates and Fencing Plans.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
POLICE STATION SECURITY FENCING
MEASUREMENT AND PAYMENT
For all Items - Unit and Lump Sum prices for each item shall be full compensation for overhead and profit, insurance, bonds, all labor, mobilization and demobilization, surveying, equipment, supplies and materials, tools, testing, inspections, and all incidentals necessary for a complete and operational facility.
Unit Prices
Chain Link Fence (203) - will be measured and paid for at the contract unit price per linear foot from center of each connection and based upon the actual length of fence excluding the width of the speed gates. the price shall include pavement saw cuts, excavation of any and all encountered material of whatever nature; dewatering; bedding, reinforced concrete, disposing of unsuitable material; and backfill.
Fence Removal (101) - will be measured and paid for at the contract unit price per linear feet for all existing materials and structures so designated for removal and will include demolition, disposal, and restoration.
Lump Sum Items
Allowance (204) – The Gate Foundation Modifications and other excavations will be paid as an allowance if such foundation depth, materials and unexpected rock is encountered. Such a differing condition will be paid as negotiated using actual costs to support the required foundation support.
Erosion and Sedimentation Controls (102) - will be measured and paid as a lump sum and shall include all labor, equipment and material to install, maintain, remove and dispose of required protection and final restoration.
Remainder of Work to Complete Project (301) – will be measured and paid as a lump sum to provide all additional or remaining materials, supplies, and incidentals, including the As-Built Survey, for a complete and operable facility as intended.
Speed Gates (201 and 202) - will be measured and paid for at the contract lump sum price and shall be full compensation for all materials, labor, tools, equipment and accessories noted on the drawings to complete the foundation and installation suitable for a complete and operable facility.
END
File details come from the government source that posted it. Updated .